Anda di halaman 1dari 92

The Basics of Cost Analysis

Contents of this Module


 Section 1 - Cost Analysis  Section 2 Defining Costs  Section 3 Source Selections  Section 4 - Cost Data Requirements  Section 5 Field Pricing Support  Section 6 - Cost Allowability
3

Section 1 - Cost Analysis


Definition

Definition of Cost Analysis


The review and evaluation of the separate cost elements and profit in an offerors or contractors proposal (including cost or pricing data or information other than cost or pricing data), and the application of judgement to determine how well the proposed costs represent what the cost of the contract should be, assuming reasonable economy and efficiency (FAR 15.404(c)(1)). 5

Price and Cost Analysis Compared


 Price Analysis is the process of examining and evaluating a proposed price without evaluating its separate cost elements and proposed profit.
 Determines whether the price is fair and reasonable. Evaluates the separate cost elements, profit, and facilities capital cost of money (if proposed). Used to evaluate/determine any or all of the following:
   cost and/or price reasonableness cost realism most probable cost and/or price

Cost Analysis
 

It is the more costly method in terms of time and manpower.


6

Cost Analysis: When to apply it.


   It is performed if certified cost or pricing data are required. It may be used to evaluate information other than cost or pricing data, e.g., non-certified cost data. Normally, it is not needed if adequate price competition exists. In this case, it still may be used if the price is determined to be unreasonable or you are considering a cost realism evaluation [see FAR 15.305(a)(1)]. Cost analysis is one of the approaches that should be used when a cost realism evaluation is required. When you perform a cost analysis, you should also include a price analysis to verify price reasonableness.
7

 

Section 2 Defining Costs Performing a Cost Analysis Examples: Proposed Price by Major Cost Element

Contract Price = Cost + Profit


Contract Price
cost
direct cost direct labor
engineering manufacturing field service ILS

profit
indirect cost

odc
travel vendor tooling

direct material
raw material purchased parts standard commercial items subcontracts

burden (O/H)
engineering manufacturing field service ILS material handling

G&A FCCM (COM)


engineering manufacturing field service ILS material handling G&A 9

Total Contract Cost (FAR 31.201-1)


 is

the sum of the direct & indirect costs allocable to the contract, incurred or to be incurred, less any allocable credits, plus any applicable cost of money (Cost Accounting Standard 414).
10

Direct Costs (FAR 31.202)


 Definition: Direct costs are identifiable to a final cost objective (a particular contract).
Examples: direct material and direct labor.

 All costs identified specifically with a contract are direct costs for that contract and shall not be charged to another contract directly, or indirectly.  No cost shall be charged to a contract as a direct cost, if other costs incurred for the same purpose in like circumstances have been charged as an indirect cost.
11

Indirect Costs (FAR 31.203)


 Definition: Indirect costs are not directly identifiable with a final cost objective (e.g. a particular contract), but identified with two or more final cost objectives.  The distribution of indirect costs to various contracts should roughly be based on the benefits received on each contract.  No cost shall be charged to a contract as an indirect cost if other costs incurred for the same purpose in like circumstances have been charged as a direct cost to that contract or any other contract.
12

Alternative Direct Cost Treatment (FAR 31.202)


 For practicality, any direct cost of minor dollar amount may be treated as an indirect cost if this treatment:
 Is consistently applied across all contracts,
and

 Produces substantially the same results as treating the cost as a direct cost
13

Proposal Major Cost Elements


 Direct Labor Cost
   Labor Categories Labor Rates Labor Hours The Actual Materials
  Raw material Purchased parts and/or assemblies

Indirect Costs
Material Handling Fringe Benefits Overhead (or burden) G&A Expenses

Direct Material Cost




Other Direct Costs


Nonrecurring costs Subcontracts Travel

  

Subcontracts Miscellaneous material Discounts, Scrap, Inventory Shrinkage, & Freight-in

Profit or Fee Cost of Money Escalation


14

Cost Analysis: First Step


 Pre-solicitation involvement by the price/cost analyst (FSO) and engineer (ESO) is recommended
 Price/cost input
 Section B set-up, Price/Cost Evaluation Template, Section L price/cost data requirements, and Section M price/cost evaluation factors SOW/PWS

Engineering and price/cost input




Read the solicitation, section B, and SOW/PWS


  What is being purchased?
 Not as easy as looking at the Section B CLINs and/or SLINs

What are the solicitation requirements for the contractor and the government?
15

Cost Analysis: Second Step


 Read the contractors proposal price/cost narrative
 It will discuss the contractors proposal structure, assumptions, rationale, etc.
  The length and quality will vary An important source of proposal information

 Study/know the proposal set-up  Check the math:


   Is the arithmetic correct? The Section B unit prices multiplied by the quantities result in the total amounts? Do the amounts foot? Do they add-up and/or calculate correctly? Do the numbers track? Can the figures be traced among the 16 support schedules?

Cost Analysis: Third Step


 What is the basis of the proposed cost?
    How did you come up with this number? What is your rationale? What are your assumptions? What are the calculations you used?

 The contractors responses provide the answer to the question:


 Why is this price and/or cost reasonable?
17

Cost Estimating Methods Used by the Contractor


An offeror may use any generally accepted estimating methods that are equitable and consistently applied in similar situations.  Common methods:  Round Table: Experts get together and make judgments on projected costs  Comparison: Adjustments are made to a past or current item to derive the cost  Parametric: Projections are based on formulas, or cost estimating relationships  Detailed: A thorough review is made, with detailed information comprising the estimate
18

Basic Cost Element Breakdown


Proposed Price By Cost Element Item/Service: RFP: CLIN: SLIN: Date/Time: 4/21/2006 13:43 File Name: Base Period Hours Cost Element: Material: Direct Material Scrap/Discount/Miscellaneous Material Handling Total Material Direct Labor: Labor Category 1 5 Labor Category 2 6 Total 11 Fringe Benefits Overhead Other Direct Costs (ODC's) Subcontracts Travel Total ODC's Subtotal G&A Expenses Total Costs Profit Unit Price Quantity Total Price

Rate

Base

Amount 100 1 2 103 25 12 37 1 2 100 50 150 193 10 202 2 204 2 409

1% 2%

100 101

5.00 2.00 3.36 3% 4%

37 38

5% 1%

193 202

19

Basic Cost Element Breakdown


Cost Element: Material: Direct Material Scrap/Discount/Miscellaneous Material Handling Total Material Direct Labor: Labor Category 1 Labor Category 2 Total Fringe Benefits Overhead Other Direct Costs (ODC's): Subcontracts Travel Transportation Total ODC's Subtotal G&A Expenses Total Costs Profit Unit Price Quantity Total Price Hours Rate Base Amount 100 1 2 103 25 12 37 1 2 100 150 50 300 193 10 202 2 204 2 409 1% 2% 100 101

5 6 11

5.00 2.00 3.36 3% 4%

37 38

5% 1%

193 202

20

Example: Loaded Labor Rate Cost Element Breakdown


Loaded Labor Rate Calculation Template Item/Service: RFP: CLIN: SLIN: Date/Time: 2/28/2006 11:08 File Name: (1) (2) (3) (4) (5) (3)*(4) Rates: Base Labor Category WGT Lbr Rate CLIN/SLIN Automotive Mechanic 40% 1.00 Metal Body Repairman 20% 2.00 Elec Tech/Mechanic 30% 3.00 Fuel/Elec Sys Mechanic 10% 4.00 0001AA Composite 100% (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (15)*(16) Est Est Labor Total Hours Price

(5)*(6) (5)+(6) (7)*(8) (7)+(8) (8)*(9) (8)+(9) (11)*(12) (11)+(12) (13)*(14) (13)+(14) 1.00% 2.00% Adj LR FB ST 3.00% O/H ST 4.00% G&A TC 1% Profit LLR

Composite L Rate Esc 0.40 0.30 0.20 0.10

1.00 0.01 1.01 0.02 1.03 0.03 1.06

0.04

1.10

0.01

1.11 100 111.46

21

SAMPLE COST BREAKDOWN


2001 2002 90 5 2 3 2003 108 6 3 3 Total

Material
Direct Material Handling Shrinkage Shop Supplies Scrap 90 5 2 3

Total Matl Labor


Labor Rate Labor Hours

100

100

120

320

25 4

30 4

35 4

Total Labor Labor O/H ODC S/T G&A Profit/Fee COM Total Price

100 10 5 215 20 15 5 255

120 10 5 235 20 15 5 275

140 10 5 275 20 15 5 315

360 30 15 725 60 45 15
22 845

Cost Analysis: Profit/Fee

23

FAR 15.404-4(c) Contracting Officer Responsibilities: Profit


 Contracting officer responsibilities.
 (1) When the price negotiation is not based on cost analysis, contracting officers are not required to analyze profit.  (2) When the price negotiation is based on cost analysis, contracting officers in agencies that have a structured approach shall use it to analyze profit.
24

DFARS 215.404-4(b)(1) Profit


 Departments and agencies must use a structured approach for developing a prenegotiation profit or fee objective on any negotiated contract action when cost or pricing data is obtained, except for cost-plusaward-fee contracts or contracts with Federally Funded Research and Development Centers.
 DFARS 215.404-70 DD FORM 1547  DFARS 215.404-71 Weighted Guidelines Method
25

FAR 15.404-4(c)(4):

Fee - Statutory Limitations


 For R&D work performed under a CPFF contract, the fee shall not exceed 15% of the contracts estimated cost, excluding fee. For architect-engineer services for public works or utilities, the contract price or the estimated cost and fee for production and delivery of designs, plans, drawings, and specifications shall not exceed 6% of the estimated cost of construction of the public work or utility, excluding fees. For other CPFF contracts, the fee shall not exceed 10% of the contracts estimated cost, excluding fee.
26

Profit-Miscellaneous
 FAR 15.404-4(c)(5). The contracting officer shall not require any prospective contractor to submit breakouts or supporting rationale for its profit or fee objective but may consider it, if it is submitted voluntarily. FAR 15.404-4(c)(6). If a change or modification calls for essentially the same type and mix of work as the basic contract and is of relatively small dollar value compared to the total contract value, the contracting officer may use the basic contracts profit or fee rate as the prenegotiation objective for that change or modification.
27

Profit and Fee Reporting


 PGI 215.404-76(1):
 send completed DD Forms 1547 on actions that exceed the cost or pricing data threshold, where the contracting officer used the weighted guidelines method, an alternate structured approach, or the modified weighted guidelines method, to designated office within 30 days after contract award. use Army Weighted Guidelines Software for reporting DD Form 1547 data. Contracting offices outside the United States and its outlying areas are exempt from reporting.
28

 

PGI 215.404-76(2):


PGI 215.404-76(4):


Section 3 Source Selection: - Price Reasonableness - Cost Realism - Completeness Cost Realism Analysis

(Best Value) Source Selection: Sect M Cost/Price Evaluation Criteria


 Three price/cost evaluation factors
 Price reasonableness
  No FAR definition Price Reasonableness is determined by the results of a price analysis. Defined in the FAR No FAR definition
30

 Cost Realism
 

 Completeness

 Also Unbalanced Pricing

Source Selection Sect M: Cost/Price Evaluation Criteria


  Price Reasonableness: No FAR definition see next slide Cost Realism: Measure of the appropriateness of a cost to its corresponding work element. The Government will determine if the proposed costs/price(s) are realistic for the work to be performed, reflect a clear understanding of the solicitations requirements, and are consistent with the various elements of the Offerors technical proposal (FAR 15.404-1(d)). Completeness (non-FAR definition): An accurate reflection, within the cost/price proposal, of all aspects of the technical proposal; compliance with the cost/price preparation instructions in the RFP Section L Instructions, Conditions, and Notices to Offerors; and compliance with any other applicable directions.
31

How to Define Price Reasonableness?


 A cost (substitute price for cost) is reasonable if, in its nature and amount, it does not exceed what a prudent person would pay in the conduct of competitive business [FAR 31.201-3(a)]. Price reasonableness will be determined based on:
    the results of a price/cost analysis the results of the application of the price analysis techniques detailed in the FAR a comparison to the IGCE a comparison of the competing offers Price reasonableness will be determined based on the results of a price/cost analysis, including a comparison to the IGCE and 32 comparisons of the competing offers.

A combination of any of the above




Reasonableness Per ESIs Advanced Source Selection


 Are the offerors cost estimating methods reasonable and accurately prepared?  What is the level of quality and credibility of the offerors basis of estimates?
 For example, are costs based on actual data or engineering judgment?

 Are the offerors cost metrics and methods logical and appropriate for the product?
33

Completeness Per ESIs Advanced Source Selection


 Has the offeror captured all proposed effort in the cost estimates?  Did the offeror provide all information required by the RFP?  Did the offeror claim some performance in technical or management not included in the cost?  Are the technical assumptions used in the cost proposal traceable to the technical volume and vice versa?
34

Cost Realism Analysis: General FAR 15.404-1(d)


 Review the specific elements of each offerors cost estimate to determine:
 If its realistic for the work to be done  If the offeror clearly understands the requirements  If its consistent with the unique aspects of their technical proposal
35

Cost Realism Analysis FAR 15.404-1(d)(2)


(Cost Reimbursement Contracts)
 The following apply to both competitive and sole source environments:
  Government shall perform cost realism analyses for costreimbursement contracts. Individually determine the probable cost of performance of each offeror.
 Probable Cost is the governments best estimate of the cost of any contract that is likely to result from the offerors proposal.

 Probable cost determined by adjusting each offerors costs, and fee when appropriate, to reflect any understatements or overstatements based on the results of the cost realism analysis.
 For a CPFF contract, the fee would not be adjusted.

Probable cost is used in deciding best value. (Competitive environment only).


36

Cost Realism Analysis FAR 15.404-1(d)(3)


(Competitive Fixed Price Contracts)
  May be performed on Fixed Price Incentive contracts. Situations where cost realism analysis may be done on competitive fixed price contracts:
   When new requirements may not be fully understood by competing offerors, or There are quality concerns, or Past experience indicates that contractors proposed costs have resulted in quality or service shortfalls

 

You cannot adjust offered prices as a result of the cost realism analysis. Results of the analysis may be used in performance risk 37 assessments and responsibility determinations.

Cost Realism Analysis and Cost Analysis


 There is a difference between the two, but
 Confusion between the terms  Often used interchangeably

 Cost Realism Analysis applies to source selections


 Used to verify that the contractors technical approach has been priced in the proposal  Used mainly on cost reimbursement type contracts  Used to determine the Probable Cost of Performance (Most Probable Cost)

 Cost Analysis methods/procedures are used to determine Cost Realism.

38

Section 4 - Cost Data Requirements


Certified Cost or Pricing Data Information Other Than Cost or Pricing Data

Obtaining Information to Establish Price Reasonableness [FAR 15.402(a)] (and Cost Realism)
 Order of preference for type of data required and/or requested:
1 No additional information 2 Information other than cost or pricing data 3 (Certified) cost or pricing data

 Do not obtain more info than necessary


 Rely first on information available within the Government.  Second, on information obtained from sources other than the offeror.  If necessary, on information obtained from the offeror.

40

Introduction to Cost Data


 Two types:
1 (Certified) Cost or pricing data 2 Information Other than Cost or Pricing Data

 Both can be the exact same information  What is the difference between the two?
 For the first, the contractor certifies that the data is current, accurate, and complete.  For the second, the contractor does not certify that the data is current, accurate, and complete.
41

(Certified) Cost or Pricing Data Defined [FAR 2.101]


 All facts that, as of the date of price agreement or, if applicable, an earlier date agreed upon between the parties that is as close as practicable to the date of agreement on price, prudent buyers and sellers would reasonably expect to affect price negotiations significantly.
    Are factual, not judgmental, and are verifiable. Includes data forming bases of judgements. More than historic accounting data. All facts contributing to soundness of estimates.

42

Certification of Cost or Pricing Data [FAR 15.406-2]


 When cost or pricing data are required, the contracting officer shall require the contractor to execute a Certificate of Current Cost or Pricing Data.
 To the best of my knowledge and belief, the cost or pricing data submitted, either actually or by specific identification in writing, to the Contracting Officer or the Contracting Officers representative in support of (the proposal) are accurate, complete, and current as of (date negotiations completed or price agreement reached). 43

Certification Implications for the Contractor


 Emphasis on non-certified data was an Acquisition Streamlining change:
  To reduce lead-times and costs to the Government & Contractors Facilitate evaluations and reduce post award administration

Certification is expensive for the contractor in terms of time, manpower, and cost to assemble, prepare, check, and present the certified data package. Administrative and legal problems for contractors with certification:
   Truth In Negotiations Act (TINA) DCAA post award audits Potential defective pricing

44

Defective Cost or Pricing Data (FAR 15.407-1)


 If, after award, cost or pricing data are found to be inaccurate, incomplete, or non-current, as of the date of final agreement on price or an earlier date agreed upon by the parties given on the contractors/subcontractors Certificate of Current Cost or Pricing Data,
 the Government is entitled to a price adjustment, including profit or fee, of any significant amount by which the price was increased because of the defective data (Clauses 52.215-10 & 52.215-11). Contract Audit Follow Up (CAFU)

 

Audit Tracking


Resolving the issue may involve repayment of disputed amount plus penalty and interest.
45

Thresholds/Awards Where Certified Cost or Pricing Data Are Required


 Per 15.403-4(a)(1):
 Award of any negotiated contract over $650K  Award of a subcontract over $650K at any tier, if contractor and each higher-tier subcontractor also have to submit certified data  Modification worth over $650K, of any sealed bid or negotiated contract (consider absolute value of both cost increases and decreases)
46

Subcontract Cost or Pricing Data FAR 15.404-3 (1 of 2)


 The contractor shall submit (or cause to be submitted by the subcontractor (s)) cost or pricing data to the Government for subcontracts that are the lower of : (1) $11.5 million or more; or (2) Both more than the pertinent cost or pricing data threshold ($650K) and more than 10% of the prime contractors proposed price, unless the Government believes such submission is unnecessary.
47

Subcontract Cost or Pricing Data FAR 15.404-3 (2 of 2)


 The PCO may require the contractor or subcontractor to submit to the Government subcontractor cost or pricing data below the thresholds that the PCO considers necessary for adequately pricing the prime contract. The subcontractor cost or pricing data shall be current, accurate, and complete as of the date of price agreement, or, if applicable, an earlier date agreed upon by the parties and specified on the contractors Certificate of Current Cost or Pricing Data. The contractor shall update subcontractors data, as appropriate, during negotiations.
48

Certified Cost or Pricing Data for Actions Under $650,000


 FAR 15.403-4(2): The head of the contracting activity, without the power of delegation, may authorize the PCO to obtain cost or pricing data for pricing actions below the pertinent threshold.
 Shall justify the requirement with written documentation and supporting facts, that cost or pricing data are necessary to determine price is fair and reasonable.
49

Exemptions from (Certified) Cost or Pricing Data Requirements


1 2 3 4 Per FAR 15.403-1(b), five exemptions: Adequate price competition Prices set by law or regulation Commercial items Waivers (HCA approval, documentation with support)
 DFARS: Canadian Commercial Corp (CCC) & Nonprofit organizations with cost reimbursement/no fee contracts

5 

Modifying commercial item contract or subcontract FAR 15.403-2 adds the exercise of options if the price was established at contract award or initial negotiation.
50

Information Other than Cost or Pricing Data Defined [FAR 15.402]


 Any type of information that is not required to be certified IAW FAR 15.406-2 and is necessary to determine price reasonableness or cost realism.  Such information may include pricing, sales, or cost information, and includes cost or pricing data for which certification is determined inapplicable after submission.  Again, certification is the difference between the two categories of cost/price data!
51

Information Other than Cost or Pricing Data, with Adequate Price Competition FAR 15.403-3(b)  Generally, no additional info is needed, unless the price is unreasonable.  If due to unusual circumstances additional info is needed to determine reasonableness, to the maximum extent practicable obtain it from sources other than the offeror.  You may request information to determine the cost realism of competing offers or to evaluate competing approaches. 52

Situations Where Non-Certified Cost Information May be Needed


 In general, you dont expect certified data will be required, but you need cost information to determine price reasonableness or cost realism.  For example, you:
 Expect adequate price competition on a source selection but dont expect to be able to rely on comparisons between offers to determine price reasonableness (e.g. offerors may use different technical approaches).  Have determined the action is below the cost or pricing data threshold ($650,000), but you need cost information to determine price reasonableness.

53

Instructions for Submission of Information Other than Certified Cost or Pricing Data FAR 15.403-5
 In the solicitation, you should specify any information other than certified cost or pricing data that is required (Section L).  It may be submitted in the offerors own format, unless the contracting officer decides use of a specific format is essential and the format is described in the solicitation.  If you didnt specify the info in the solicitation, you can still request and obtain the needed information after initial proposals are submitted.54

Info other than Cost or Pricing Data: Limitations on Commercial Items - FAR 15.403-3(c)
 Requests for offerors sales data is limited to data for the same or similar items during a relevant time period.  To the maximum extent practicable, limit any request for info to include only info that is in the form regularly maintained by the offeror.
55

Things the Solicitation Must Specify on Cost or Pricing Data, or Info Other than Cost or Pricing Data (FAR 15.403-5) - P. 1 of 2  Whether certified cost or pricing data are required  That offerors may submit a request for exception, instead of submitting certified data  Any information other than certified cost or pricing data that is required  The required format for the cost or pricing data or information other than cost or pricing data  Necessary pre-award or post-award access to offerors records, if not provided by one of the standard clauses
56

Things the Solicitation Must Specify on Cost or Pricing Data, or Info Other than Cost or Pricing Data (FAR 15.403-5) - P. 2 of 2

 Standard Clauses are 52.215-20, and 52.215-21 (mods)


 Called out in FAR 15.408(l) & (m)  You may use these if reasonably certain cost or pricing data (or Info Other than.) needed  These cover the requirements and allow offerors to request one of the exceptions from submitting the data  If you want specific data without exception, 57 dont use the standard clause

Section 5 Field Pricing Support

Field Pricing Services FAR 15.404-2(a)(2)


   Technical, audit, and special reports associated with the cost elements of a proposal, including subcontracts. Information on related pricing practices and history. Information to help contracting officers determine commerciality and price reasonableness:
      verify sales history to source documents identify special terms and conditions identify customarily granted or offered discounts for the item verify the item to an existing catalog or price list verify historic data for item to qualify as commercial identify general market conditions affecting determinations of commerciality and price reasonableness
59

Information relative to the business, technical, production, or other capabilities and practices of an offeror.

Field Pricing Support FAR 15.404-2(a)(b)(c)


 Defense Contract Audit Agency (DCAA)
 Trained in accounting, finance, and auditing  Access to contractor accounting records  Auditors (on-site/off-site) & Financial Advisors (FA)
 Provide proposal analysis of material, labor, indirect rates, G&A, COM, etc.

 Defense Contract Management Agency (DCMA)


 Pricing and/or Technical Personnel: production specialist, engineer, etc.
 Provide technical analysis and/or pricing support
60

Defense Contract Audit Agency (DCAA)


 DCAA provides the following:
 Proposal audits by request  Agreed Upon Procedures Assignment  Forward Pricing Rate Agreements (FPRAs)
 Direct labor and indirect rates w/DCMA ACO as lead

 Incurred cost audits: on going

 Qualifications/requirements:
 Formal proposal request  Formal contractor proposal in a structured/auditable format  Minimum 30 to 45 day request processing time

61

Other DCAA/DCMA Reviews


 Accounting system reviews
 Pre-award/post award  FAR/DFARS 9.106/209.106

 Estimating system reviews


 DFARS 215.407-5 Estimating systems  DCAA performs but DCMA/ACO function

 Compensation System Reviews (CSR)  Contractor Purchasing System Review (CPSR)


 Reference FAR 44.3 and DFARS 244.3  DCMA/ACO function with DCAA assistance
62

Technical Analysis [FAR 15.404-1(e)]


 Evaluation performed by personnel having specialized knowledge, skills, experience, or capability in engineering, science, or management on proposed material types and quantities, labor, processes, special tooling, facilities, reasonableness of scrap and spoilage, and other factors in the proposal in order to determine the need for and reasonableness of the proposed resources. At a minimum:
  examine the types and quantities of material (kinds and quantities evaluation) and the need for the types and quantities of labor hours and the labor mix (skill and category)
63

Field Pricing Support & the Cost or Pricing Data Threshold


 DFARS 215.404-2(a):
 PCO should consider field pricing support for
   Fixed price proposals exceeding $650K Cost type proposals exceeding $650K from offerors with significant estimating system deficiencies Cost type proposals exceeding $10 million from offerors without significant estimating system deficiencies

 PCO should not request field pricing support for proposals less than $650K; exceptions:
  lack of knowledge of particular contractor sensitive conditions/problem areas
64

Points to Consider When Requesting Field Pricing Support


 Per FAR 15.404-2(a)(1):
 The contracting officer should request field pricing assistance when the information available at the buying activity is inadequate to determine a fair and reasonable price; tailor requests to reflect the minimum essential supplementary information needed to conduct a technical or cost or pricing analysis.

Consider cost risk!


  Contract type: there is more risk on a FFP than CPFF or CPAF contracts. Proposal total dollar value

The DCAA PLA or FA can help determine the type of 65 field pricing support/audit services needed.

FSO is the POC for DCAA


 Request DCAA audits through the FSO
 Submit audit request to DCAA  Receive/file DCAA audit reports  Tracking/report status of DCAA audits
 AFARS 5142.1-90-2

 Contract Audit Follow Up (CAFU) Program


 DoDD 7640.2  AFARS 5142.1-90-2  SOP Number 25
66

Contract Audit Follow Up (CAFU) Program (1 of 2)


 Track/provide status of reportable audits  Reportable Audits
 Estimating/accounting system and internal control reviews  Incurred costs including final indirect cost rates  Claims  Defective pricing reviews  Termination settlements  CAS issues/cost impact statement reviews
67

Contract Audit Follow Up (CAFU) Program (2 of 2)


 Recent revision: DCMA database now used  Rules/procedures?  Reviewed/updated:
 March 31st  September 30th

 Overage Audit Review Board


 Discuss unresolved DCAA audits over 6 months old with the Commander

 Bottom Line: reportable audits must be resolved in a timely manner


68

Section 6 - Cost Allowability

Factors Affecting Cost Allowability (FAR 31.201-2)


 Reasonableness  Allocability  Accounting Principles & Standards  Contract Terms
70

Reasonableness - (FAR 31.201-3)


 Definition: A cost is reasonable if, in its nature and amount, it does not exceed what a prudent person would pay in the conduct of competitive business.  Considerations
 Is the cost necessary?  Is the cost consistent with sound business practice and law?  Are the contractors purchases done on an arms-length basis?
71

Allocability - (FAR 31.201-4)


 Definition: A cost is allocable to one or more cost objectives (e.g., contracts) if it is charged based on the relative benefits received or some other equitable relationship.  A cost is Allocable to a Government contract if:  It is incurred specifically for the contract, or  It benefits the contract and other work (e.g. its an overhead cost), and can be fairly distributed based on benefits received, or  It is necessary to overall operation of the business (e.g. certain G&A expenses).
72

The Most Common Ways Costs are Incurred


 Expend Cash - Actual outlay of dollars (by cash, check, etc.) in exchange for goods or services. (e.g. Pay a vendor for raw materials)  Accrue Expense - For accounting purposes, because a future obligation is being incurred or an asset is being used. (e.g. Incurring an obligation to current workers, for their future pensions)  Use Inventory - For example, contractor buys inventory in advance and charges it to contracts as inventory is used.
73

Sources of Accounting Principles & Standards


 Generally Accepted Accounting Principles (GAAP)  Cost Accounting Standards (CAS)  FAR Part 31 Contract Cost Principles and Procedures
74

Accounting: Financial & Cost


In semi-plain English:
 Accounting is the process of identification, measurement, and communication of financial information about economic entities to interested parties. Two types:
 Financial accounting focuses on measuring the results of an organizations operations for a period of time, reflected in the financial statements. Cost (or management) accounting focuses on cost allocation to a product, service, or contract; management uses the information to plan, evaluate, and control within its organization and to assure appropriate use of, and accountability for, its resources.
75

Generally Accepted Accounting Principles (GAAP)


 Generally Accepted Accounting Principles or GAAP refers to the common set of accounting concepts, standards, and procedures which represent a general guide. GAAP principles are those that have substantial authoritative support or are based on accounting practices accepted over time by prevalent use.
 Financial Accounting Standards Board (FASB), American Institute of CPAs (AICPA), Accounting Principles Board (APB), etc.

The end products of the accounting cycle, the financial statements (balance sheet, income statement, etc.) are prepared in accordance with GAAP.

76

Cost Accounting Standards (CAS) (1 of 2)


 Purpose of CAS:
 Promulgate standards to achieve uniformity and consistency in cost accounting practices to be followed by contractors and subcontractors for defense contracts. It is an attempt to provide common ground between the contractors and the federal government on cost accounting issues during proposal preparation, negotiations, etc.
77

Cost Accounting Standards (CAS) (2 of 2)


  Currently, there are 19 standards. Cost Accounting Standards Board (CASB) administers CAS: five members, includes representatives from government, industry, and academia. CAS/CASB was originally established in August 1970 under the legislative branch. Ceased operations September 30, 1980 due to lack of funds. Re-established in November 1988 under the executive branch within Office of Federal Procurement Policy (OFPP) which is under Office of Management and Budget (OMB).
78

  

Exemptions From CAS (1 of 2)


 Eleven exemptions, with the most common (7) below:
Sealed bid contracts. Negotiated contracts/subcontracts less than $650,000. Contracts & subcontracts with small businesses. FFP & FFP with EPA contracts/subcontracts for the acquisition of commercial items.  FFP contracts & subcontracts awarded on the basis of adequate price competition without the submission of cost/price data.    
79

Exemptions From CAS (2 of 2)


 Contracts/subcontracts in which the price is set by law or regulation.  Contract/subcontract executed and performed outside the U.S., its territories, and its possessions.

80

CAS Coverage
 Two types of CAS can be applicable, depending on the dollar value of previous awards and current acquisitions.
  Full coverage: comply with all CAS in effect on the contract award date and with any new standards. Modified coverage: requires contractor to comply with four standards
    CAS 401, Consistency in estimating, accumulating, & reporting costs. CAS 402, Consistency in allocating costs incurred for the same purpose. CAS 405, Accounting for unallowable costs. CAS 406, Cost accounting period.
81

CAS - Disclosure Statement


 Firms that have contracts/subcontracts subject to full CAS coverage should have submitted a CASB Disclosure Statement, providing information on how they charge specific types of costs.
 Contractor discloses/documents company accounting practices to the government.

 The ACO and cognizant DCAA auditor are responsible for reviewing the contractors Disclosure Statement for adequacy, and for compliance with FAR Part 31 and CAS.

82

GAAP vs. CAS


 GAAP and CAS are not the same.  GAAP generally refers to financial, not cost, accounting guidance.  CAS is an attempt to extend GAAP-like guidance to government cost accounting.  CAS Objectives:
 Common cost treatment, same terminology, and the avoidance of cost manipulation (gaming).  Facilitate proposal preparation and negotiations.
83

CAS: FAR References


 FAR Part 30
 CAS Administration  Policies and Procedures for applying CAS to negotiated contracts & subcontracts

 FAR Appendix B
 Contains the actual CAS
84

FAR 31.2 Cost Principles for Commercial Organizations


 Applies to all contractors.  Defines direct and indirect costs.  Addresses specific kinds of costs as to whether allowable, unallowable, or allowable with restrictions.  Examples of unallowable costs: interest expense, bad debts, entertainment costs, donations, attorney fees for claims.
85

FAR Part 31: Examples of Unallowable Costs


    31.205-3 -- Bad Debts 31.205-8 -- Contributions or Donations 31.205-14 -- Entertainment Costs 31.205-20 -- Interest and Other Financial Costs  31.205-51 -- Costs of Alcoholic Beverages
86

FAR Part 31 Cost Principles for Other Organizations


 Refer to FAR 31 for separate, unique coverage of the cost principles for contracts with:
 Educational institutions (FAR 31.3)  State & local governments, & federally recognized Indian tribal governments (FAR 31.6)  Nonprofit organizations (FAR 31.7)
87

Contract Terms & Cost Principles


 Specific costs may be addressed in RFP or contract. (e.g. Although transportation costs are generally allowable, the contract may restrict them to a certain mode.)  On cost allowability, contract terms can only be more restrictive than other factors. (e.g. Contract terms cannot make interest expense allowable on the contract.)
88

Conclusion

89

Management/Cost Accounting System


 Contractors have to manage their organizations, products/services, and contracts  There needs to be a system in place to determine whether the service, product, or contract
 Is on schedule for completion  Is at its budgeted cost  And if not
  Why not? What is being done to correct the situation?

 All major companies have such a system!


90

Adequate Estimating System


 ACO estimating system approval means that the system has the controls to consistently produce adequate and reliable estimates.
 established policies, procedures, and practices to persons responsible for preparing and supporting estimates

A disapproved system is a red flag indicating that the firm's estimating system does not consistently provide adequate proposals.
 Normally, proposals from a firm with a disapproved system should be subjected to closer scrutiny, particularly closer scrutiny by audit professionals.
91

Adequate Accounting System


 Primary goal of an acceptable accounting system:
 Ensure that costs are appropriately, equitably, and consistently allocated to all final cost objectives (i.e., individual contracts, jobs, or products).

 

Pre-award accounting system survey performed by DCAA. System should answer affirmative to specific questions:
      IAW GAAP? (IAW CAS?) Identify & segregate direct from indirect costs, allocating these costs equitably to specific contracts on a consistent basis? Timekeeping & labor distribution systems appropriately identify direct and indirect labor charges to intermediate & final cost objectives? Accumulates costs integrated with, and reconcilable to, the general ledger? Determine cost of work performed at interim points (at least monthly) because of routine posting to books of account? If required by the contract, identify costs by CLIN/SLIN or by unit?
92

Specifically: Are there accounting controls in place?

Anda mungkin juga menyukai