Tugas AIT (MACRS, DCFROR Dan NPV)
Tugas AIT (MACRS, DCFROR Dan NPV)
C = 60 jt OP = 10 jt OP = 12 jt OP = 14 jt OP = 16 jt
Alat Lama :
0 1 2 3 4
OP = 40 jt OP = 42 jt OP = 44 jt OP = 46 jt
B–L
0 1 2 3 4
C = 60 jt S = 30 jt S = 30 jt S = 30 jt OP = 30 jt
Lanjutan Penyelesaian…
Jadi,
Lanjutan Penyelesaian…
Analisis Inkremental DCFROR
Interpolasi :
Lanjutan Penyelesaian…
NPV
NPV = PWrev – PWcost
= 21.429.600 (P/F 20%,1) + 23.877.400 (P/F 20%,2)
+ 22.197.600 (P/F 20%,3) + 28.495.200 (P/F 20%,4) –
60.000.000
= 61.026.738,32 – 60.000.000
= 1.026.738,32 (alat baru diterima)