1. Name Of Work 132/33KV Transformer Bays (Hybrid ) at GSS at Gaighat(NIT-
97/PR/BSPTCL/2015). 2. Project Cost (Rs Cr) - 04.77 3. Agency - M/S ABN Towers & Transmission Pvt. Ltd., Kolkata 4. LOI Date - 10.06.2016 5. SDOC -09.12.2016 6. Likely Date of Completion -09.12.2016 7. Project Team -Sri Chittranjan Roy (ESE) ,Sri Ravi Shankar(EEE) & Sri M.K.Sharma(A.Ex.E) Total Scheduled Actual Actual Payments (Rs Cr) Remarks Qty (30.09.16) (31.08.16) (15.10.16) Fund Fund Pending Released for payment Foundation(%) 100 50 NIL NIL Approval of foundation drawing,CT, Foundation Bolt,PT,Isolator,Power & Control cable,BPI, Disc Insulator 33 kv VCB,hybrid module and Moose Conductor are done.
Supply of Structure(MT) 05 02 NIL NIL
Supply of Equipment (%) 100 40 NIL NIL DI of Cable rack, MS rod, control cable and GI flat are issued.
Erection Of Structure(MT) 05 - Erection of Equipment (%) 100 - Commissioning 100 -
Note:- work for dismantling of store shed started.