0 penilaian0% menganggap dokumen ini bermanfaat (0 suara)
12 tayangan29 halaman
This document outlines the construction of a 4-storey building with a parking area at the ground floor level for the DPWH Davao City District Engineering Office in Davao City. It provides details on the location, estimated costs, project duration, scope of works, manpower, and progress photos for each month of the 8-month construction period. The project involved excavation, concrete work, installation of windows, doors, roofing, electrical systems, plumbing, tiles, and landscaping to complete the new office building.
This document outlines the construction of a 4-storey building with a parking area at the ground floor level for the DPWH Davao City District Engineering Office in Davao City. It provides details on the location, estimated costs, project duration, scope of works, manpower, and progress photos for each month of the 8-month construction period. The project involved excavation, concrete work, installation of windows, doors, roofing, electrical systems, plumbing, tiles, and landscaping to complete the new office building.
This document outlines the construction of a 4-storey building with a parking area at the ground floor level for the DPWH Davao City District Engineering Office in Davao City. It provides details on the location, estimated costs, project duration, scope of works, manpower, and progress photos for each month of the 8-month construction period. The project involved excavation, concrete work, installation of windows, doors, roofing, electrical systems, plumbing, tiles, and landscaping to complete the new office building.
AREA AT GROUND FLOOR LEVEL DPWH DAVAO CITY DISTRICT ENGINEERING OFFICE BUILDING (DCDEO), DAVAO CITY
ANTONIO, BERDERA, CALUGDAN, PELIÑO, SANCHEZ
CONSTRUCTION 4-STOREY WITH PARKING AREA AT GROUND FLOOR LEVEL DPWH DAVAO CITY DISTRICT ENGINEERING OFFICE BUILDING (DCDEO), DAVAO CITY
▪ Location : Davao City
▪ Estimated Project Cost : Php44,856,493.61 ▪ Source of Fund : SARO-SR2016-07-010062 ▪ Classification : Office Building ▪ Total Project Duration : 240 Calendar Days ▪ No. of pre determined unworkable days : 32 Calendar Days ▪ Project Status : Finished Project PERT CPM MONTHLY WORK PROGRESS 1ST MONTH – JANUARY 2018 SCOPE OF WORKS MANPOWER
▪ Mobilization ▪ 1- Project Engineer
▪ Project Billboard / Sign Board ▪ 1- Material Engineer ▪ Additional Geotechnical ▪ 1- Safety Officer Investigation ▪ 1- Foreman ▪ Occupational Safety & Health ▪ 2-Carpenter Program ▪ 10- Steelman ▪ Removal of Structures & ▪ 20- Laborer Obstruction ▪ Structure Excavation ▪ Embankment (Structure Excavation) ▪ Embankment (Borrow) ▪ Gravel Fill ▪ Reinforcing Steel G40 TOTAL COST FOR ITEMS ▪ Reinforcing Steel G60 ▪ Plain/Lean Concrete P 1,975,380.31 ▪ Structural Concrete (Footings, Footings Tie Beam) 1ST MONTH – JANUARY 2018 ACCOMPLISHMENT PHOTOS 2ND MONTH – FEBRUARY 2018 SCOPE OF WORKS MANPOWER
▪ Occupational Safety & Health ▪ 1- Project Engineer
Program ▪ 1- Material Engineer ▪ Embankment (Structure ▪ 1- Safety Officer Excavation) ▪ 1- Foreman ▪ Embankment (Borrow) ▪ Gravel Fill ▪ 10- Steelman
▪ Reinforcing Steel G40 ▪ 20- Laborer
▪ Reinforcing Steel G60 ▪ 10- Carpenters ▪ Structural Concrete ▪ Structural Concrete (Columns, TOTAL COST FOR ITEMS Slab on fill) P 3,956,633.10 ▪ Formworks & False work 2ND MONTH – FEBRUARY 2018 ACCOMPLISHMENT PHOTOS 3RD MONTH – MARCH 2018 SCOPE OF WORKS MANPOWER
▪ Occupational Safety & Health ▪ 1- Project Engineer
Program ▪ 1- Material Engineer ▪ Reinforcing Steel G40 ▪ 1- Safety Officer ▪ Reinforcing Steel G60 ▪ Structural Concrete ▪ 1- Foreman ▪ Structural Concrete (Columns, ▪ 10- Steelman Beams & Girders, Suspended ▪ 20- Laborer Slab) ▪ Formworks & False work TOTAL COST FOR ITEMS P 4,334,657.40 3RD MONTH – MARCH 2018 ACCOMPLISHMENT PHOTOS 4TH MONTH – APRIL 2018 SCOPE OF WORKS MANPOWER
▪ Occupational Safety & Health Program ▪ 1- Project Engineer
P 4,116,570.45 4TH MONTH – APRIL 2018 ACCOMPLISHMENT PHOTOS 5TH MONTH – MAY 2018 SCOPE OF WORKS MANPOWER ▪ Occupational Safety & Health Program ▪ 1- Project Engineer ▪ Reinforcing Steel G40 ▪ 1- Material Engineer ▪ Reinforcing Steel G60 ▪ 1- Safety Officer ▪ 1- Foreman ▪ Structural Concrete (Columns, Suspended ▪ 10-Steelman Slab, Beams & Girders) ▪ 15-Laborers ▪ Metal Structures (Structural Trusses) ▪ 7- Welders ▪ Corrugated Metal Roofing ▪ 7-Roof Installer ▪ Aluminum Metal Cladding ▪ Metal Pipe ▪ Metal Railings
TOTAL COST PER ITEMS
P 5,537,485.64 5TH MONTH – MAY 2018 ACCOMPLISHMENT PHOTOS 6TH MONTH – JUNE 2018 SCOPE OF WORKS MANPOWER ▪ Occupational Safety & Health Program ▪ 1- Project Engineer ▪ Fabricated Materials & Hardware ▪ 1- Material Engineer * Aluminum Windows ▪ 1- Safety Officer * Doors ▪ 1- Foreman *Steel Door ▪ 5- Electricians * Finishing Hardware ▪ 1- Team of Aluminum & Glass Installer ▪ Tile Works ▪ 6- Plumbers ▪ Metal Structures (Structural Trusses) ▪ 10- Tile Installers ▪ Corrugated Metal Roofing ▪ 5- Carpenters ▪ Aluminum Metal Cladding ▪ 7- Welders ▪ Metal Pipe ▪ 7-Roof Installer ▪ Metal Railings
TOTAL COST PER ITEMS
P 4,387,222.94 6TH MONTH – JUNE 2018 ACCOMPLISHMENT PHOTOS 7TH MONTH – JULY 2018 SCOPE OF WORKS MANPOWER
▪ Occupational Safety & Health Program ▪ 1- Project Engineer
▪ 1- Material Engineer ▪ Electrical Works ▪ 1- Safety Officer ▪ Plumbing Works ▪ 1- Foreman ▪ 5- Electricians ▪ Fabricated Materials & Hardware ▪ 1- Team of Aluminum & Glass Installer * Aluminum Windows ▪ 6- Plumbers * Doors ▪ 10- Tile Installers ▪ 5- Carpenters *Steel Door * Finishing Hardware ▪ Tile Works TOTAL COST PER ITEMS P 5,332,624.81 7TH MONTH – JULY 2018 ACCOMPLISHMENT PHOTOS 8TH MONTH – AUGUST 2018 SCOPE OF WORKS MANPOWER
▪ Occupational Safety & Health Program ▪ 1- Project Engineer
▪ 1- Material Engineer ▪ Demobilization ▪ 1- Safety Officer ▪ Electrical Works ▪ 1- Foreman ▪ 5- Electricians ▪ Fire Alarm ▪ 2- Fire Alarm Technicians ▪ 1-Team of Elevator Technicians ▪ Electrical Elevator
TOTAL COST PER ITEMS
P 6,372,705.40 8TH MONTH – AUGUST 2018 ACCOMPLISHMENT PHOTOS 4-STOREY WITH PARKING AREA AT GROUND FLOOR LEVEL
DPWH DAVAO CITY
DISTRICT ENGINEERING OFFICE BUILDING (DCDEO), DAVAO CITY