Considerations &
Construction Aspects
• Excavation support
• Good for restricted access
• Eliminate mult.
mobilizations
Case I
Typical Applications Micropiles
Structural Support
Repair/
Arresting/ Upgrading of
Scour Replacement
Prevention Foundation
Protection of Existing
of Movement Capacity
Foundations
Case II
Design Use Micropiles
• Settlement
Control
• Underpinning
of structures
• Ground
strengthening
• In situ
Reinforcement
• Slope
stabilization
Case II
Typical Applications Micropiles
In-Situ
Reinforcement
Slope
Stabilization Ground Settlement Structural
And Earth Strengthening Reduction Stability
Retention
Types and
Installation Process Notations
Pressure Gauge
Packer
• Geotechnical Component
• Design similar to conventional piling and anchor systems
• Most critical component is grout-to-ground bond
• Bond is affected by
• In situ conditions - geology, groundwater conditions
• Construction process - drilling operations, hole cleaning,
grouting,
grout quality
Axial Loading –
Design Considerations Compressive or Tensile
• Design is similar to drilled shafts and ground anchors
• Interface shear strength (or ground-to-grout bond)
• Based on presumptive bond strength values (e.g., in FHWA) or
based on experience
• Allowable stresses in grout and steel are straight forward
• Challenges
• Interaction and transition between different cross sections
• Strain compatibility
• Between various steel materials (rebar and casing) and
cementitious grout
Structural Design
Design Considerations – Axial Loading
• Assume concentric axial
loading
• Assume fully composite
cross section
• Pc,ult=f(Pcasing+Pbar+Pgrout)
• Pb,ult=f(Pbar+Pgrout)
Bearing Plate
Stiffener
Structural Design
Design Considerations – Pile Cap Connections
• Connection strength research (Gómez and Cadden, 2006)
Dilation Effect
Structural Design
Design Considerations – Strain Compatibility
• Micropile - a composite element (casing, bar, grout)
• Concept - have the composite pile’s materials share a
common strain level at failure (ef)
• For unconfined concrete: ef = 0.3% (assume same for grout)
• For steel (bar and casing), to have ef = 0.3%:
Fy,max = (ef)(Es) = (0.003)*(29,000 ksi) = 87 ksi
• Cannot use steel with Fy > 87 ksi!
• Precludes use of Gr. 150 bars
1. 2. 3. 4. 5.
Single Tube Rotary Duplex Rotary Percussive Rotary Percussive “Double Head” Duplex 6.
Advancement Concentric Duplex Eccentric Duplex Hollow-Stem
(End of Casing Auger
Flush)
Tension
Load Test
Lateral
Load Test
Deformation
Instrumentation
Quality Control / Quality Assurance
• Specific areas to concentrate to ensure a well-run QC/QA
program
• Pre-construction meeting(s)
• Field Inspection
• Load testing program
• Reporting and documentation
Pre-Construction
QC / QA Program Tasks and Concerns
• Meeting(s) – some may be same person/company
• Engineer, Micropile Design Engineer, Prime Contractor,
Micropile Specialty Contractor, Excavation Contractor,
Geotechnical Instrumentation Specialist, Inspection Firm
• Discussion Topics
• Project requirements
• Construction procedures
• Contract documents and layout
• Reporting procedures and requirements
• Installation schedule
• Other concerns
Pre-Construction
QC / QA Program - Contracting
• Micropile Specification
• Prescriptive vs. Performance
• Contractor Qualification
• Prequalification
• On-site pre-production “test” program
• Definition of responsibility
• Owner / owner’s representative
• Contractor
• Engineer
• Inspector
Pre-Construction -
QC / QA Program Owner Responsibility
• Geotechnical reports and data
• Work restrictions, site and environmental limitations
• Overall scope of work
• Level of corrosion protection
• Testing criteria and in-service performance criteria
• Method of measurement and payment
• Requirements for QA/QC and verification
• Construction techniques that are not acceptable since
they may adversely impact the structure and/or the
subsurface conditions
Pre-Construction -
QC / QA Program Contractor Responsibility
• Details of all construction steps
• Gaining access (physically) to every pile location
• Setting up of load test frames
• Handling of spoils
• Construction records
Pre-Construction -
QC / QA Program Project Specific Responsibility
• Easements, utility locations
• Micropile type, design, and layout
• Connection design and details
• Corrosion protection details
• Micropile testing procedures and requirements
• Instrumentation requirements
• Reports on load testing
• Construction schedule
• Sequencing and coordination of work
Field Inspection of
QC / QA Program Micropile Installation
• Every pile is a data point
• Observe and document
• Drilling, installation of reinforcing, and grouting
• Inspection should be performed by micropile designer
• Timeliness
• Collect, document (including photographs), prepare, review and
deliver required reporting documentation
Field Inspection -
QC / QA Program Typical Micropile Log
Questions?
www.adsc-iafd.com