CONSTRUCTION OF 4-

STOREY WITH PARKING


AREA AT GROUND
FLOOR LEVEL
DPWH DAVAO CITY DISTRICT
ENGINEERING OFFICE BUILDING
(DCDEO), DAVAO CITY

ANTONIO, BERDERA, CALUGDAN, PELIÑO, SANCHEZ


CONSTRUCTION 4-STOREY WITH
PARKING AREA AT GROUND FLOOR LEVEL
DPWH DAVAO CITY DISTRICT ENGINEERING OFFICE BUILDING
(DCDEO), DAVAO CITY

▪ Location : Davao City


▪ Estimated Project Cost : Php44,856,493.61
▪ Source of Fund : SARO-SR2016-07-010062
▪ Classification : Office Building
▪ Total Project Duration : 240 Calendar Days
▪ No. of pre determined unworkable days : 32 Calendar Days
▪ Project Status : Finished Project
PERT CPM
MONTHLY WORK
PROGRESS
1ST MONTH – JANUARY 2018
SCOPE OF WORKS MANPOWER

▪ Mobilization ▪ 1- Project Engineer


▪ Project Billboard / Sign Board ▪ 1- Material Engineer
▪ Additional Geotechnical ▪ 1- Safety Officer
Investigation ▪ 1- Foreman
▪ Occupational Safety & Health ▪ 2-Carpenter
Program ▪ 10- Steelman
▪ Removal of Structures & ▪ 20- Laborer
Obstruction
▪ Structure Excavation
▪ Embankment (Structure Excavation)
▪ Embankment (Borrow)
▪ Gravel Fill
▪ Reinforcing Steel G40 TOTAL COST FOR ITEMS
▪ Reinforcing Steel G60
▪ Plain/Lean Concrete P 1,975,380.31
▪ Structural Concrete (Footings,
Footings Tie Beam)
1ST MONTH – JANUARY 2018
ACCOMPLISHMENT PHOTOS
2ND MONTH – FEBRUARY 2018
SCOPE OF WORKS MANPOWER

▪ Occupational Safety & Health ▪ 1- Project Engineer


Program ▪ 1- Material Engineer
▪ Embankment (Structure ▪ 1- Safety Officer
Excavation)
▪ 1- Foreman
▪ Embankment (Borrow)
▪ Gravel Fill ▪ 10- Steelman

▪ Reinforcing Steel G40 ▪ 20- Laborer


▪ Reinforcing Steel G60 ▪ 10- Carpenters
▪ Structural Concrete
▪ Structural Concrete (Columns, TOTAL COST FOR ITEMS
Slab on fill) P 3,956,633.10
▪ Formworks & False work
2ND MONTH – FEBRUARY 2018
ACCOMPLISHMENT PHOTOS
3RD MONTH – MARCH 2018
SCOPE OF WORKS MANPOWER

▪ Occupational Safety & Health ▪ 1- Project Engineer


Program ▪ 1- Material Engineer
▪ Reinforcing Steel G40
▪ 1- Safety Officer
▪ Reinforcing Steel G60
▪ Structural Concrete ▪ 1- Foreman
▪ Structural Concrete (Columns, ▪ 10- Steelman
Beams & Girders, Suspended ▪ 20- Laborer
Slab)
▪ Formworks & False work
TOTAL COST FOR ITEMS
P 4,334,657.40
3RD MONTH – MARCH 2018
ACCOMPLISHMENT PHOTOS
4TH MONTH – APRIL 2018
SCOPE OF WORKS MANPOWER

▪ Occupational Safety & Health Program ▪ 1- Project Engineer


▪ Reinforcing Steel G40 ▪ 1- Material Engineer
▪ Reinforcing Steel G60
▪ 1- Safety Officer
▪ Structural Concrete
▪ Structural Concrete (Columns, Beams & ▪ 1- Foreman
Girders, Suspended Slab) ▪ 10- Steelman
▪ Formworks & False work
▪ 20- Laborers
▪ 10- Carpenters

TOTAL COST FOR ITEMS


P 4,116,570.45
4TH MONTH – APRIL 2018
ACCOMPLISHMENT PHOTOS
5TH MONTH – MAY 2018
SCOPE OF WORKS MANPOWER
▪ Occupational Safety & Health Program ▪ 1- Project Engineer
▪ Reinforcing Steel G40 ▪ 1- Material Engineer
▪ Reinforcing Steel G60 ▪ 1- Safety Officer
▪ 1- Foreman
▪ Structural Concrete (Columns, Suspended ▪ 10-Steelman
Slab, Beams & Girders) ▪ 15-Laborers
▪ Metal Structures (Structural Trusses) ▪ 7- Welders
▪ Corrugated Metal Roofing ▪ 7-Roof Installer
▪ Aluminum Metal Cladding
▪ Metal Pipe
▪ Metal Railings

TOTAL COST PER ITEMS


P 5,537,485.64
5TH MONTH – MAY 2018
ACCOMPLISHMENT PHOTOS
6TH MONTH – JUNE 2018
SCOPE OF WORKS MANPOWER
▪ Occupational Safety & Health Program ▪ 1- Project Engineer
▪ Fabricated Materials & Hardware ▪ 1- Material Engineer
* Aluminum Windows ▪ 1- Safety Officer
* Doors ▪ 1- Foreman
*Steel Door ▪ 5- Electricians
* Finishing Hardware
▪ 1- Team of Aluminum & Glass
Installer
▪ Tile Works ▪ 6- Plumbers
▪ Metal Structures (Structural Trusses) ▪ 10- Tile Installers
▪ Corrugated Metal Roofing ▪ 5- Carpenters
▪ Aluminum Metal Cladding ▪ 7- Welders
▪ Metal Pipe ▪ 7-Roof Installer
▪ Metal Railings

TOTAL COST PER ITEMS


P 4,387,222.94
6TH MONTH – JUNE 2018
ACCOMPLISHMENT PHOTOS
7TH MONTH – JULY 2018
SCOPE OF WORKS MANPOWER

▪ Occupational Safety & Health Program ▪ 1- Project Engineer


▪ 1- Material Engineer
▪ Electrical Works ▪ 1- Safety Officer
▪ Plumbing Works ▪ 1- Foreman
▪ 5- Electricians
▪ Fabricated Materials & Hardware ▪ 1- Team of Aluminum & Glass
Installer
* Aluminum Windows ▪ 6- Plumbers
* Doors ▪ 10- Tile Installers
▪ 5- Carpenters
*Steel Door
* Finishing Hardware
▪ Tile Works
TOTAL COST PER ITEMS
P 5,332,624.81
7TH MONTH – JULY 2018
ACCOMPLISHMENT PHOTOS
8TH MONTH – AUGUST 2018
SCOPE OF WORKS MANPOWER

▪ Occupational Safety & Health Program ▪ 1- Project Engineer


▪ 1- Material Engineer
▪ Demobilization ▪ 1- Safety Officer
▪ Electrical Works ▪ 1- Foreman
▪ 5- Electricians
▪ Fire Alarm ▪ 2- Fire Alarm Technicians
▪ 1-Team of Elevator Technicians
▪ Electrical Elevator

TOTAL COST PER ITEMS


P 6,372,705.40
8TH MONTH – AUGUST 2018
ACCOMPLISHMENT PHOTOS
4-STOREY WITH
PARKING AREA AT
GROUND FLOOR
LEVEL

DPWH DAVAO CITY


DISTRICT ENGINEERING
OFFICE BUILDING
(DCDEO), DAVAO CITY