SUMP ACTUAL &PLANNING PROGRES

PT. RAHMAN ABDIJAYA

Periods : Oct-Dec 2007


Sump Temporary Actual Per Oct 2007

Data Teknis Sump Temporary Actual PT. RA ;


1. Base Sump = +56
2. Area Sump = 2.984 m2
3. Capacity = 12.000 m3
4. Location ; Roof Coal (N. 14.100-14.200)

Pump Graphics Progress


66 4,500

64 4,000

3,500
62
Drainage line 3,000
60
2,500
58
2,000
56
1,500
Dinding sump 54
1,000

52 500

50 -
1/Oct
2/Oct
3/Oct
4/Oct
5/Oct
6/Oct
7/Oct
8/Oct
9/Oct

13/Oct

29/Oct
10/Oct
11/Oct
12/Oct

14/Oct
15/Oct
16/Oct
17/Oct
18/Oct
19/Oct
20/Oct
21/Oct
22/Oct
23/Oct
24/Oct
25/Oct
26/Oct
27/Oct
28/Oct

30/Oct
31/Oct
Base Level (m) (m) MUD Level (m) (m)
Sump Water Level (m) Critical Level (m) (m)
Pumping Volume (m3) Input Volume (m3)
Sump Temporary Actual Per Oct 2007

Base Act +56


Sump Temporary Actual Per Oct 2007

Sump (1 x MF420)
Q = 200 lt/s Act 56,
Plan RL 40until
Dec2007

sekatan Act +77.3

Outlet to SP 10
Beberapa rencana kerja di bulan November s/d Desember 2007 :
1. Pembentukan Dimensi Final sump di N. 14.100 E.6.500 dengan data :
Sump Progress Planning to End 2007 - Dimensi Sump = 75 x 75 m2
- Final elevasi = RL.+40
- Capacity sump = 36.000 m3
2. Perapihan slope sekitar sump
Sump Progress Planning to End 2007

Base RL +40
Sump Progress Planning to End 2007