Introduction

 The purpose is to outline the planning of UI assignment for FTTH Network in


existing or new high-rise building without internal fiber cabling to support
High Speed Broadband Service.
 Currently there are 16 high rise building have been identified for pilot
project
 Network part until vertical installation will be done by AND
 Fulfilment part from DP until customer premise will be performed by Unifi
Installer (UI)
Vertical Design

 There are several type of vertical design proposed by AD


 To ensure smooth FTTH Network installation and HSBB Service provision in
future, permission from BM shall be obtained before proceeding with any
planning works. There are 2 options that can be proposed during
negotiation BM :
 BM to install the Internal Fibre Cabling at their own cost as for Greenfield
arrangement as explained in Technical Standards of In-Building Fibre Cabling For
Fibre-To-The-Premise (FTTP), MTSFB 002:2009 document or,
 BM to allow and agree for TM to install internal fibre cabling including to install a
new cable inside the vertical trunking, FTB or Fibre DP installation in riser room,
and installation of horizontal trunking and drop cable installation
 A proper agreement shall be prepared and signed off by BM and TM.
Vertical Design

Design 1 : Design 2 : Design 3 :


Internal cabling prepared by BM Internal Cabling Prepared by Internal Cabling Prepared by
TM with Tie DP at Every Floor TM with 2:32 Floor Fibre DP
Vertical Design (cont..)

Design 4 : Design 5 :
Internal Cabling Prepared by Internal Cabling Prepared by UI
TM with 1:8 Floor Fibre DP
Description for Vertical Design
Design # Description Application of suitable or criteria

Design 1 Internal Cabling Prepared by Greenfield building with pre-wired internal


BM fibre cabling by Properties Developer
Design 2 Internal Cabling Prepared by Internal fibre cabling by TM and pre-wired at
TM with Tie DP at Every Floor every floor with Tie DP
Design 3 Internal Cabling Prepared by Internal fibre cabling by TM and pre-wired at
TM with 2:32 Floor Fibre DP every floor with 2:32 Fibre DP
Design 4 Internal Cabling Prepared by Internal fibre cabling by TM and pre-wired at
TM with 1:8 Floor Fibre DP every floor with 1:8 Fibre DP
Design 5 Internal Cabling Prepared by Internal fibre cabling by TM and will be
UI installed as and when customer subscribe
Horizontal Design

 There are 3 design for horizontal


 BM will select type of work options before TM proceed with installation up to
customer’s premise
 For work option horizontal installation without trunking, distance
requirement between each U-clip as below:
i. 1m for white drop fiber with bearer
ii. 1ft for white drop fiber without bearer
Horizontal Design (cont.)
No Work Options Description Scenario

1 Normal drop fiber (PVC) will be installed Trunking already installed during network delivery
inside this without microduct

With Trunking
2 Normal drop fiber will be installed over the Installed in building that have access on the ceiling
ceiling with microduct

Over Ceiling
3 Normal Drop fiber (PVC) Option 1

For building without trunking, we will install new


trunking for internal wiring

White Drop Fiber Option 2

For building without trunking, we will install white


drop fibre with U-Clip
Without Trunking
Propose process for UI assignment
 Propose to have dedicated UI team for each HRF building
 Should the mapping of UI assignment as in matrix below

HRF 1 HRF 2 Other


zone
Team 1 X X
Team 2 X X
Team 3 X

 For interim, assignment of UI will be done manually by JCC based on the list
of dedicated UI provided by VDM
 For ultimate, we desire assignment of UI will be auto by SWIFT
Interim process for UI assignment
Ultimate process for UI assignment