1
Transition Planning
It is important to plan for and execute a
smooth transition of the project into the
normal operations of the company
Most projects produce results that are
integrated into the existing organizational
structure
Some projects require the addition of
new organizational structures
Some projects lead to follow-on efforts
2
AT CONTRACT CLOSURE
Transfer of Transfer of
PROJECT MANAGER Materials
Responsibilities
Release Resources
3
CONTRACT FILES
4
Administrative Closure
Administrative closure involves
– verifying and documenting project
results to formalize acceptance of the
products produced
– collecting project records
– ensuring products meet specifications
– analyzing whether the project was
successful and effective
– archiving project information for
future use
5
Lessons Learned
Projects can result in informal or formal
lessons learned.
Here are some common examples of
“Lessons Learned”:
– Beginnings are important
– Top management support is critical
– Set realistic milestone dates, and then
stick to the schedule as much as possible
– Plan at a workable level
Did the project meet goals?
6
Summary: Project Closure
Gain stakeholder acceptance of the
final product(s)
Bring the project to an orderly end
Verify that all of the deliverables have
been completed (and accepted)
Complete the Project Notebook
Write Lessons Learned
Conduct a project audit
7
Planned Closure – An
Overview
Transferring responsibility
Completion of project records
– Historic reports
– Post project analysis
Documenting results to reflect “as
built” product or installation
Acceptance by sponsor/user
Satisfying contractual requirements
10
We Know What We Should
Do
Handover Gain
Finish Review
the acceptan
the work performance
product ce
18
Benefits of a Postmortem
Helps team members learn from
successes as well as mistakes
Provides a way to improve the future
process
Documents lessons learned so that
future teams and others can benefit
from them
Enhances team morale
19
The Final Report -
Project Closure Report
The final report is the history of the
project
It is a chronicle of the life and times of
the project, a compendium of what went
right and what went wrong
The required information is contained in
the master plan, all project audits, and
evaluations
The precise organization of the report is
not of great concern; the content is
20
The Final Report
Several Subjects should be addressed in the final
report:
– Executive Summary
– Closure Activities
– Project Performance
– Financial Management
– Post Project responsibilities
– Project and administrative teams
– Summary of Recommendations
21
The Final Report
For each element covered in the final
report, recommendations for changing
current practice should be made and
defended
Equally important are comments and
recommendations about those aspects of
the project that worked unusually well
The fundamental purpose of the final
report is to improve future projects
22
Closure Process/Plan:
Developing a closure plan
– How, when, where, who affected, etc.
– Use a checklist
– Staffing
– Arrange for redeployment of resources
Communicating the plan
– Formal announcement of the ending of
the project.
Implementing the plan
Project / Team evaluation
23
Why Projects Fail
Inadequately trained and/or inexperienced project
managers
Failure to set and manage expectations
Poor leadership at any and all levels
Failure to adequately identify, document and track
requirements
Poor plans and planning processes