197.54
Total =
kg
1.975
quintal
Abstract of estimated cost
1 RCC work 1:2:4
exculding steel and its
bending but including
centering and
shuttering and bending
of steel 2.495 cum= 675.00/cum= RS 1684.12
2 steel bars including
bending (mild steel ) in
RCC work 1.975 q @ 515.00 per quintel= Rs 1017.13
Total Rs 2701.25
5% cotige. & WE Rs 135.06
Grand toatal 2836.31
SCHEDULE OF BARS --- RCC SLAB
Length Total
Description of Weight
Shape of Bending Dimensions In cm of each No. Length
bars (kg)
(m) (m)
Main straight bars
12 mm. DIA 3.44 27 92.88
Bottom distribution
buting bars
6 mm dia 6.33 18 113.94
Top distributing
Bars 6mm dia 6.33 6 37.98
151.92 33.42
EXAMPLE 2
18 x 2.42 40.32 - -
Total
Stirrups 6mm dia.
@0.22 kg/m At
central remaining 14 2.42 - - -
length of 5.20m at 35
cm c. to c.
0.22 kg
Total 14 x 2.42 = 33.88 x 7.45 kg
=
Total 250.01 kg
2.5 quintal
ABSTRACT OF ESTIMATED COST
Main Bent
up bars
9.48 2 18.96 46.83
20mm
dia.
Main Bent
up bars
9.48 2 18.96 46.83
20mm
dia.
Top
straight
8.74 2 17.48 15.56
Bars 20
mm dia
Stirrups
10 mm 2.24 18 40.32 25
dia
Stirrups 6
14 31.36 6.9
mm dia
Note -- (i) If centering and shuttering is paid separately , the area and xost can be found as follows
Area of centering and shuttering = Bottom and two vertical sides x length + two ends
[(40 cm + 2 x 75 cm ) x 8.60 m] + (2 x 40 cm x 75 cm ) = (1.90 x 8.60 ) + ( 2x 0.40 x 0.75 )
:= 16.34 + 0.60 = 16.94 sq
Cost of centering and shuttering @ Rs 20.00 per sq.m = 16.94 x20.00 = 338.80
(ii) For over lapping at joints 5% of the whole steel may be provided in the estimate .
RCC COLUMN WITH FOUNDATION
4
RCC Work 1:2:4 in column above
G.L excluding steel and its
bending but including centering
and shuttering and binding steel
Square portion below plinth level
1x0.35x0.35x60 = 0.074cu.m
(ii) 16 mm dia dowel bars @ 1.58 kgs ………….. 6 nos x 1.27 x 1.58 = 12.04 kg
(L= 0.45+0.75-cover + bend = 1.20 - 0.80 + 0.15 = 1.27m
(iii) 16 mm dia bars @ 1.58 kgs in column ………….. 6 nos x 4.10 x 1.58 = 38.87 kg
(L= 3.30 +0.60 +0.10 +0.10 = 4.10m
(iv) 10 mm dia bars @ 0.62 kgs in lateral ties ………….. 27 nos x 0.70 x 0.62 = 11.72 kg
Lateral ties No = (3.90/0.15) + 1 = 27 nos Total 115.96kg
L = (3.14 x 0.22) = 0.70 m 1.16q
ABSTRACT OF COST
Name of items and details of Rate Amount
Item no Quantity
work (Rs.P) (Rs.P)
Earthwork in excavation in 350 per
1 3.32 cu.m
foundation cu.m 11.62
Cement concrete 1:4:8 in base 300per
2 0.32cu.m
with brick ballast cu.m 96
RCC work 1:2:4 in footing
excluding steel and its bending 625per
3 1.804cu.m
but including centering and cu.m
shuttering and binding steel
1127.5
RCC Work 1:2:4 in column above
G.L excluding steel and its 590per
4 0.307cu.m
bending but including centering cu.m
and shuttering and binding steel
181.13
Steel reinforcing bars including 515per
5 1.16q
bending -- cu.m 597.4
Total 2013.65
Add 5% for Contingences and Worcharged Establishment
100.68
Grand
Total 2114.33
Square portion above GL upto plinth level 4 nos x 0.35 x 0.45 = 0.630 sq.m
Cicular portion above plinth level --- (3.14 x 0.30 ) x 3.30 = 3.109 sq.m
Total = 8.27sq.m
Example 4
6 steel work
including bending in rinforce-
ment and railing 2.503 q 515 /q 1289.05