http://www.scottish.parliament.uk/business/res
STANDARD PROJECT MANAGEMENT TECHNIQUES
The Scottish Parliament
TOOL STANDARD USEAGE USEAGE ON SCOTTISH PARLIAMENT BUILDING
Launch Meeting Understand and agree scope and responsibilities Project Manager was not in position at the first meeting
Action Plan/Work Identify activities, durations, milestones, This was in place, but not updated, hence useless
Breakdown Schedule personnel
Activity Orientated BudgetAllow cost estimates based on historic data Not adopted.
gathered on similar projects.
Risk Management Identify sources of risk, analyse them and agree a Risks were identified and analysed but no action taken.
(budgetary) response
Project Evaluation and Calculate activity slack/float times and rank in This does not appear to have been carried out and certainly
Review Techniques order – pessimistic, most likely, optimistic not adhered to.
Gantt Chart Sequencing of operations Bovis utilised their own methods, which were criticised by
team members as being difficult to understand.
Goldratt’s Critical Chain To focus on common project issues of unrealistic Trade offs should have been made between design – cost or
due dates, too many changes, lack of resources design – time, but this did not occur.
and data, unrealistic budget.
Plan – Monitor – Control Specific measurement of performance cost and These reports were compiled, but the findings “filtered out”
Cycle time to allow these items to be controlled. Data by the civil service to give an unrealistic performance report.
should have been collected and regular reports
instigated.
Earned Value Analysis Measurement of % budget spent against Not adopted in this case
completion – not a good indicator of
completion.
Project Control Should regulate results by altering activities Ineffective as the architect ignored the project manager’s
accordingly by correcting errors, instructions and requests.
considering impact on creativity and
innovation.
Go/No Go System Agreed standard must be met before permission is Not adopted – instead post-control seems to have been in
given to continue with another item of place.
work
Change Control Requested changes should be reviewed, impact on Not followed – architect and client simply agreed changes
other areas evaluated, communicated and without informing project manager or other team
agreed prior to action. members
Project Evaluation Appraise progress vs goals and objectives to Conducted but ignored.
improve performance
Project Termination Decide whether to continue with an under- Considered but never seriously evaluated.
performing project based on “sunk costs”
or to terminate and cut losses.
http://
www.scottish.parliament.uk/vli
/ holyrood/inquiry/sp205-00.htm
Lists everything
The Scottish Parliament
http://www.scottish.parliament.uk/business/research/pdf_res_notes/rn01-64.pdf
• 28 SEPTEMBER 2000.
• At the Audit Committee meeting on
Tuesday, 26 September, Muir Russell
agreed to provide notes on a number of
issues that were touched on during the
evidence taking session on the Auditor
General for Scotland's Report on the new
Scottish Parliament Building.
• I thought it would be helpful to put in
writing the areas on which the Committee
is expecting to receive clarification. These
are:
• Details of the person specification and
recruitment method adopted for the
replacement project manager
The Scottish Parliament
RESPONSE
http://www.audit-scotland.gov.uk/public
The Scottish Parliament
The Scottish Parliament
The Scottish Parliament
The Scottish Parliament
http://www.scottish.parliament.uk/business/committees/historic/finance/
• Alasdair Morgan: I find it difficult to understand why the target date has
not only slipped three to four months since last you gave evidence on 8
October, but has become less certain rather than more certain.
• Sarah Davidson: The current target date of best completion at the end of
August, which means that everything will have happened to the best
possible outcome, has the same status as the previous date of the end of
April.
• Alasdair Morgan: Do you have a worst possible outcome date?
• Sarah Davidson: No.
• Alasdair Morgan: What kind of Gantt chart is used? Some kind of worst-
case scenario must have been considered.
• Robert Brown: The object of the exercise is to finish the thing as quickly
as possible—that is clearly what we are after and the progress group is
keeping on top of the contractors to try to ensure that that happens.
However, as we have already explained, the business of the glazing and
blast proofing could have had a dramatic effect on the progress of the
contract. Had last Friday's blast test failed, we would be coming to the
committee today to report a serious situation; there are no two ways
about that. Happily, the blast test was passed. Although we have to take
account of the fact that the test had to happen in the first place, that is
part of the risk review that is taking place at the moment. The major
concerns that we would have had if the blast test had failed have not
materialised. We are therefore able to come to the committee with good
news on that particular point because passing the test removes what was
probably the single biggest risk that remained on the contract.