PA ARCHITECTS PRESENTS:
THE MOUNTAIN VIEW ELEMENTARY
MASTER PLAN

architects

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

Challenges At Mountain View Elementary:


 Air Quality  Noise Pollution  Site Drainage  Out-dated Utilities  Failing Buildings  Access and Circulation  Propose removal of all site buildings except:

KINDERGARTEN

GYMNASIUM

architects

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

PHASE 1
 EXTEND EXISTING BUS LANE Temporary bus-loop aligns with 2nd Street for student drop-off and pick-up during construction period.  TEMPORARY PARKING LOT Allows staff/visitors to access classrooms and offices during construction.  STAGE CONSTRUCTION ZONES Zones allow construction and school activities to work concurrently.

Temporary contractor access from Shirk Lane

architects

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

PHASE 1
 SITE CLEARING Playground equipment, parkinglot, track, environmental area.
CR

classrooms Parking Lot admin Media center

 CONSTRUCT NEW BUILDINGS Administration Suite, Classrooms, Kitchen/Dining, Art/Music, Media Center

Track
music Kitchen/ dining

 OCCUPY NEW BUILDINGS Students and staff use existing school buildings until new classrooms/offices are complete.

Playground

architects

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

PHASE 2
 SELECTIVE BUILDING DEMOLITION Administration offices, library, cafeteria/kitchen; clear basketball courts and remove portable classrooms from site.  KINDERGARTEN AND GYMNASIUM TO STAY  SELECTIVE SITE DEMOLITION & GRADING: Prepare site (from removal of buildings) for new sidewalks, parent drop-off, bus-loop and parking.

architects

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

PHASE 3
 CONSTRUCT SITE PARKING Prepare new surface parking adjacent to 2nd Street, kitchen, Head-start, and Kinder drop off.

 PARENT & BUS DROPOFF Separate layout of parent drop-off and bus-loops maintain traffic flow.  KINDERGATEN DROP-OFF Bus-loop located close to administration area; secure circulation for young students.

architects

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

PHASE 3
 RESTORE PLAY YARDS AND LANDSCAPE Relocate or replace play yard equipment.

Future CR Exist Kinder K 20 Classrooms (2 story)

Admin Media center

 FUTURE CLASSROOM EXPANSION Plan will accommodate future classroom expansion.


Play Field

PK PK Exist Gym

Play court Play court

Visitor Parking Kitchen/ Dining

Music

Play Equip

Service

Residential Teacher Parking Head Start

architects

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

Massing Studies

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

MOUNTAIN VIEW ELEMENTARY SCHOOL MASTER PLAN

architects
PA Architects

We appreciated this opportunity to work for APS and Mountain View Elementary School !