Methode Pipa Chiller
Methode Pipa Chiller
PEKERJAAN DESIGN & BUILD PENGEMBANGAN BANDAR UDARA SULTAN HASANUDDIN, MAKASSAR SULAWESI SELATAN TAHAP
1-STAGE 1-PAKET 1
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
01 DIAGRAM ALUR PEKERJAAN PELAKSANAAN PIPA CHILLER
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
DIAGRAM ALUR PEKERJAAN PEMASANGAN PIPA CHILLER
START
A. REFERENSI
1. SMACNA Time Schedule & Shopdrawing & Approval Material
2. SNI
Cek NO
3. ASTM OK / NO
Revisi
OK
Persiapan Material Persiapan Alat Kerja
B. OPERASI
Marking Jalur instalasi
4. PEMBUATAN STRUKTUR & elevasi
ORGANISASI
5. PEMBUATAN TIME SCHEDULE Fabrikasi Pipa
6. PEMBUATAN SHOPDRAWING
Instalasi Pipa
7. PENGAJUAN APPROVAL MATERIAL
Repair
No
Cek
FINISH
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
02 PEKERJAAN PEKERJAAN PELAKSANAAN PIPA CHILLER
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
A. PERALATAN & MATERIAL
Peralatan
Gurinda Mesin Senai Meteran Las Bor Tangga/ PCH Tang Kunci Pas
Material
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
B. PROSES PELAKSANAAN
PASANG ACESSORIS ( VALVE,
Marking jalur instalasi & elevasi
STRAINER DLL)
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
PROSES PELAKSANAAN
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
PROSES PELAKSANAAN
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
PROSES PELAKSANAAN
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
PROSES PELAKSANAAN
FABRIKASI SUPPORT
a. Penyangga Pipa
- Marking kebutuhan UNP / Siku. Sesuaikan dengan drawing standart detail pipe support
- Potong UNP / Siku dan lubangi sesuai dengan yg diperlukan untuk masing-masing dimensi pipa
b. Sadle Support
- Potong UNP dengan Panjang kurang lebih 100mm
- Potong pipa yg akan dipasang dengan ukuran 100-150mm kemudian potong 1/8 dari diameter
pipa yg akan dipasang
- Potong Rubber Gasket dengan ukuran sama seperti potongan pipa
c. Pemasangan
- Sambungkan setiap UNP / Siku yg sudah dipotong sesuai ukuran mengikuti drawing standart
detail pipe support.
- Sambungkan potongan UNP dengan Panjang 100mm ke UNP penyangga pipa.
- Sambungkan potongan pipa 1/3 diameter dengan potongan UNP Panjang 100mm (sambung /
las diatasnya)
- Pasang karet packing diatas potongan pipa 1/3 diameter
- Install pipa diatas karet packing
- Pasang Insulasi dengan ketebalan mengikuti table standart
- Setelah prosess pemasangan insulasi selesai, pasang u-bolt pada sisi terluar insulasi lalu
kencangkan
Referensi : PT. Wijaya Karya Bangunan Gedung, Tbk
This presentation is copyright by PT. Wijaya Karya (Persero), Tbk. Don’t copy or duplicate any content of this presentation without a permission from WIKA
ASPEK K3L