SLOGAN SAFETY :

5S SEBAGAI DASAR KESELAMATAN & KESEHATAN KERJA

PENGGUNAAN OVERFLOW RAW WATER TANK GB #2


UNTUK MAKE-UP CWR TANK

IMPLEMENTASI SURINDO WAY


- TERPERCAYA ( PEDULI LINGKUNGAN & PERBAIKAN BERKESINAMBUNGAN )
- TARGET YANG MENANTANG ( MEMILIKI KEMAUAN UNTUK BERKEMBANG )

AGENDA :
1. BACKGROUND &TARGET
2. ANALISIS KONDISI
3. IMPROVEMENT
4. EVALUATION
5. NEXT ACTION 30 September 2015
ROFIQ, MAINTENANCE UTILITY
BACKGROUND & TARGET P

1. BACKGROUND
- Kebijakan Perusahaan untuk menurunkan
Water Index Fact. GB #2 : > 5% vs 2014
- Harga air yang cenderung terus naik

2. TARGET
Menurunkan Water Index Fact. GB #2 sebesar 10%
 dari 24.84 m3/dzn menjadi 22.3 m3/dzn

3. RESULT
Water Index Fact. GB #2 turun sebesar 21.8%
 dari 24.84 m3/dzn menjadi 19.42 m3/dzn

2
ANALISIS KONDISI P
SISTEM DRAIN TANK
1. Raw Water Tank Overflow 3. Simulasi Efek Panas Air Drain Tank
Tanggal 3April, kami lakukan simulasi
loss pencampuran Air Drain Tank yang suhunya 90 oC
dengan Air CWR Tank yang suhunya 30 oC.
Ada resiko kenaikan suhu CWR Tank jika
mendapat make-up dari Air Drain Tank .
65 m3/day

56 cc air suhu 90oC

+
Setelah dicampur suhu
Tanggal 9-13 Maret kami melakukan observasi di
air menjadi 30.2 oC.
lapangan, air yang terbuang sekitar 65 m3/hari Kenaikan suhu tidak
signifikan.
2. Analisis Kualitas Air Drain Tank 100 liter air
suhu 30oC
Dari Laporan Bulanan PT Kurita Indonesia dan juga
analisis 2G di lapangan pada Minggu ke-4 Maret 2015,
kualitas air keluaran Drain Tank bisa digunakan untuk
Raw Water Boiler yang mempunyai persyaratan lebih Kesimpulan :
ketat jika dibandingkan air CWG yang digunakan untuk Air Keluaran Drain Tank layak untuk Make-up
pendingin mesin-mesin di Fact. GB #2 . CWR Tank

3
IMPROVEMENT D

Sebelum Improvement Sesudah Improvement

Tanggal 1 Mei 2015 dipasang


Line overflow Raw Water Tank branch pipa 2”
hanya mengarah ke Water Pit menuju CWR Tank

Flow Chart Sesudah Improvement

65 m3/day

Investment :
Pemasangan branch pipa pada saat stop
produksi, dilakukan oleh Kontraktor
Installment Cost : Rp 15,000,000
Cost permonth : Rp 1,250,000 / month

4
EVALUASI C

1 GB #2 Factory Water Cons. 2 32.0


GB #2 CWG COOLING SYSTEM
14.1
13.8
15.0
13.2 14.0
190 178.0 31.5 12.8 12.8
13.0
170 after improvement reduced 63.6 m3/day 31.0
12.0
ave. : 108.6 m3/day ( 37% ) 10.9
150 30.5 10.3 10.4 11.0
m3/day

122.1 120.0 120.0 10.0


130 30.0
before improvement after improvement
102.6 105.1 104.4 motor cur. : 13.5 A 9.0
110 98.9 95.9 29.5
motor cur. : 11.1 A
8.0
90 target 110 m3/day CWG Tank & CWR Tank 29.0 7.0
max. temp. 32oC 1st 2nd 3rd 4th 1st 2nd 3rd 4th
70 before & after improvement week week week week week week week week
1st week

4th week
1st week

3rd week

4th week

3rd week
2nd week

2nd week
all temperature is OK Apr-15 Mei-15

Jan-Apr Mei-15 Jun-15


15

EFEK S, Q, C, D, M, P, E
3 2015 GB #2 Water Index
Item Sebelum After
29
27.14 Safety Air panas yang mengalir ke water Air panas tidak ada yang mengalir ke
26.3 pit bisa mengenai orang water pit
27 26.09
25.52
target 25.02 m3/dzn Quality Conductivity Air CWG Conductivity Air CWG
m3/dzn

25 actual achievement 23.19 m3/dzn 421 µS/cm 392 µS/cm  turun

Cost Water cost : Rp 32,058000/month CR Net : Rp 32,058,,000 – Rp


23 1,535,400
– Rp 1,250,000
21 19.57
: Rp 29,272,600 /month
18.7
18.02 21.37
19 Delivery
before improvement after improvement
ave. : 26.26 m3/dzn ave. : 19.42 m3/dzn Moral Kurang peduli adanya air yang Energy saving minded meningkat
17 terbuang

15 Productivity
Jan Feb Mar Apr May Jun Jul Aug Environment Overflow Raw Water Tank sebagai
Dump Water 65 m3/hari
Mengurangi Dump Water Fact. 5
sebanyak 66.5 m3/day
GB #2
NEXT ACTION PLAN A

Aktifitas Menurunkan Konsumsi Air Fact. GB #2


No. Aktifitas Mei- Jun- Jul- Aug- Sep Okt- Nov Des
15 15 15 15 -15 15 -15 -15

1. Pengontrolan Blowdown Boiler

2. Pengontrolan Blowdown Cooling Tower

3. Pengontrolan Konsumsi Steam

4. Yokotenkai Sistem Penggunaan Air Hujan

5. Penggantian Sistem Softener menjadi Sistem RO

6
TERIMA KASIH
SEMOGA SELAMAT
Air Make-up Air CWG

8
2015 GB #1 Water Index
target : 8.65 m3/dozen
8.6
8.4

m3/dozen
8.2 actual : 8.05 m3/dozen

8
7.8
7.6
7.4
Jan Feb Mar Apr May Jun Jul Aug

2015 GB #2 Water Index


29
27
m3/dozen

target : 25.02 m3/dozen


25 actual : 23.19 m3/dozen
23
21
19
17
15
Jan Feb Mar Apr May Jun Jul Aug