Tie Tie
Tie
a) Floor carrying horizontal forces from wind by beam action b) Floor carrying horizontal forces from wind by virendal action
RW CCIP-030
Check the design of the hollowcore diaphragm, without structural topping, carrying wind load to
walls at each end, as shown below.
Edge beam
vs vs
Hollowcore
unit
vs A vs
KEY
vs - Very smooth surface
s - Smooth surface
Section A - A
Hence:
and:
This check demonstrates that Exp. (6.25) is not usually a limiting control.
The design would now normally continue to calculate the tensile steel required in the edge beam to
carry the diaphragm tensile boom force, taking into account that this calculation must also
consider the other actions for the appropriate combination of actions.
Interface 3 Interface 2
Interface 4
Interface 1
RW CCIP-030
Consider Example 13.7 in the Precast Eurocode 2: Design Manual24. Interface shear check is between
the edge beam and in-situ concrete provided in the joint (see figure). In this example the contribution
of the horizontal surface is ignored. The shear resistance of the interface between the upstand of
the precast unit and the main body below should also be checked.
Shear interface
200
In-situ concrete
The flange over each hollowcore is cut out and therefore the units should be temporarily propped.
1 No. H16 U-bar is placed in each void to interlock with projecting reinforcement in the edge beam
as shown.
Assume that the compression flange of the edge beam is 600 + 175 + 110 = 885 mm wide.
h1
h2
Gradual detensioning
mechanism Unit moulds or continuously
Stressed strands extruded units
Calculate the effect of differential shrinkage in a beam constructed in two stages as shown below.
The element is simply supported and 20 m span. The free differential shrinkage strain is 0.0002.
B785 mesh
1000
100
50
B283 mesh
Precast concrete
150
Movement
Friction can
cause cracking
Rotation
Rotation
Rotation can
cause spalling
d2 > a1 + a3 c3
r3
r2
c2 > a1 + a2 d3
> a2 + a3
b1
a a1
a2 + a2
a3 + a3 1
a
RW CCIP-030
A 1.2 m wide hollowcore slab seated on an in-situ concrete nib, treated as a non-isolated member.
The length of hollowcore unit is 9 m. The in-situ concrete beam is class C35/45 concrete.
Table 4.2
Table 4.3
Table 4.4
The reinforcement in the in-situ concrete nib is assumed to be 20 mm vertically bent with a
nominal cover of 20 mm.
= 20 + 15 + 3.5 x 20 = 105 mm
The bearing stress should also be checked for the hollowcore unit.
20
H20 bar
10 30 105
20
Chamfer option Lowered support area option
The precast skins are
connected and spaced
by steel lattice
Lattice reinforcement
In-situ concrete
Vertical reinforcement
Slab reinforcement
In-situ concrete
Tie reinforcement
Decide which side props
should be positioned
Consider tolerances
for starter bars
Use of U-bars or links recommended
to ensure reinforcement remains
in correct position during concreting
In-situ
concrete
Lattice
Precast
concrete
slab
Main steel
Distribution steel
Hole grouted before
Grouting ring
placing column
40 mm
h/2
Normal limits to
placing of tie bar
h/2
a) Edge support b) Intermediate support
In-situ concrete
In-situ
concrete
Double tee
a) Standard double tee support b) Support of double tee with full continuity.
with welded connection Note: Temporary support of beam may be required
Strut and tie (1) Strut and tie (2)
Reinforcement and anchorage provided for struts and tie layouts 1 and 2
Strand must be
present and must
not be debonded
Only additional reinforcement for the mechanism of strut and tie is shown.
This figure is to be read with Figure 5.32
Tie
Strut
Double tee
Tie
Screed
H12 bar
Screed
H12 bar
10
90 15
100 min
100 min
15 90
15 90
90 min
10
100 min
15 90
375 15
15 375
120
35 Screed
40
70
120
Screed
375 15
15 375
RW CCIP-030
Consider a 1.5 m wide stair flight spanning 4 m, with a vertical spacing between precast units of 10 mm
permanent action of the stair flight.
where
Hence:
and
Structural
reinforcement
Temporary 2 way
braced props
HEd aH
Ftd
ac’
z0
d hc
x
RW CCIP-030
is assumed to be 45 mm. The width of the corbel is 300 mm, other details are as shown below.
300 kN bc = 300
175
160
60 kN
Ftd
45
605
Z0
605 650
o
67.64 Z
400
x/2
y
300
x = 120
Note: Further iteration could be carried out to maximise the strut efficiency.
RW CCIP-030
Use 5 H8 links
See the figure below for layout of reinforcement in accordance with The Standard Method of
Detailing Structural Concrete32.
2 H20 bars
H32 bar
5 No
H8 links
db
FEd
Zb ac
Ft2d
HEd
Ft1d
Zn
Tension lap
Qk,c Construction
Resisting 1.15* Gk,b
Resistance
beam
Gk,f floor
Gk,b
* Check that using a factor of 1.0 for both favourable and unfavourable
does not give a more unfavourable effect
a) Separate support systems can cause cracking in precast unit. b) Common support of precast floor and insitu beam.
Structural slab Floor finish
50
300
100
60
440 1500
Permanent formwork
Stub columns
& acoustic insulation
550
Diagrid beams
300
1800
The concept wheel Structural organisation
Ceiling
extract
Supply
Extract
Floor finish Air supply, electrical services and communications
300
950
150 650
250