Anda di halaman 1dari 37

Contract Management in International Construction

EPC Contracts
Tim Steadman

Beijing, April 28, 2009

General Overview
  

Introduction to CC Construction Group Purpose of presentation Outline of presentation


     

Context Roles Philosophy Structure Form Key risks and contract terms

EPC Contracts - 28 April 2009

Context - Economic


Effect of cycles
    

Participants Procurement methods and structures Price Risk allocation Funding sources and methods

EPC Contracts - 28 April 2009

Context Business Culture




Most countries embrace market economics (in theory) In practice there are exceptions helpful and otherwise So relationships are to some extent adversarial/competitive And negotiations can be complex (especially if lenders are involved)

EPC Contracts - 28 April 2009

Context Legal/Regulatory
 

Legal system is part of business culture The rule of law/contract is important, especially in project financed deals Civil and common law systems differ in form and substance Impact of procurement rules
 

On owners behaviour On bidding tactics

EPC Contracts - 28 April 2009

Roles
    

Prime contractor (not always EPC) Vendor Technology licensor Investor Funder (deliberate or by default)

EPC Contracts - 28 April 2009

Philosophy


As a contractor
    

Open bidding or sole source? Immediate profit or market penetration/profile? Sole or in consortium? Legal and practical consequences of joint liability? Equity or contracting role only?

EPC Contracts - 28 April 2009

Philosophy (contd)


As an owner
   

Alliance or risk transfer? Linked to funding method Some sectoral patterns Also varies between public and private sector

Philosophy is influential only if shared within supply chain

EPC Contracts - 28 April 2009

Structure the Project




Privately procured
 

On balance sheet Off balance sheet May still be accounting considerations, eg in PPP PPP projects Concessions Others eg PPAs

Publicly procured


Combinations
  

EPC Contracts - 28 April 2009

Typical PPP Structure


PUBLIC ENTITY
SPONSOR EQUITY CONCESSION CONTRACT INSURERS

THIRD PARTY EQUITY INVESTORS

SPV INVESTORS

SURPLUS REAL ESTATE DISPOSAL

MEZZANINE FUNDERS CONSTRUCTION SENIOR FUNDERS (BANK/BOND)

OPERATION & MAINTENANC E

DEVELOPER

SUBCONTRACTOR 1 DESIGNERS

EQUIPMENT SUPPLY

SUBCONTRACTOR 3

BONDS & GUARANTEE S

DUE DILIGENCE ADVISER 1

DUE DILIGENCE ADVISER 3 DUE DILIGENCE ADVISER 2 SUBCONTRACTOR 2

SURETIES & GUARANTORS

EPC Contracts - 28 April 2009

Structure the Main Construction Contract(s)


   

EPC/design and build Owner designed EPCM/CM Other variants

EPC Contracts - 28 April 2009

10

EPC Structure
Traditional OWNER

ARCHITECT/ENGINEER

CONTRACTOR

KEY

SUB-CONTRACTORS

= Building Contract = Sub-Contracts = Appointments


EPC Contracts - 28 April 2009 11

EPC Structure (contd)


Where does EPC fit in?
Owner assumes risk Construction Management RISK SPECTRUM Contractor retains risk

Traditional

Design & Build

LSTK/ EPC

Except as otherwise stated in the Contract: a) the Contractor shall be deemed to have obtained all necessary information as to risks, contingencies and other circumstances which may influence or affect the Works; b) by signing the Contract, the Contractor accepts total responsibility for having foreseen all difficulties and costs of successfully completing the Works; and c) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs.

LSTK Lump Sum Turnkey EPC Engineering Procurement and Construction

EPC Contracts - 28 April 2009

12

EPC Key Features


   

 

Single point responsibility Subject to caps and carve-outs High degree of risk for contractor Also high (but not absolute) degree of contractor control Priced accordingly The preferred structure for project finance/PPP transactions Linkage to shareholder support

EPC Contracts - 28 April 2009

13

EPC Key Features (contd)


 

Sensitive to market conditions recent history Wide choice of standard contracts (eg FIDIC Silver and Yellow) Commonly used in infrastructure, thermal power and downstream petchem

EPC Contracts - 28 April 2009

14

Owner Design
Traditional OWNER

ARCHITECT/ENGINEER

CONTRACTOR
KEY = Building Contract = Sub-Contracts = Appointments
EPC Contracts - 28 April 2009 15

SUB-CONTRACTORS

Owner Design Key Features


   

More control for owner Design and other risks also retained by owner History of disputes Use has declined in recent decades but still used in, eg, public civil works and technology projects Incompatible with project finance approach

EPC Contracts - 28 April 2009

16

EPCM/CM
OWNER
CONSTRUCTION MANAGER
KEY

PROFESSIONAL TEAM ARCHITECT STRUCTURAL ENGINEER M&E ENGINEER QUANTITY SURVEYOR CDM CO-ORDINATOR

= Trade Contract = CMA = Appointments

TC

TC

TC

TC

TC

TC

TC

TC

TC

TC = TRADE CONTRACTOR
EPC Contracts - 28 April 2009 17

EPCM/CM Key Features


 

EPCM contractor is essentially a consultant Owner bears substantial risk


 

Interface Recourse/leverage

 

Can produce the lowest cost and fastest completion But is heavily dependent on specialist skills, experience and resources Can be disastrous if those are not present examples Widely used in upstream oil and gas, renewables and some real estate markets
EPC Contracts - 28 April 2009 18

Variants


Timing two-stage contracting


   

Market driven and mixed feedback Conversion mechanism Scope is FEED included? Can be attractive for contractors Usually a consequence rather than a choice Examples eg 2012 Link to philosophy

Pricing target cost/GMP


  

EPC Contracts - 28 April 2009

19

Forms of Contract


a profusion of colour and variety!

EPC Contracts - 28 April 2009

20

Forms of Contract
     

Standard or specially drafted? Relevance of wider structure Origin of standard forms Example of FIDIC Other standard forms, eg NEC, AIA, ENAA, EIC Why amend a proven form?


To correct perceived anomalies or bias (examples)

EPC Contracts - 28 April 2009

21

Forms of Contract (contd)


To reflect deal specifics or sector practice (examples)  To incorporate material from other contracts (eg in PPP)  To reflect requirements of funding (which may be owner or contractor sourced)  For legal reasons (examples)


Who drafts owner or contractor?

EPC Contracts - 28 April 2009

22

Key Risks and Contract Terms




Law and language


  

  

English language and style commonly used Precedence and integration of documents Distinguish language of contract and of communications Common law preferred but less strongly these days Impact of local law in any event Wide choice of methods and places for dispute resolution

EPC Contracts - 28 April 2009

23

Key Risks and Contract Terms (contd)




Quality and scope




    

Wrapping eg of technology or existing works or design Fitness for purpose and reasonable skill and care Insurance and risk retention implications Compliance with laws and consents Special importance of environmental requirements Pass-down from other project documents

EPC Contracts - 28 April 2009

24

Key Risks and Contract Terms (contd)




Intellectual property
   

Ownership by contractor Assigned or licensed to owner? Scope of license Indemnities for infringement capped or not?

EPC Contracts - 28 April 2009

25

Key Risks and Contract Terms (contd)




Performance Security
  

Joint liability Guarantees Bonds


 Types and purposes  Issues with on-demand bonds  Credit issues in current market

Retention funds

EPC Contracts - 28 April 2009

26

Key Risks and Contract Terms (contd)




Subcontracting
Approval  Step-in rights


Site conditions
Can threaten viability of project/parties  Mitigants


   

An open-minded approach Government support Surveys and staging Flexibility in design

EPC Contracts - 28 April 2009

27

Key Risks and Contract Terms (contd)




Labour
Local laws  Local preference


Time
Status of programme  Remedies for delay


    


Liquidated damages (LDs) for delay Enforceability issues with delay LDs Acceleration Milestones Look-forward default
EPC Contracts - 28 April 2009

Calculation and capping of LDS


28

Key Risks and Contract Terms (contd)




Completion, commissioning and testing


Sector differences  Performance LDs and make-good


Defects liability
Typical periods  Evergreen clauses  Latent and patent defects  Remedies under the general law


EPC Contracts - 28 April 2009

29

Key Risks and Contract Terms (contd)




Variations
Instructed by the owner  Resulting from changes in law or standards


 Examples of risk allocation




Price and payment


Lump sum or other?  Currency issues  Input cost fluctuation  Milestones or measurement?  Offsite materials

EPC Contracts - 28 April 2009

30

Key Risks and Contract Terms (contd)


      

Advance payments Cashflow neutrality Payment security for contractor Set-off and correction ECA requirements Remedies for non-payment Role of lenders engineer

EPC Contracts - 28 April 2009

31

Key Risks and Contract Terms (contd)




Termination


For owner convenience


 Payment of profit

 

For force majeure For owner default


 Typical grounds  Remedies

For contractor default


 Typical grounds  Remedies (to include rejection?)

EPC Contracts - 28 April 2009

32

Key Risks and Contract Terms (contd)




Risk
    

Indemnities Treatment of hazardous sites Care of the works Excepted risks Link to insurance Liability cap Exclusion of consequential loss Exceptions
EPC Contracts - 28 April 2009

Liability
  

33

Key Risks and Contract Terms (contd)




Insurance


Main categories
      

CAR/EAR TPL/PL PII Plant and vehicles DSA/ALOP Latent defects Operational insurance

Who arranges cover?  Other contract terms




EPC Contracts - 28 April 2009

34

Key Risks and Contract Terms (contd)




Force Majeure
   

Open or closed clause? Territorial limits? Exclusions Consequences

EPC Contracts - 28 April 2009

35

Contract Management in International Construction


Beijing, April 28, 2009

EPC Contracts

www.cliffordchance.com
Clifford Chance, 10 Upper Bank Street, Canary Wharf, London, E14 5JJ, UK Clifford Chance LLP 2007 Clifford Chance Limited Liability Partnership

Anda mungkin juga menyukai