BRGF, Phase-III, Part-II, (N-1) Compliance(Bay )

1. Name Of Work 132/33KV Transformer Bays (Hybrid ) at GSS at Gaighat(NIT-


97/PR/BSPTCL/2015).
2. Project Cost (Rs Cr) - 04.77
3. Agency - M/S ABN Towers & Transmission Pvt. Ltd., Kolkata
4. LOI Date - 10.06.2016
5. SDOC -09.12.2016
6. Likely Date of Completion -09.12.2016
7. Project Team -Sri Chittranjan Roy (ESE) ,Sri Ravi Shankar(EEE) & Sri M.K.Sharma(A.Ex.E)
Total Scheduled Actual Actual Payments (Rs Cr) Remarks
Qty (30.09.16) (31.08.16) (15.10.16)
Fund Fund Pending
Released for payment
Foundation(%) 100 50 NIL NIL Approval of foundation
drawing,CT, Foundation
Bolt,PT,Isolator,Power &
Control cable,BPI, Disc
Insulator 33 kv
VCB,hybrid module and
Moose Conductor are
done.

Supply of Structure(MT) 05 02 NIL NIL


Supply of Equipment (%) 100 40 NIL NIL DI of Cable rack, MS
rod, control cable and GI
flat are issued.

Erection Of Structure(MT) 05 -
Erection of Equipment (%) 100 -
Commissioning 100 -

Note:- work for dismantling of store shed started.