Objectives
Procurement Indices
5/11/12
PROCUREMENT
Inputs to Projects
Inputs to Project
Identifying what you Need to Buy In Clear requirements Who you are going to work with(supplier)
incoming
8 5/11/12
incoming
5/11/12
PROCESS Identify procurement requirements(Concept) Plan procurement(Design) Conduct & Administer(Implementation) Close procurements(Finalization)
10
CONTRACTS Agreements Purchase order Memorandum of Understanding(MOU) Sub- contract Service level agreements
11
5/11/12
Identifying what you Need to Buy In Clear requirements Who you are going to work with(supplier)
incoming
12 5/11/12
Identifying what you Need to Buy In Clear requirements Who you are going to work with(supplier)
incoming
13 5/11/12
CONTRACTS-cont Terms & Conditions Clear points of payment Specific product/service provisions Schedule Exclusions 14 Model-Time & Material
5/11/12
Quality/OHS
15 5/11/12
16 5/11/12
YOU Will CREATE Procurement management plan Procurement statement of work(SOW)-similar to a PD but for the contract; not the individual Invitation To Tender(ITT) Request for Information(RFI), request for 17 Proposal(RFP) etc.
5/11/12
SELECTION CRITERIA Clear outline of requirement Ensure all responses received are in identified format Think ahead- word the ITT to enable numerical value to be applied to a suppliers response(simplifies overall analysis)
18
5/11/12
SELECTION CRITERIA-cont. No duplications or ambiguity in requirements Provide one point of contact where questions can be asked Evaluate, compare, choose
19
5/11/12
5/11/12
Identifying what you Need to Buy In Clear requirements Who you are going to work with(supplier)
incoming
21 5/11/12
DIFOT Performance
Final payments
22
5/11/12
23 5/11/12
Summary
Procurement is managing contracts, inputs to the project as well as outputs Influences outside the project will influence (organizational policies..) Identify, Clarify, Invite, evaluate & decide Know your contracts and the clients of each DIFOT FORMAL PROCESS-stick to it 24