By
Prof. Nadpurohit
The number 5 over the arrow indicates the Time required for completion of the
activity
A
1 2
5
C
5 6
D
E
7 8
1 2
G
2
5
C H
D1 D2
B F I
1 4 6 7
A D
E
3
A(23) D(16)
E(24)
3
Earliest Event Time Latest Event Time
E G(19) E
2 5
L L H(4)
C(20)
D1
D2
0
B(8) E F(18)) E
1 E I(10))
0 4 6 7
L L
L
A(23)
D(16)
E(24))
E
3
L
20 G(19) 39
2 5
L L H(4)
C(20)
D1
8,39 D2
43, 67, 47
0 39, 57
B(8) F(18)
39 67
57 I(10)
1
0 4 6 7
L L
L
A(23)
D(16)
E(24)
23
23
3
L
Hence earliest completion of Project time
is 67 days
C (8) K (3)
D H (5)
J (16)
8 G (4) 12
3 5
Activity I: 8 12
Total Float = 28 – 17 - 10 = 1 day
Activity F:
Total Float = 18-7-5 =6 days
If F absorbs all its float then I has no float, but if F absorbs only 5 days of its float then I still has its 1 day float
The float in an activity which can be used with out affecting float of any succeeding activity is called as Free Float
Consider activity K: If the tail event of this K activity is reached as late as possible and the Head event of the
activity starts as early as possible then the float for K is 17-8-3 = 6 days. This float of 6 days whose absorption
does not affect neither preceding activity nor the subsequent activity is called Independent Float
1 3 6 12
2 8 9 10
3 6 8 10
4 2 5 8
5 3 9 12
6 3 4 5
Critical Path
11
3
11 6
9
0
17
1
0 4
6 17
5
5
10
2 10
5
3
10 6
9
Normal Project Time = 17 days 0
16
Normal direct cost = Rs. 800/- 1
4
0
Total Project cost 5 16
2-3 6 4 80 200 60
5
5 2-4 10 8 130 230 50
10
2
5 3-4 6 4 110 290 90
9
3
9
Project Time = 16 days 9
6
Direct cost = Rs. 800/- + 60 = Rs. 860
0
Total Project cost 15
1
= Direct cost + Indirect cost / day x Duration of the Project 0 4
4
15
= 860 + 120 x 16 = Rs. 2780
Critical path 1-2, 2-3, 3-4 5
Activity 1-3 and 2-4, each have a float of 1 days 5
10
Crashing critical activity with minimum cost slope i.e. activity 2-3 we get 2
5
2-3 6 4 80 200 60
5
5 2-4 10 8 130 230 50
10
Project Time = 15 days 2
5
Direct cost = Rs. 860/- + 60 = Rs. 920 3-4 6 4 110 290 90
Total Project cost
= Direct cost + Indirect cost / day x Duration of the Project
= 920 + 120 x 15 = Rs. 2720
Critical path all paths are critical
Now Activity 1-3 and 2-4, do not have any float
Activity 2-3 has reached its crash duration and cannot be reduced further
Crashing options
a) Crash 1-2 & 1-3 at a crash cost of 70+80=Rs.150
b) Crash 2-4 & 3-4 at a crash cost of 50+90=Rs. 140
c) Crash 1-2 & 3-4 at a crash cost of 70+90=Rs. 160
8 9 9
3 3 3
8 6 9 5 9 5
8 9 9
0 0 0
14 14 14
1 1 1
0 4 0 4 0 4
4 14 4 14 4 14
4 5 4
4 5 4
10 9 10
2 2 2
4 5 4
2-3 6 4 80 200 60
a 8 9 9
b c
3 3 3
8 6 9 5 9 5
8 9 9
0 0 0
14 14 14
1 1 1
0 4 0 4 0 4
4 14 4 14 4 14
4 5 4
4 5 4
10 9 10
2 2 2
4 5 4
Project Time = 14 days, Direct cost = Rs. 920/- + 100 = Rs. 1020
4
Total Project cost 4
10
= Direct cost + Indirect cost / day x Duration of the Project 2
4
= 1020 + 120 x 14 = Rs. 2700
Jan – Mar 2006 Network Analysis Slide 41 of 43
By
Prof. Nadpurohit
Activity Normal Crash Normal Crash Cost
d 9 Time Time Cost (Rs.) Cost (Rs.) Slope
3 (days) (Days) (Rs.)
9 5
9
1-2 5 4 170 240 70
0
14 1-3 9 6 310 550 80
1
0 4
5 14
2-3 6 4 80 200 60
Project Time = 14 days, Direct cost = Rs. 920/- + 100 = Rs. 1020
Total Project cost
= Direct cost + Indirect cost / day x Duration of the Project
= 1020 + 120 x 14 = Rs. 2700
9
3
9 4
9
All activities are critical
Activity 1-2 is at its crash time & hence cannot be further crashed 0
13
For a Project duration of 13 days the crashing options are 1
0 4
5 13
a) Crash 2-4 and 3-4 at a crash cost of 50+90=140
b) Crash 1-3, 2-3 and 2-4 at a crash cost of 80+60+50=190
4
Choosing a option we get 4
9
2
4