Denah Rumah
TampaK & Potongan
Pekerjaan Persiapan, Galian dan Urugan
Pekerjaan Pengecatan
V=PxL
V = 20 x 10
2. Bouwplank
3. Galian
V=bxh xp
V = 0,85 X0,7 X98,5
= 58,6 m3
4. Urugan Pasir dan Tanah V=bxh xp
V = 0,05 x 0,85 x 98,5
= 4,1862 m3
Urugan Pasir dibawah lantai V = h x l x p atau V = h x L
= 0,05 x 119
=5,93 m3
Urugan tanah kembali sisi fondasi
V = V galian tanah –(V pasangan batu kali + V urugan pasir di bawah pondasi )
V = 58,6 – (29,34 + 4,18)
V = 25,08
V=hxL
V = 0,35 x 18 m2
V = 6,30
PEKERJAAN FONDASI DaN BETON BERTULANG
VA = (a+b)h/2 x P
VA = (0.3+0.65)0.65/2 x 76,5
VA = 23.619 m3
VB = (a+b)h/2 x p
VB = (0.25 +0.55) 0.65/2 x 22
VB = 5.72 m3
Tipe A Tipe B
V tot = 29.34 m3
c. Kolom Beton 13 x 20 cm
V=bxhxpxn
V = (0.13x0.2x3.45) 2
V = 0.179m3
d. Kolom Beton 20 x 30 cm
V=bxhxpxn
V = (0.2x0.3x3.45) 2
V = 0.414m3
e. Ring balk (13 x 20 cm)
V=bxhxp
V = 0.13 x 0.2 x 98.5
V = 2.56 m3
f. Beton dapur tinggi 80 cm (tebal = 8 cm)
V=bxlxp
V = 0.08 x 0.7 x 3
V = 0.168 m3
g. Lis plank 8 cm x 40 cm
V=bxhxp
V = 0.1 x 0.4 x 3
V = 0.12 m3
V2 = h x p
V2= 1.6 x 10.6
V = 16.92
b. Dinding bata 1: 5
V = h x p – N. pintu
V = 3.25 x 98.5 -50.55
V = 269.57
c. Pasangan rolaag
V= hxp
V = 0.25 x 6.5
V = 1.62 m3
d. Plesteran dan aci 1: 3
V1 = Vt x 2
V1 = 20.76 x 2
V = 41.52
V1 = 1.6 x 1
V = 16.92
e. Dinding bata 1: 5
V = 269.57 x2
= 539.14
f. Dinding tekstur
V= hxp
V = 1 x 10.25
V =10.25 m3
PEKERJAAN LANTAI DAN DINDING KERAMIK
a. Keramik 30 x 30 cm
V1 =112,75 m2
b. Keramik 20 x 20 (KM WC
V = 5.88 m2
c. Dinding keramik
V= hxp
V = 1.6 x 11.33
V =18.08 m3
V = 4m2
PEKERJAAN PLAFON
a. Rangka plafon
V = luas ruangan
V = 130.75 m2
b. Plafon triplek
V = 130.75
c. Lis Plafon
V = 136.8 m
PEKERJAAN KUSEN PINTU DAN JENDELA
a. Kusen Kayu
V= Lxp
= 0.06 x 0.15 x 94 m
= 0.846 m3
b. Daun Pintu dan Jendela
1. Multiplek 2. Garasi
V = Lxh xn p V = Lx h x np
= 0.82 x 2.02 x 7 = 0.7 x 2.02 x 4bh
= 11.5948 m2 = 5.656 m2
PEKERJAAN ATAP
Kuda-kuda
Rencana Atap
a. Kuda-kuda Atap Rumah d. Lisplank
V1 = h x b x p
V1 = 0.12 x 0.08 x 123 V = 38 m
V = 1.18
V = 220 m2
PEKERJAAN INSTALASI AIR
Air Bersih
-Pipa ½ inch = 33 m
--Keni ½ = 10bh
-- tee ½ = 4 bh
-Pipa ¾ = 11.5 m
-Knee ¾ = 2 bh
-Tee ¾ = 2 bh
-Lem + amplas
Air Kotor
-Pipa 2 inch =6 m
--Keni 2 = 4bh
-- tee reducer 2 ke 4 = 1 bh
-Pipa 4 = 33.5 m
-Knee 4 = 2 bh
-Pipa talang 3 ‘ = 9m
- T reducer 3 ke 4 = 1 bh
PEKERJAAN INSTALASI LISTRIK