Example 1 : ESTIMATE OF RCC ROOF SLAB

Details of Measurements & Calculations of Quantities


Height
Item Particulars of items & Length Breadth
No. or Quantity Explanatory notes
No. details of works (m) (m)
Depth(m)
1
RCC work 1:2:3
excluding steel & its 2.495 No deduction for steel
bending, but including 1 6.3 3.3 0.12
cum bars
centering & shutering &
binding steel

2 Steel bars including


bending(maild steel in
RCC work- Main bars Side cover 4 cm
12mm dia @ 0.89 kg/m - L=3.30-2side covers + 2
27 3.44
--- hooks = 3.30-
Straight bars 24cm c/c 0.08+(18x0.12)=3.44m
(No= ((6.30-
0.80)/0.24)+1=27

Adding one depth 8 cm


Bent up bars 24 cm c/c 26 3.52
for two bent ups.
(No=((6.30-0.8)/0.24)=26
@ 0.89 kg/M 164.12
Total 184.4
= 184.40 *0.89= kg

Distribution bars 6mm


(dia @ 0.22 kg/m) 1=6.30-
12 6.33
Bottom bars central 0.08+(18*0.12)=6.33m
portion 18 cm c/c
(Nos =( 2.00/18 ) + 1=12)
Bottom bars two sides 2x3 6.33
Top bars two sides 2x3 6.33
151.92 @
Total 33.42 kg
0.22kg/m
151.92 x
0.22 =
33.42 kg

197.54
Total =
kg
1.975
quintal
Abstract of estimated cost
1 RCC work 1:2:4
exculding steel and its
bending but including
centering and
shuttering and bending
of steel 2.495 cum= 675.00/cum= RS 1684.12
2 steel bars including
bending (mild steel ) in
RCC work 1.975 q @ 515.00 per quintel= Rs 1017.13
Total Rs 2701.25
5% cotige. & WE Rs 135.06
Grand toatal 2836.31
SCHEDULE OF BARS --- RCC SLAB

Length Total
Description of Weight
Shape of Bending Dimensions In cm of each No. Length
bars (kg)
(m) (m)
Main straight bars
12 mm. DIA 3.44 27 92.88

Main Bent up bars


12mm dia. 3.52 26 91.52
Total 184.4 164.12

Bottom distribution
buting bars
6 mm dia 6.33 18 113.94

Top distributing
Bars 6mm dia 6.33 6 37.98
151.92 33.42
EXAMPLE 2

ESTIMATING OF R.C.C BEAM

A detailed estimate of a R.C.C beam of 8m clear span and 75cm x 40cm


Height
Particulars of items Length Breadth or
Item No. No. Quantity Explanatory notes
& details of works (m) (m) Depth
(m)
1 R.C.C. work 1:2:4
excluding steel and No deduction for vol. Of
1 8.6 0.4 0.75 2.58 cu.m
its bending but steel bars.
including centering
2 Steel bars including
L=8.60-2 end cover + 2
(mild steel) in R.C.C
4 8.92 35.68 x2.98 kg 106.33 kg hooks= 8.60-(2X4
work Main bars –
cm)+(18X22mm) =8.92 m
22mm dia. Straight
L=8.60-2 end covers +2
20 mm dia. bent up x 2.47 hooks+one depth=8.60-8
4 9.48 37.92 93.66 kg
bars @2.47kg/m kg cm +(18X20 mm) +60
cm=9.48 cm
L=8.60-2 end covers +2
12mm dia top bars x 0.89
2 8.74 17.48 15.56 kg hooks = 8.60-8 cm+
@0.89 kg/m kg
(18X12 mm)= 8.74m

Stirrups, 10mm dia.


bars @0.62 kg/m-at 5x2 2.42 - - -
L=(65X2+32X2 cm)+2
end 12 cm c. to.c.
hooks+extra 30 cm = 194
cm + (18X10 mm ) + 30
cm = 2.42m
Next at 20 cm c/c 4x2 2.42 - - -

18 x 2.42 40.32 - -
Total
Stirrups 6mm dia.
@0.22 kg/m At
central remaining 14 2.42 - - -
length of 5.20m at 35
cm c. to c.
0.22 kg
Total 14 x 2.42 = 33.88 x 7.45 kg
=

Total 250.01 kg

2.5 quintal
ABSTRACT OF ESTIMATED COST

Particulars of item Quantit


Item No. Unit Rate per cost
of work y
Rs P Rs P
1 R.C.C. work 1:2:4
excluding steel and
its bending but 2.58 cu.m 675 cu.m 1714.5
including centering
and binding of steel
2
Steel bars including
(mild steel) in R.C.C
2.5 quintal 515 quintal 1287.5
work Main bars –
22mm dia. Straight
bars @ 2.98 kg/m.
Total 3002
Add 3% for contingencies and 2% for workcharged Establishment

Grand Total 3152


Descrip Total
Length of Weight(
tion of Shape of Bending Dimensions In cm No. Length
each (m) kg)
bars (m)
Main
straight
8.92 4 35.68 106.33
bars 22
mm. DIA

Main Bent
up bars
9.48 2 18.96 46.83
20mm
dia.

Main Bent
up bars
9.48 2 18.96 46.83
20mm
dia.

Top
straight
8.74 2 17.48 15.56
Bars 20
mm dia

Stirrups
10 mm 2.24 18 40.32 25
dia

Stirrups 6
14 31.36 6.9
mm dia
Note -- (i) If centering and shuttering is paid separately , the area and xost can be found as follows
Area of centering and shuttering = Bottom and two vertical sides x length + two ends
[(40 cm + 2 x 75 cm ) x 8.60 m] + (2 x 40 cm x 75 cm ) = (1.90 x 8.60 ) + ( 2x 0.40 x 0.75 )
:= 16.34 + 0.60 = 16.94 sq

Cost of centering and shuttering @ Rs 20.00 per sq.m = 16.94 x20.00 = 338.80
(ii) For over lapping at joints 5% of the whole steel may be provided in the estimate .
RCC COLUMN WITH FOUNDATION

Example 3: Prepare a detailed estimate of a RCC column with foundation footing


1 Earth work in excavation in
foundation
1x2.00x2.00x0.83m = 3.32 cu.m

2 Cement concrete 1:4:8 in base


1x2.00x2.00x0.08m= 0.32 cu.m

3 RCC work 1:2:4 in footing


excluding steel and its bending
but including centering and
shuttering and binding steel
Bottom square portion
1x2.00x2.00x0.25m = 1.00 cu.m
Trapezoidal portion vol..
= h/6(A1+A2+4Am)
0.50/6 {0.22 + 0.352 + 4( 2 + 0.35 )2/ 2} = 0.804 cu.m
Total 1.804 cu.m

4
RCC Work 1:2:4 in column above
G.L excluding steel and its
bending but including centering
and shuttering and binding steel
Square portion below plinth level
1x0.35x0.35x60 = 0.074cu.m

Cicular portion above plinth level


1x(3.14x0.302)/4x3.30 = 0.233 cu.m

Total 0.307 cu.m

5 Steel reinforcing bars including bending --


(I) 12 mm Dia bars @ 0.89 kg in base footing …………………
No of bars = (200 cm - 8 cm ) /15cm + 1 = 14 nos one way
L = 200 -2 cover +2 hooks = 200 - 2x4 +18x1.2 = 213.6 = 2.14 cm

(ii) 16 mm dia dowel bars @ 1.58 kgs ………….. 6 nos x 1.27 x 1.58 = 12.04 kg
(L= 0.45+0.75-cover + bend = 1.20 - 0.80 + 0.15 = 1.27m

(iii) 16 mm dia bars @ 1.58 kgs in column ………….. 6 nos x 4.10 x 1.58 = 38.87 kg
(L= 3.30 +0.60 +0.10 +0.10 = 4.10m

(iv) 10 mm dia bars @ 0.62 kgs in lateral ties ………….. 27 nos x 0.70 x 0.62 = 11.72 kg
Lateral ties No = (3.90/0.15) + 1 = 27 nos Total 115.96kg
L = (3.14 x 0.22) = 0.70 m 1.16q
ABSTRACT OF COST
Name of items and details of Rate Amount
Item no Quantity
work (Rs.P) (Rs.P)
Earthwork in excavation in 350 per
1 3.32 cu.m
foundation cu.m 11.62
Cement concrete 1:4:8 in base 300per
2 0.32cu.m
with brick ballast cu.m 96
RCC work 1:2:4 in footing
excluding steel and its bending 625per
3 1.804cu.m
but including centering and cu.m
shuttering and binding steel
1127.5
RCC Work 1:2:4 in column above
G.L excluding steel and its 590per
4 0.307cu.m
bending but including centering cu.m
and shuttering and binding steel
181.13
Steel reinforcing bars including 515per
5 1.16q
bending -- cu.m 597.4
Total 2013.65
Add 5% for Contingences and Worcharged Establishment
100.68
Grand
Total 2114.33

Note -- Centering and shuttering if required may be estimated separately as follows

Footing trapezium portion --- 4 nos x (2.00+0.35) / 2 x sloping height


4x1.175xsqrt{ (0.825)2+ 0.522 } = 4.531 sq.m

Square portion above GL upto plinth level 4 nos x 0.35 x 0.45 = 0.630 sq.m

Cicular portion above plinth level --- (3.14 x 0.30 ) x 3.30 = 3.109 sq.m

Total = 8.27sq.m
Example 4

A detailed estimate of R.C.C.


Staircase
Details of Measurement and calculation of Quantities
Item No. Particulars of item and No. length breadth height or depth Quantity Explanatory notes
details of works m m m

1 R.C.C. work 1:2:4


excluding steel and its bending
but including centering and
bending steel--
Base of flights in ground floor 1 1.2 0.5 0.25 0.15
slab of flights(inclined) 2 3.12 1.2 0.15 1.156 bearing 15cm
Landing middle and first floor 2 2.7 1.35 0.15 1.094
total 2.4 cu m

2 Brickwork in steps in 1:4


cement mortar(cut brickwork) 2 1.2 1/2(.25.25) 0.495 cu m

3 20mm cement plaster 1:6


in steps finfshed neat cement
floating--
Tread and rise 2 1.2 (.25.25) 10.56
Ends of steps 2 1/2(.25.25) 0.41
Total 10.97 sq m

4 2.5cm Nosing in steps


in 1:3 cement mortar 2 1.2 - - 28.8

5 2.5cm c.c floor 1:2:4 finished


neat cement floating in landing
middle and first floor 2 2.7 1.2 - 6.48 sq m
Item No. Particulars of item and No. length breadth height or depth Quantity Explanatory notes
details of works m m m
6 steel work
including bending in rinforce-
ment and railing
(i)12mm Dia. bar@0.86kg in
R.C.C work--main bars in
landing
No of bars 120/12=11 11 5.22 L=4.10+0.90+0.18
main bars in upper fright and
middle and first floor landing 11 6.25 L=1.3+3.7+1.05+
.18+0.12=6.25m
Top bars first floor landing 11 1.8 L=1.08+.61+9.012

Extrs bsrs first floor middle


of each landing 2 1.49 L=1.2+.15-2cover+
2hooks=1.49m
Total 148.950.86 132.56kg

(ii)8mm Dia distributing bars@


0.39kg in R.C.C work
Lower flight 15nos and
upper flight 14nos 29 1.27 L=1.2-2cover+
2hooks=1.27m
middle landing 9nos and upper
landing 8 nos 17 2.77 L=2.70-2cover+
2hooks=2.77m
83.92 0.39 32.73kg

(iii) 16mm sq bars in railing@


2.01kg 47 0.90 2.01 85.02kg
Total 250.3kg
2.503q

7 R.C.C 1:2:4 hand rail includive


reinforcement centering and
shuttering finished neat cement
floating with moulding 1 6.82 6.82rm L=23.21+0.40=6.82

8 R.C.C 1:2:4 Newal posts


including steel reinforcement
and from work finished
Ground floor 1 1 0.1 0.1 0.01
first floor 1 0.9 0.1 0.1 0.01
Total 0.02 cu m

9 Caps of Newal post of c.c 2 nos


ABSTRACT ESTIMATE
Item No. Particulars of item and Quantity Unit Rate per cost
details of works Rs P Rs P

1 R.C.C. work 1:2:4


excluding steel and its bending
but including centering and
bending steel-- 2.4 cu m 775 /cu m 1860

2 Brickwork in steps in 1:4


cement mortar(cut brickwork) 0.495 cu m 365 /cu m 180.68

3 20mm cement plaster 1:6


in steps finfshed neat cement
floating-- 10.97 sq m 9.5 /sq m 104.22

4 2.5cm Nosing in steps


in 1:3 cement mortar 28.8 rm 5.5 /r m 158.4

5 2.5cm c.c floor 1:2:4 finished


neat cement floating 6.48 sq m 18 /sq m 116.64

6 steel work
including bending in rinforce-
ment and railing 2.503 q 515 /q 1289.05

7 R.C.C 1:2:4 hand rail includive


reinforcement centering and
shuttering finished neat cement
floating with moulding 6.82 rm 24 /r m 163.68

8 R.C.C 1:2:4 Newal posts


including steel reinforcement
and from work 0.02 cu m 675 /cu m 13.5

9 Caps of Newal post of c.c 2 nos 10 each 20


Total 3905.17
Add 3%for contingenvies 117.18
Add 2% Workcharged Establishment 78.12
Grand Total 4101.47