PA ARCHITECTS PRESENTS:
THE MOUNTAIN VIEW ELEMENTARY
MASTER PLAN
architects
KINDERGARTEN
GYMNASIUM
architects
PHASE 1
EXTEND EXISTING BUS LANE Temporary bus-loop aligns with 2nd Street for student drop-off and pick-up during construction period. TEMPORARY PARKING LOT Allows staff/visitors to access classrooms and offices during construction. STAGE CONSTRUCTION ZONES Zones allow construction and school activities to work concurrently.
architects
PHASE 1
SITE CLEARING Playground equipment, parkinglot, track, environmental area.
CR
CONSTRUCT NEW BUILDINGS Administration Suite, Classrooms, Kitchen/Dining, Art/Music, Media Center
Track
music Kitchen/ dining
OCCUPY NEW BUILDINGS Students and staff use existing school buildings until new classrooms/offices are complete.
Playground
architects
PHASE 2
SELECTIVE BUILDING DEMOLITION Administration offices, library, cafeteria/kitchen; clear basketball courts and remove portable classrooms from site. KINDERGARTEN AND GYMNASIUM TO STAY SELECTIVE SITE DEMOLITION & GRADING: Prepare site (from removal of buildings) for new sidewalks, parent drop-off, bus-loop and parking.
architects
PHASE 3
CONSTRUCT SITE PARKING Prepare new surface parking adjacent to 2nd Street, kitchen, Head-start, and Kinder drop off.
PARENT & BUS DROPOFF Separate layout of parent drop-off and bus-loops maintain traffic flow. KINDERGATEN DROP-OFF Bus-loop located close to administration area; secure circulation for young students.
architects
PHASE 3
RESTORE PLAY YARDS AND LANDSCAPE Relocate or replace play yard equipment.
PK PK Exist Gym
Music
Play Equip
Service
architects
Massing Studies
architects
PA Architects
We appreciated this opportunity to work for APS and Mountain View Elementary School !