Power Station.
Assessment of Kwh Generation Daily,
monthly, yearly in aspect of 20 Years total
kwh generation auditing and Determination
of kwh generation costing.
Solar Module
Generator
Bi Battery
On Grid Multicluster
Directional Bank
Inverter Box
Inverter
DB Box PFI
Feeder Load
04. Auditing daily saleable kwh from battery output, the As per research on
output capacity of the Batteries (70-78%), so, (332×78%)=259 practical application
Kwh per day (useable for the Consumers) = 259 kwh
05. Daily achievement of total kwh generation of the plant As daynight actual
At day & night total Kwh (3+4)=226+259 = Kwh auditing 485 kwh
06. Technical Losses of different system : = By BPDB 13%
a) DC to AC Conversion Loss + Inverter Equipment Loss +Technical &
Loss of Distribution Line etc. total-6% As per Research on
b) Self Consumption of the Project-4% Practical Application
c) Auditing Yearly losses of Diversity Factor (Load Factor & By BPDB
Generation loss) =20% (Achievement 80%) =
Achievement 60%
Exp: About 50% of total saleable Kwh will not be used by the &
consumer during winter season (i.e. 120 days per year) and average As per Research on
daily generation non use something Kwh etc. everything considering to Practical Application
the diversity factor.
d) According to the instruction of the manufacturer of the panels, the By Manufacturer IDCOL
panels will be 10% depreciated after 10 years that is average 5% in view Specification showing
of 20 years. & their
So, Total loss-(A+B+C+D)=6+4+20+5=35% As per Research on Model-
i.e. 485*35%=170Kwh = the basis Practical 170 Kwh 652 Kwh,
Application /day, which
07. The daily actual Receivable & Saleable unit (Kwh), is
(485-170)= 315 kwh = 315 Kwh unrealistic
08. Actual saleable Kwh during 20 years aspect (Kwh), [315×365×20] = 2299500 Kwh
09. @ BDT 30 per Kwh, total amount of saleable kwh during 20 Years = By IDCOL FM BDT 6,89,85,000/-
10. Monthly Service Charge, Average 500 Consumers during 20 Years By IDCOL FM BDT 75,60,000/-
(500×70×12×18) =
Total Income of 20 Years Grand Total= BDT 7,65,45,000/-
IDCOL MODEL
Supply from Battery (6PM to 7 AM)
319kWh
Battery Depth of Discharge
0.50
Minimum Required Capacity of the Battery (2V, 50% DOD) 319,069Ah
Minimum Number of Batteries (2V, 1540 Ah) 208
Number of Battery Racks (considering 48V System) 9
Next suitable number of battery banks / racks 9
Battery Capacity (2V)
332,640Ah
Number of Batteries
216
Supplying Capacity of Batteries
333kWh/day
Total= 652KWh/day
Total generation expenses in aspect of 20
years with equipment change, repair
maintenance and management expenses etc.
Sl. Particulars Reference Amount (Tk.) Remarks
No
01. Project Cost (Initial Project Cost) By IDCOL FM BDT 6,83,95,033/-
02. BDT 52,00,000/-
Due to under design & insufficient BOQ additional cost
a) such as L.T Switchgear, P.FI Board, Earthling of distribution line,
Lightning arrester of distributer line, arrester of panel lighting, arrester of PWD RCC
equipment lighting, all around lighting of plant, building wearing, building
Design and BOQ of construction
arrangement of water supply, sanitary fittings, bath tiles fittings, coloring of
Monpura Solar Mini schedule rate is
building & boundary, different type of tools & Instruments purchase ,such as- grid which did not BDT 2700/sft
Chainpuli, raset, chainkoppa, tools box, Ladder, carrier, Pliars cliponameter, follow the Building whereas
Code, Electrical Monpura
avometer etc. all of the plant management equipment purchase
Design Manual & building
b) Building construction section additional Cost 20%(Annexure) adding due The Electricity Act. construction
to under estimated of building materials & construction cost because the same 1910. schedule rate of
same size
size building construction cost of PWD is BDT 2700/sft & IDCOL rate for
building is only
monpura building cost is only BDT 1200/sft.Total additional BDT 1200/sft.
expenses=52,00,000.00 for above mentioned reason was expensed for
limitation of BOQ & project design.
03. 2 times Battery change in aspect of 20 years By IDCOL FM BDT 2,95,00,000/-
04. Inverter, charge controller and related all equipment & connector etc in aspect By IDCOL FM BDT 1,75,00,000.00/-
of 20 Years Cost minimum 1 time
05. During aspect of 20 years building, distribution line, boundary & etc.
maintenance costing will be needed
Explanation:
a) General repair & structure coloring, building boundary wall etc.
yearly repair work at every 2years- 4,00,000*9= 36,00,000/-
b) Every year distribution line repair ,pillar change & line re-tensining As per Building
etc. all of the repair expenses per year 1,40,000= Code, Electrical
1,40,000*18=25,20,000/- Design Manual,
The Electricity
c) Every year trimming 50,000*18=900,000.00
Act. 1910.
d) The total cost of major repairing for damage building, boundary wall
etc. due to salvage for every 7 years 20,00,000*3 times=60,00,000.00)
e) During 20 years 100 pillar may be damage for any reason. So, its
will be purchase ,whose price 100*20,000=20,00,000/-
TotalCost+(a+b+c+d+e) = 15,020,000/-
BDT 1,50,20,000/-
Total production by generator in 18 years =2,72,160 unit & Generator As per research
on practical
will generate 41 unit electricity per hour & Generator will be service per
application
150 hours.
So, To generator will be service 47 times in 18years, per service cost with
related goods Tk.12,000/- 12,000*47 =
12 Total expenses of plant in aspect of 20 years BDT 24,84,96,914/-
13 Depreciation:
a) The sales value of land & building excluding salvage value after 20 BDT 30,00,000/-
years
b) Total sales value of related battery & all installation excluding salvage BDT 70,00,000/-
value
c) Total salvage value BDT 100,00,000/-
14 Total cost in 20 years (24,84,96,914-1,00,00,000) BDT 23,84,96,914/-
15 Total sales of Kwh & others in aspect of 20 years, ( Sl. No -8, Page-3) 2299500 Kwh
16 Per Kwh generation cost will be(23,84,96,914/2299500) =BDT 103.71 Actual Kwh BDT 103.71
in aspect of 20 years project lifetime generation Cost
17 The entrepreneur loss As per research on Entrepreneur
in aspect of 20 years of project lifetime (Total cost BDT practical Total Loss in
23,84,96,914-Total income BDT 7,65,45,000)= Total Application BDT 16,19,51,914/- aspect of 20
& years lifetime
Loss 16,19,51,914/- due to wrong design, BOQ,
on basis of
Unrealistic & imitation model. Actual Expenses