Learning Objectives
Describe the conditions under which MRP
is most appropriate.
Describe the inputs, outputs, and nature of
MRP processing.
Explain how requirements in a master
production schedule are translated into
material requirements for lower-level items.
Discuss the benefits and requirements of
MRP.
Learning Objectives
Explain how an MRP system is useful in
capacity requirements planning.
Outline the potential benefits and some of
the difficulties users have encountered with
MRP.
Describe MRP II and its benefits.
Describe ERP, what it provides, and its
hidden costs.
MRP
A Dependent Demand
B(4) C(2)
Demand
Demand
“Lumpy” demand
Stable demand
Time Time
Amount on hand
Amount on hand
Safety stock
Time Time
Overview of MRP
MRP Inputs MRP Processing MRP Outputs
Changes
Order releases
Master
schedule Planned-order
schedules
Primary
reports Exception reports
Bill of Planning reports
materials MRP computer Secondary
Performance-
programs reports control
reports
Inventory
records Inventory
transaction
MPR Inputs
Assembly
Subassembly
Fabrication
Procurement
1 2 3 4 5 6 7 8 9 10
1 Leg Back
Assembly Seat Assembly
Level
0 X X
1 B (2) C B (2) C
Available Inventory:
Available Inventory = Projected on hand
– Safety stock
– Inventory allocated to
other items
Assembly Time Chart
Procurement of
raw material D Fabrication
of part E
Subassembly A
Procurement of Final assembly
raw material F and inspection
Procurement of
part C
Procurement of
part H
Subassembly B
Procurement of Fabrication
raw material I of part G
1 2 3 4 5 6 7 8 9 10 11
Time-Phased Product
Structure
Must have D and E
completed here so
Start production of D production can
begin on B
Lead time
1 week
D (2)
2 weeks to A 1 weeks
produce
B 2 weeks
B (2)
2 weeks C 1 weeks
E (2)
A D 1 weeks
2 weeks 1 week E 2 weeks
2 weeks
E (2)
1 week
F 3 weeks
G (1) C (3) G 2 weeks
3 weeks
F (2)
1 week
D (2)
| | | | | | | |
1 2 3 4 5 6 7 8
Time in weeks
Gross Requirements Plan
Week
1 2 3 4 5 6 7 8 Lead Time
A. Required date 50
Order release date 50 1 week
B. Required date 100
Order release date 100 2 weeks
C. Required date 150
Order release date 150 1 week
E. Required date 200 300
Order release date 200 300 2 week
F. Required date 300
Order release date 300 3 weeks
D. Required date 600 200
Order release date 600 200 1 week
G. Required date 300
Order release date 300 2 week
Net Requirements Plan
Net Requirements Plan
MRP Processing
Gross requirements
Schedule receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases
MPR Processing
Gross requirements
Total expected demand
Scheduled receipts
Open orders scheduled to arrive
Projected on hand
Expected inventory on hand at the
beginning of each time period
MPR Processing
Net requirements
Actual amount needed in each time period
Planned-order receipts
Quantity expected to be received at the
beginning of the period
Offset by lead time
Planned-order releases
Planned amount to order in each time
period
Lot-Sizing Techniques
Lot-for-lot techniques order just what
is required for production based on
net requirements
May not always be feasible
If setup costs are high, costs may be
high as well
Economic order quantity (EOQ)
EOQ expects a known constant
demand and MRP systems often deal
with unknown and variable demand
Lot-Sizing Techniques
Part Period Balancing (PPB) looks at
future orders to determine most
economic lot size
EPP = setup cost / holding cost
Programming technique
Assumes a finite time horizon
Effective, but computationally
burdensome
Lot-for-Lot Example
Week 1 2 3 4 5 6 7 8 9 10
Gross
35 30 40 0 10 40 30 0 30 55
requirements
Scheduled
receipts
Projected on
35 35 0 0 0 0 0 0 0 0 0
hand
Net
0 30 40 0 10 40 30 0 30 55
requirements
Planned order
30 40 10 40 30 30 55
receipts
Planned order
30 40 10 40 30 30 55
releases
Total
Gross cost = $3,798 /year
35 30 40 0 10 40 30 0 30 55
requirements
Cost for 10 weeks = $3,798 x (10/52) = $730
Scheduled
receipts
Or
Projected on
35 35 0 0 0 0 0 0 0 0 0
hand
Total
Net cost = setup0 cost
30
+ 0holding
0 7
cost
0 4 0 0 16
requirements
Total cost = 4 x $100 + 318 x ($1 /weeks)
Planned order
Total
receiptscost = $718
73 73 73 73
Planned order
73 73 73 73
releases
Lot-for-lot $700
EOQ $730
PPB $490
F
Week
9 8 7 6 5 4 3 2 1 0
Accumulative production
Balancing chart
Target Plan
J F M A M J J A S O N D A B C D E F G H I J K
Resource Requirements Profile
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8
Period Period
(a) (b)
Smoothing Tactics
1. Overlapping
Sends part of the work to following
operations before the entire lot is complete
Reduces lead time
2. Operations splitting
Sends the lot to two different machines for
the same operation
Shorter throughput time but increased setup
costs
3. Lot splitting
Breaking up the order into smaller lots and
running part ahead of schedule
Other Considerations
Safety Stock
Lot sizing
Lot-for-lot ordering
Economic order quantity
Fixed-period ordering
MRP in Services
Market Master
Finance Manufacturing production schedule
Demand
Rough-cut Capacity
capacity planning planning
Adjust
production plan
Yes No Requirements No Yes
Problems? schedules Problems?
ERP