A. Forecast number
of participants 14 -
B. Survey Program
fees 3 -
10
3
F
C
3
B
C
Algorithm for finding Critical Path :
Notations
• ES Early Start (Earliest possible time that an
activity can begin).
• EF Early Finish = ES of the activity + activity
duration
• LS Late Start (Latest time an activity can
begin without delaying the project)
• LF Late Finish = LS of an activity + activity
duration
• ES, EF etc., of any activity “a”, are written as
ES(a), EF(a) etc.
Computations of ES, EF, LF,LS
• Let Start time for the Project = 0, then
ES(a)= 0, for all starting activities.
• For other activities, ES(a) = Max[EF(all
predecessors of a)]
• EF(a) = ES(a) + duration of “a”
• T = Max[EF(all activities)] = Earliest
Finish Time for the Project.
• Let LF(a) = T for all ending activities.
Computations (contd.)
• For other activities, LF(a) = Min[LS(all
successors of “a”]
• LS(a) = LF(a) – duration of “a”
Activity ES EF LF LS
A 0 14 14 0
B 0 3 22 19
C 14 17 25 22
D 14 21 21 14
E 21 25 25 21
F 25 35 35 25
SOLUTION: EXAMPLE 1(cont.)
• Identification of critical activities
Act. Imm.Pred. a m b
A - 2 5 14
B - 3 12 21
C A 5 14 17
D B 2 5 8
E B 6 15 30
F C,D 1 4 7
Example 2 (Contd.)
• “a” is the most optimistic time
• “m” denotes most probable time
• “b” denotes the most optimistic time
Question
Assuming resources are not a constraint;
determine the expected duration of the
project. What is the probability of completing
the project in (a)33 days (b) 23 days?
PERT : COMPUTATIONS
Step 1 Calculate Expected duration of
Each activity = te= (a+4*m+b)/ 6.
Step 2 Taking te s’ as the activity durations
Determine the critical path. Say, the
length of the critical path is μ days.
Step 3 Calculate the Standard deviation (σ)
and variance (σ 2 ) of each activity in
the critical path.
Standard Deviation = σ = (b-a)/6
Variance = σ 2
PERT Computations (Contd.)
Network Diagram
6 13 4
A F
C
5
D 16
12 E
B
SOLUTION : EXAMPLE 2
The Critical Path in the network) is BE.
Expected Project Duration (say, μ ) is the sum
of the expected duration of the activities on the
critical path. Variance (σ) of project duration is
the sum of the variances of the activities on the
critical path. Project Duration (T) is a random
variable that is normally distributed with mean
of μ and standard deviation of σ.
Check, for the given problem, T is N (28,5) σ
SOLUTION : EXAMPLE 2
The probability of completing a project by “D”
days can be determined as follows:
7
B
3
A 5
D
4
C
SCHEDULE GRAPH
SLACK
B
7
A C D
4 5
3
PROJECT DURATION 12
OPTIMUM PROJECT DURATION
Duration Crashing Cost Indirect Cost TC
(Days) (Rs.) (Rs.) (Rs.)
12 - 54 54
11 2 49.5 51.5
10 4 45 49
9 7 40.5 47.5
8 11 36 47
7 15 31.5 46.5
6