ISAP Components
Road Sector Institutional Development
Odisha Roads Asset Management System
IT-ICT-MIS Implementation Strategy, formulation, solution architecture
GAAP Components
ISAP Action Plan based on ISAP Matrix
2008-18
The ISAP action plan is finalized under 3 major components
Sector Strategy
organization and Management
Human Resources Development and Capacity Building
A. Road Sector Institutional Development
RSID Consultantancy Services
Name :-Intercontinental Consultants and Technocrats Pvt. Ltd- in JV with M/s GT-APL in association with
ARKITECHNO Consultants(I) Pvt. Ltd
Period : - Date of Commencement : 9th April 2012; (duration- 30 Months) Date of Completion : 9th Oct 2014
Payment made till 12.05.2015:- 78% of Contract Value [ INR 7,05,36,180/- and US$ 4,95,378/-
Plus applicable ST (Exclusive of any taxes any deductions)
EoT granted till : 31.05.2015 for making the contract live for completion of balance tasks under the Contract
Progress/ Status :- Deliverables submitted as per contract agreement. Two stake holder’s workshop conducted. One
Workshop-cum-High Level Meeting conducted for Future Road Sector Institutional Options.
Exposure visits to outside States organized.
Sl. RSID Component/ Current Status Way forward actions
No. Tasks
1 Code and Manuals Revised OPWD Code and New OPWD Manual Approved by - Revised OPWD Code and new OPWD Manual shall have to be deliberated
ISAP Review Committee and Bank. Consultants also in the Code Revision Committee Meeting for further refinement and
submitted the SBDs and Procurement Manuals for Works, approval by Law and Finance Dept.
Goods and Services.
- Procurement Manuals and SBDs for Works, Consultancy Services and
Goods have been submitted and to be further deliberated at next Code
Revision Committee and finalized in coordination with Law and Finance
Department.
2 Odisha road sector OWD shared the Report to other stakeholder - The Suggestions from Stakeholders Department need to be incorporated
Policy Department for suggestions. Draft Highway Act/Bill 2015 suitably prior to placing for approval by Govt.
submitted by RSID Consultant .
- OSTM integration for finalization of Road Sector Policy.
- Road Policy shall be in line with Transport Policy of the State/ GoI.
3 Draft Road Safety OWD shared the Report to other stakeholder - After obtaining suggestions from other stakeholder departments, the
Action Plan (RSAP) Department for suggestions. same shall be updated in coordination with Transport Department.
Implementation
- OWD to prepare an action plan for the Department as required.
4 Approval of Setting up of HRD • The Resolution on HRD Policy for Works - Works Department to Notify the creation of Training & HRD Cell under
& Training Cell Department has been approved by E.I.C.(Civil), Odisha
Government in April 2015 and sent to
Gazette for its publication along with wide - Separate Budgetary allocation for Training & HRD activities.
circulation by OWD.
• HRD Policy for Works Department- 2015 - Hiring of HRD &Training Experts as per WB Guidelines
approved , Revised Training Plan submitted
and approved by Bank and ISAP Review
Committee.
5 Implementation of As per observations of CS, Odisha in a - Consultant’s recommended actions focused broadly on (a) strategic
Recommendations in Meeting on Road Network Master Planning corridor/ road improvements,(b) RNMP integrated with Road Policy &
Completion Report on in September 2015, the ORSAC have been (c) Institutional Development perspective need to be considered by
Inaugural Master Planning for assigned the task of providing GIS Maps of OWD/GOO.
Main Road Network of Odisha GP HQ connectivity networks (Block-wise).
- Delivery of updated ORSAC GIS Map for GP Level connectivity is under
Executive Engineer Planning and Asset process. After receipt of the same, verification of proposed roads (its
Management has entrusted to look after the day length, ownership etc) shall be verified and taking over process of
to day operations/ functions of the Cell/ Unit with recommended 20,000 KM VR for up gradation to minimum ODR Standard
inadequate support staffs. shall be initiated.
6 Reorganisation & Strengthening Short-to-medium Term Working Paper Report, - The Restructuring of Top Level Posts EEs and above upto the Level of
of OWD approved by ISAP Review Committee. E.I.C need to be finalized based on emerging additional functions and
responsibility .
Sl. No. RSID Component/ Tasks Current Status Way forward actions
7. Draft & Final Report on Draft Report approved by 9th ISAP Review - Actions to be taken based on Bank’s observation in Oct 14, March 2015
Medium-to-Long term Committee. & April 01, 2015.
Institutional Framework for
Road Sector Workshop-cum-High Level GOO for future - GoO final restructuring Framework on Road Sector to be notified which
institutional framework / structures of Roads shall be part of Final Institutional Report.
sector convened on 12th May 2015.
- Establishment of ORDC with merger of OB & CC Ltd was the viable
options in the Workshop.
- HRD & Training Cell, Road Safety Engineering Cell, Road network
Master Planning Cell, Policy and Planning Cell of OWD , Legal Cell , IT
Wings of OWD shall function dedicatively with adequate Staffings and
detailed operational guidelines and relevant codal provisions shall
have to be made like e-procurement system functioning in the State.
8. Implementation of Vehicle The Consultant’s recommendation in Vol-III - Recommendations are to be implemented by Govt. in consultation
Axle Load Regulation & Revised Report has been shared and reviewed with Stakeholder agencies like Transport Department.
Management by Bank and ISAP Review Committee.
9. Study of Main Road Funding Approved by ISAP Review Committee & - Consultant’s recommended action shall be reviewed and finalized for
Options Bank. final GOO- decision making .
10. Report on Road Toll Collection Revised Toll Report approved by ISAP Review - The Consultant have submitted the proposed work plan for conducting
and Maintenance/ Operations Committee and the World Bank. a Pilot Project on Toll Plaza Migration from existing Manual Type to
Automatic and Semi-Automatic Types which need to be deliberated
and reviewed.
Pending Tasks need Consultant’s Services beyond May 2015
Legal Assistance for many Policies, action plans like Road Policy, Road Safety Action
Plan, Finalizing PPP Policy for State Road Sector with State specific MCA document
Draft revision of of OPWD Code and Manual, SBDs etc
Drafting of Axle Load Control Policy for Transport Department
Development of Training Syllabus for HRD & Training Cell
Consultant’s Proposal vis-à-vis ISAP Cell’s observation
Department have an observation and appeal to complete all tasks/ activities pertaining
to contract agreement. And for implementation support for Post-RSID activities can be
taken up, which must have been all reflected in the DFR stage.
It is requested to grant EoT up to 4-6 months up to October 2015 to accomplish tasks on
Axle Load Control Policy, Piloting Support implementation for Tolling and Vehicle Axle
Load etc.
B. ODISHA ROAD ASSET MANAGEMENT SYSTEM
Name :- LEA Associate South Asia Pvt Ltd, (LASA), India, in joint venture with LEA International Ltd
(LEA), Canada and in association with Geo Infospace Private Limited (GIPL), India as sub-consultant
Period :-DoC: 05th May 2011 Original Duration- 36 Months, extended till 15th June, 2015
Consultancy Price :-US$ 560,117 and INR 16,07,63,517/- exclusive of ST& Cess
Payment made till 12.05.2015 : 89% of Contract Value [INR 14,15,34,189/- and US$ 5,34,279/- +
applicable taxes]
Sl. Category of Road Length as per Links Length No. of Culverts No. Bridges
PWD Book of
A/c
1 Project Plan for Project Plan submitted by Consultant in August, 2014 - NIC has been requested to take up the
remainder of project, along with the Extension proposal till May, 2015 was Software Audit and Security Audit based
with a view to OWD shared with Bank during August 2014 Mission. on the Design Report submitted by the
taking ownership of the Consultant.
RIS and PMS by end of The Following Tasks are pending as of 15 Apr, 2015. - Draft Acceptance Test Formats shared
October 2014, and with Bank for their review. After Bank’s
completion of the AMS 1. Software Audit of components of O-RAMS comments formal Testing can be
consultancy by early 2. Security Audit of O-RAMS before migrating to conducted.
May 2015. State Data Centre. - Implementation Support for a period of
3. Acceptance Tests of O-RAMS and formal handing one year is necessary.
over to OWD. - Proposal for exposure visits has to be
4. Implementation Support for 1 year initiated from the Consultant.
5. Submission of Final Manuals
6. Exposure Visits to Other States for two groups ( 8
Persons)
7. 2nd International Exposure visit
Sl. Asset Management Current Status Way forward actions
No Component/ Tasks
.
2 Data Collection Strategy Data Collection Strategy prepared by - Proposal for Automated Data Collection by CRRI
including indicative Consultant and shared to World Bank for is under review of the Govt.
costing, for bringing O- Review.
RAMS up to complete - GIS referencing of newly declared ODRs has
operational status, and been entrusted to ORSAC.
then for future
sustainability.
- Executive Engineers has been requested to
update the inventory data of roads, bridges
and culverts under their jurisdiction.
Necessary hands-on training is also been
imparted.
3 Implementation Plan for Implementation Plan prepared by Consultant - EE, Planning has been entrusted the assignment
OWD to take ownership of has been shared with Bank. of AMS.
O-RAMS.
Sl. Asset Management Current Status Way forward actions
No Component/ Tasks
.
4 Staffing Plan for Asset Staffing Plan prepared by Consultant has - AMS Cell now has 1 AEE and 1 JE.
Management Unit (Based been shared with Bank. The AMS Cell - 1 AEE positioned for RNMP and 1 AEE looking
on the detailed require the following personnel to operate after ISAP are also associated for future
Implementation Plan and the AMS. requirements.
Skills Requirements to be 1. 4 AEE for Pavement Management & - 2 IT Specialist, 1 Network Engineer and 2 GIS
submitted by AMS Traffic Operators have been hired through NICSI.
Consultant). 2. 2 AEE for Bridge Management - Hiring of minimum 6 Graduate Civil Engineers
3. 2 IT Specialists is necessary for Data Collection Quality
4. 2 GIS Operators Assurance, Processing of PMS & RMMS to
5. 1 Network Engineer generate Maintenance Plans for subsequent
years.
C. IT-ICT-MIS Strategy, Solution Architecture in OWD :
IT-ICT-MIS Consultant:
The Draft Strategy Report along with revised cost estimate of Rs. 43.91 Cr spanning 3 years
have been submitted to Govt. placing before ISAP Steering Committee and approval for the
same is kept pending.
Revised Costing details shall have to be shared with the Bank team with an assessment of
provision of dash board mechanism including Environmental activities on road corridors, Road
Safety aspects and Utility shifting for better Monitoring .
Enhancement in e-Nirman , e-procurement , CHS and WAMIS modules and its integrations.
Finalization of a Dedicated IT-Wing/ Cell for monitoring, guiding, looking after the smooth
functioning of IT activities of OWD at HQ , Hiring of outsourcing Staffs have been proposed in
the strategy report.
Industry level participation in a Stakeholder Workshop in June 2015 to finalize procurement
standards
Procurement of SIs by PMC through SLAs with a joint venture partnership between Hardware
and software vendors.
Road User Satisfaction Survey (RUSS)
Mid-Term RUSS survey from 1st April 2015 initiated by M/s MDRA.
RUSS Review Committee has been convened on 25th April 2015 and approved
the Baseline RUSS Report, Executive Summary on findings on Base-line RUSS
assessment.
Balance Payment of Baseline phase is being released soon.
Baseline RUSI Index : Overall Road User Satisfaction Index 2.38 out of 5 point
scale.(Six Road Corridors : OSRP Packages + 2 Odisha Roads)