What is a WBS? The 100% Rule Three Types of WBS Structures Four Types of WBS Elements Two Types of Programs Use of WBS to Define Activities
2
GLH, Incorporated
What is a WBS? The 100% Rule Three Types of WBS Structures Four Types of WBS Elements Two Types of Programs Use of WBS to Define Activities
3
GLH, Incorporated
Guide: A Deliverable - Oriented Grouping of Project Elements that Organizes and Defines the Total Scope of the Project. Each Descending Level Represents an Increasingly Detailed Definition of the Project Work.
GLH, Incorporated
Tail
Legs
Body
Head
GLH, Incorporated
WBS CONCEPT
Outline
of the Work to be Performed Provides a Framework for Defining the Work on the Project - SOW Provides a Framework for Planning (Work Not in the WBS is Work Not in the Project)
GLH, Incorporated
Definitions
A
WBS Consists of Elements The Lowest Level Element in the WBS is Often Referred to as a Work Package A Work Package Consists of Tasks or Activities Elements are Described by Nouns Activities Contain Verbs
GLH, Incorporated
SOFTWARE PROJECT
TRAINING MATERIALS
USER DOCUMENTS
SOFTWARE SYSTEM
SYSTEM ANALYSIS
PROJECT MGT
MODULE 1
MODULE 2
MODULE 3
SYSTEM TEST
Level 3
CODING
GLH, Incorporated
TEST 8
What is a WBS? The 100% Rule Three Types of WBS Structures Three Types of WBS Elements Two Types of Programs Use of WBS to Define Activities
9
GLH, Incorporated
100 % Rule
The next level decomposition of a WBS element (child level) must represent 100% of the work applicable to the next higher (parent) element.
GLH, Incorporated
10
PERMITS/ INSPECTIONS
GROUNDS
GARAGE
CONSTR. PLANS
PROJECT MGT
FOUNDATION
WALLS
ROOF
UTILITIES
ASSEMBLY
FRAME
GLH, Incorporated
ASSEMBLY
Level 4 11
GLH, Incorporated
12
What is a WBS? The 100% Rule Three Types of WBS Structures Four Types of WBS Elements Two Types of Programs Use of WBS to Define Activities
13
GLH, Incorporated
GLH, Incorporated
14
Product Breakdown
Decomposition
of the Natural, Physical Structure of the Deliverable Follows a BOM Framework The Deliverable is a Tangible Product Most Common Example Used
GLH, Incorporated
15
PERMITS/ INSPECTIONS
GROUNDS
GARAGE
CONSTR. PLANS
PROJECT MGT
FOUNDATION
WALLS
ROOF
UTILITIES
ASSEMBLY
FRAME
GLH, Incorporated
ASSEMBLY
Level 4 16
Service Breakdown
No
Tangible Output Product Main Event or Service Decomposition Based on a Logical Grouping (not Physical Structure) Often Developed Bottom-up Detailed Activities May be Checklists Lend Themselves to Templates
GLH, Incorporated
17
Attendees
Transportation
Facilities
Program
Displays
Project Management
Level 3
Receptions
Spouse Activities
Presentations
Tours
Level 4
Papers
Speakers
Translators
GLH, Incorporated
18
Does not have a Well-Structured Primary Product as a Deliverable May Have Several Products that Collectively Achieve the Planned Result The Projects are Process-Based
GLH, Incorporated
19
1. Work Plan
3. Hazard Analysis
4. Q.A. Process
6. HACCP Implementation
7. Project Management
GLH, Incorporated
20
What is a WBS? The 100% Rule Three Types of WBS Structures Four Types of WBS Elements Two Types of Programs Use of WBS to Define Activities
21
GLH, Incorporated
GLH, Incorporated
22
1. Integrative
Level 1 New Technology Bicycle Project
Level 2
Preliminary Design
Bicycle
Project Management
Frame
Seat Assembly
Handlebars
Assembly
GLH, Incorporated
23
2. Analytical
Level 1 New PC Development
Project Management
Documentation
Personal Computer
System Test
System Analyses
Structure
Circuit Boards
Hard Disk
Power Supply
Assembly
GLH, Incorporated
24
3. Process
Level 1 Aircraft System
Project Management
Support Equipment
Air Vehicle
Facilities
GLH, Incorporated
25
3. Process
Level 1 New PC Development Level 2 Project Management Personal Computer System Analyses
Documentation
System Test
Structure
Circuit Boards
Hard Disk
Power Supply
Assembly
Design
Procurement
Fabrication
Subsystem Test
GLH, Incorporated
26
4. Project Management
A
Special Type of WBS Element All Projects have a PM Element May be Looked-at Conceptually as an Overhead Element
GLH, Incorporated
27
4. Project Management
PROJECT MANAGEMENT (Level 2)
Level 3 PROJECT START AND FINISH Level 4 Work Packages
Contract Award Complete Project Kick-off Meeting Monthly/Quarterly Project Reviews Corporate Reviews In-Process Reviews Close-out Meeting Action Item Tracking System Monthly Progress Report Annual Report Budget/Financial Status Report Project Charter Master Schedule Project Plan (Current and Future Phases Risk Management & etc
REPORTS
PLANS
GLH, Incorporated
28
4. Project Management
PROJECT MANAGEMENT (Level 2)
Level 3 CONTROL Level 4 Work Packages
Schedule Tracking Cost Tracking Earned Value Management Analysis Variance Analysis Corrective Action Work-Arounds Project Management Office Space/Relocation Correspondence Control System Procurement/Purchasing Subcontract Management Contract Management
ADMINISTRATIVE
PROJECT SUPPORT
GLH, Incorporated
29
What is a WBS? The 100% Rule Three Types of WBS Structures Four Types of WBS Elements Two Types of Programs Use of WBS to Define Activities
30
GLH, Incorporated
PMBOK GUIDE: A group of related projects managed in a coordinated way. Programs usually include an element of ongoing work.
GLH, Incorporated
31
Feasibility, Conceptual or Initiation Planning Execution or Implementation Close-Out Operations and Maintenance (Program Management)
GLH, Incorporated
32
GLH, Incorporated
33
PM Elements at Level 1 Level 2 PM Elements for each Phase/Project Level 2 PM Elements that Relate to Subsequent Phases
Cross-cutting Analytical Elements Outputs for Future Phases
GLH, Incorporated
34
Pl nning Phase r s
l cti
l s s
r ti i t s c
.
c l
.
l i it si ck
.
cri t ck
.
ti l ti r t t i r
. c ti l s
.7
Planning Pr ject anagement
.7.
l s . . . . c l t tr cki rts t i s i
.7.
l r s . . r r r i r cti l s ct l ct l l t
.7.
l s s t l s
.7.
r ffic . t rc , t . r ct s ffic rt r t ct t
isk r ct r
. I iti l sc . I iti l r s sc l
GLH, Incorporated
35
Level 1 PM Decomposition
Level 1
Program Management
Communications
Program Support
Program Control
Etc.
GLH, Incorporated
36
What is a WBS? The 100% Rule Three Types of WBS Structures Four Types of WBS Elements Two Types of Programs Use of WBS to Define Activities
37
GLH, Incorporated
TSS PROJECT
Project Management
Requirements Specification
Initial Specification Final Specification
Design Specification
TSS Software
Module 1 Module 2 Integrate Modules
GLH, Incorporated
38
WBS in MS Project 98
GLH, Incorporated
39
GLH, Incorporated
40
Summary
Generic WBS Elements
Level 0 PROGRAM
Level 1
Program Management
Phase/ Project
Project A
Phase/ Project
Ongoing Work
Level 2
GLH, Incorporated
41
GLH, Incorporated
42
Thank You
Dr. Gregory T. Haugan P.O. Box 30 Heathsville, VA 224 3 804 580 2166 ghaugan@crosslink.net