Identify RISK
How do you get paid?
40
hours
35 B
30
25 C
20
15
10
100 200 300 400 500
Size of Project in Thousands of Dollars
A Simple project
B Medium complexity
C Difficult project
12
0
110
100 C
90
80
70
60
50
40
30
1.5 2.0 2.5 3.0 3.5
Size of Project in Millions of Dollars
A Complex
B Medium complexity
C Simple
Prof. Awad S. Hanna
Profit Should Correlate to Risk
Job Comparison
Compare two jobs of identical direct cost,
yet very diverse in overhead and risk
factor: Job “A” Job “B”
Material $200,000 $100,000
Labor 20,000 230,000
Subcontractors 100,000 10,000
General Expenses 30,000 10,000
Subtotal 350,000 350,000
Overhead @10% 35,000 35,000
Profit @10% 38,500 38,500
Selling Price $423,500 $423,500
5 5 6 6 5 5 7 7 7 5 5 4
1 2 3 4 5 6 7 8 9 10 11 12 week
12 weeks 65 labors
# labor
15 15
10 10
2 3 3 2 2 3 2 3
1 2 3 4 5 6 7 8 9 10 11 12 week
12 weeks 65 labors