CHANGE PROPOSAL
EVALUATION AND PREPARATION
CLAIM
• Time Schedule
• Scope
• Price
• Contract Conditions
• Time is money, Schedule is the most easily affected
element of the lumpsum contract baseline, because any
delay, acceleration, disruption, or distortion of
performance constitutes a change which may entitle the
Contractor and obligate the Employer to pay additional
compensation.
• The Contractor's right to obtain time related compensation
must be proven against the contract's ‘baseline’, which
should be accurate and verifiable with the contract scope,
schedule, and condition.
• A claim consisting of a request by the Contractor for
money or time, due to a change in any of the three basic
elements of the contractual baseline, given that each
change is beyond the control of the Contractor.
4. EVALUATION PROCESS
• Evaluation is the process of quantifying the amount or extent of
the additional costs sustained due to the breach, and establishing
that the subject losses were actually and properly sustained as a
result of the breach. As the Contract Price of the lumpsum
contract is equated to the elements of ‘baseline’
• Site Overheads
• Head-Office Overheads
• Profit
7. METHOD OF CLAIMS
• Global Claims
• The correct way of presenting a claim to the Engineer or
before a Court or Arbitrator is by using causation, i.e.,
rational and logical linking of the effect with the cause. If
the Engineer is 14 days late in issuing the drawings for
the foundations and as a result the completion of the work
is delayed by 14 days, will illustrate cause and effect
linkage.
• To avoid a great deal of argument over a global claim,
Contractors and Subcontractors establish the linkage
between cause and effect of every event, which may lead
to a claim, at the time of occurrence itself. As well as
producing the cause and effect matrix, it will be
appropriate to highlight major delaying events in the text
of the claim by making reference to progress of works and
effect on other trades.
TOTAL COST METHOD
• Introduction
• Contractual basis of the claim
• The details of the claim
• The evaluation of the claim
• Appendix
INTRODUCTION
• As the person, who is responsible for the final assessment may not
be totally familiar with the contract, it is important to give background
details in order to make the document a complete entity in itself. The
minimum required details should be as follows:
• Names of the parties to the contract and the consultants
• Details of the conditions of contract governing the contract
• Contract Signing Date
• Original Contract Price
• Commencement & Completion Date
• Details of EOT
• Details of Variation Orders
BASIS OF THE CLAIM
• It is important to state precisely about contractual basis of the
claim. The claim will fall under one or both of the following
categories:
• A claim for loss and expense or extra costs or expense flowing
from a remedy contained within the conditions themselves
• A claim for damages resultant upon a breach of the express or
implied terms of the contract or the law.
• It is essential to state clearly the event or events pertaining to the
claim. It is also good practice in this section of the claim to make
reference to notifications which have been made during the
contract.
DETAILS OF THE CLAIM
• In most cases the evaluation will fall into two sections, i.e.,
costs associated with prolongation and costs associated
with disruption. Methodology of heads of claim has been
described earlier in this Paper.
APPENDICES