Anda di halaman 1dari 44

Chapter 9

Project Management
Operations Management - 5th Edition
Roberta Russell & Bernard W. Taylor, III

Copyright 2006 John Wiley & Sons, Inc.

Beni Asllani University of Tennessee at Chattanooga

Lecture Outline
Project Planning Project Scheduling Project Control CPM/PERT Probabilistic Activity Times Project Crashing and Time-Cost Trade-off
Copyright 2006 John Wiley & Sons, Inc. 9-2

What is a Project?
Project

unique, one-time operational activity or effort


constructing houses, factories, shopping malls, athletic stadiums or arenas developing military weapons systems, aircrafts, new ships launching satellite systems constructing oil pipelines developing and implementing new computer systems planning concert, football games, or basketball tournaments introducing new products into market

Examples

Copyright 2006 John Wiley & Sons, Inc.

9-3

Project Elements
Objective Scope Contract requirements Schedules Resources Personnel Control Risk and problem analysis
9-4

Copyright 2006 John Wiley & Sons, Inc.

Project Management Process


Project planning Project scheduling Project control Project team

made up of individuals from various areas and departments within a company a team structure with members from functional areas, depending on skills required

Matrix organization

Project Manager

most important member of project team

Copyright 2006 John Wiley & Sons, Inc.

9-5

Project Scope
Scope statement

a document that provides an understanding, justification, and expected result of a project

Statement of work

written description of objectives of a project


breaks down a project into components, subcomponents, activities, and tasks
9-6

Work breakdown structure

Copyright 2006 John Wiley & Sons, Inc.

Work Breakdown Structure for Computer Order Processing System Project

Copyright 2006 John Wiley & Sons, Inc.

9-7

Organizational Breakdown Structure

a chart that shows which organizational units are responsible for work items shows who is responsible for work in a project

Responsibility Assignment Matrix

Copyright 2006 John Wiley & Sons, Inc.

9-8

Project Scheduling
Steps

Techniques

Define activities Sequence activities Estimate time Develop schedule

Gantt chart CPM PERT Microsoft Project

Copyright 2006 John Wiley & Sons, Inc.

9-9

Gantt Chart
Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack

amount of time an activity can be delayed without delaying the project

Copyright 2006 John Wiley & Sons, Inc.

9-10

Example of Gantt Chart


0
Activity Design house and obtain financing Lay foundation Order and receive materials Build house

Month 4

10

Select paint
Select carpet Finish work

3 Month

Copyright 2006 John Wiley & Sons, Inc.

9-11

Project Control
Time management Cost management Quality management Performance management

Earned Value Analysis

a standard procedure for numerically measuring a projects progress, forecasting its completion date and cost and measuring schedule and budget variation

Communication Enterprise project management

Copyright 2006 John Wiley & Sons, Inc.

9-12

CPM/PERT
Critical Path Method (CPM)

DuPont & Remington-Rand (1956) Deterministic task times Activity-on-node network construction

Project Evaluation and Review Technique (PERT)


US Navy, Booz, Allen & Hamilton Multiple task time estimates Activity-on-arrow network construction
9-13

Copyright 2006 John Wiley & Sons, Inc.

Project Network
Activity-on-node (AON)

nodes represent activities, and arrows show precedence relationships


1

Node
2 3

Activity-on-arrow (AOA)

arrows represent activities and nodes are events for points in time completion or beginning of an activity in a project

Event

Branch

Copyright 2006 John Wiley & Sons, Inc.

9-14

AOA Project Network for a House


3
2 0

Lay foundation

Dummy

3
Design house and obtain financing

1
Order and receive materials

Build house

Finish work

4
Select paint 1

3 1

6
Select carpet

Copyright 2006 John Wiley & Sons, Inc.

9-15

Concurrent Activities
Lay foundation

3
Lay foundation Dummy 2 1 Order material (b) Correct precedence relationship 0

3 2

Order material

(a) Incorrect precedence relationship

Copyright 2006 John Wiley & Sons, Inc.

9-16

AON Network for House Building Project


Lay foundations Build house

2 2 Start 1 3 3 1 5 1

4 3

Finish work

7 1 6 1
Select carpet

Design house and obtain financing

Order and receive materials

Select paint

Copyright 2006 John Wiley & Sons, Inc.

9-17

Critical Path
2 2 Start 1 3 3 1 5 1 6 1 4 3 7 1

A: B: C: D:

1-2-4-7 3 + 2 + 3 + 1 = 9 months 1-2-5-6-7 3 + 2 + 1 + 1 + 1 = 8 months 1-3-4-7 3 + 1 + 3 + 1 = 8 months 1-3-5-6-7 3 + 1 + 1 + 1 + 1 = 7 months

Critical path

Longest path through a network Minimum project completion time


9-18

Copyright 2006 John Wiley & Sons, Inc.

Activity Start Times


Start at 5 months

2 2
Start

4 3

Finish at 9 months

1 3 3 1
Start at 3 months

7 1 6 1
Start at 6 months

Finish

5 1

Copyright 2006 John Wiley & Sons, Inc.

9-19

Mode Configuration
Activity number Earliest start

Earliest finish

1
3

0
0

3
3
Latest finish

Activity duration

Latest start

Copyright 2006 John Wiley & Sons, Inc.

9-20

Forward Pass
Start at the beginning of CPM/PERT network to determine the earliest activity times Earliest Start Time (ES)

earliest time an activity can start ES = maximum EF of immediate predecessors earliest time an activity can finish earliest start time plus activity time

Earliest finish time (EF)


EF= ES + t

Copyright 2006 John Wiley & Sons, Inc.

9-21

Earliest Activity Start and Finish Times


Lay foundations

Build house
Start

2 2 1 1 0 3

5 4 3 5 8

7
1 6 3 3 4 5 1
Select pain

Design house and obtain financing

Finish work

1 5 6
Select carpet

1
Order and receive materials

Copyright 2006 John Wiley & Sons, Inc.

9-22

Backward Pass
Determines latest activity times by starting at the end of CPM/PERT network and working forward Latest Start Time (LS)

Latest time an activity can start without delaying critical path time

LS= LF - t
Latest finish time (LF)

latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors

Copyright 2006 John Wiley & Sons, Inc.

9-23

Latest Activity Start and Finish Times


Lay foundations Build house Start

2
2 1 0 3

3
3

5
5 4 3 5 5 8 8 7 8 9

3
6 3 1 3 4 4 5 1 6 7 7 8

Design house and obtain financing

Finish work

5
1

5
6

6
7
Select carpet

Order and receive materials

Select pain

Copyright 2006 John Wiley & Sons, Inc.

9-24

Activity Slack
Activity
*1 *2 3 *4 5 6 *7

LS
0 3 4 5 6 7 8

ES
0 3 3 5 5 6 8

LF
3 5 5 8 7 8 9

EF
3 5 4 8 6 7 9

Slack S
0 0 1 0 1 1 0

* Critical Path

Copyright 2006 John Wiley & Sons, Inc.

9-25

Probabilistic Time Estimates


Beta distribution

a probability distribution traditionally used in CPM/PERT a + 4m + b Mean (expected time): t= 6 Variance: where a = optimistic estimate m = most likely time estimate b = pessimistic time estimate

b-a = 6

Copyright 2006 John Wiley & Sons, Inc.

9-26

Examples of Beta Distributions


P(time) P(time)

t
Time

a
Time

P(time)

a
Copyright 2006 John Wiley & Sons, Inc.

m=t
Time

b
9-27

Project Network with Probabilistic Time Estimates: Example


Equipment installation

1
6,8,10 System development

Equipment testing and modification System training Final debugging 10 1,4,7 11

2,4,12

8
Manual testing 3,7,11

Start

2
3,6,9 Position recruiting

Finish

5
2,3,4 Job Training

9
2,4,6 System testing

1,10,13 System changeover

3
1,3,5

6
3,4,5 Orientation

7
2,2,2

Copyright 2006 John Wiley & Sons, Inc.

9-28

Activity Time Estimates


TIME ESTIMATES (WKS) ACTIVITY MEAN TIME VARIANCE

a 6 3 1 2 2 3 2 3 2 1 1

m 8 6 3 4 3 4 2 7 4 4 10

b 10 9 5 12 4 5 2 11 6 7 13

t 8 6 3 5 3 4 2 7 4 4 9

2 0.44 1.00 0.44 2.78 0.11 0.11 0.00 1.78 0.44 1.00 4.00

1 2 3 4 5 6 7 8 9 10 11

Copyright 2006 John Wiley & Sons, Inc.

9-29

Activity Early, Late Times, and Slack


ACTIVITY

t 8 6 3 5 3 4 2 7 4 4 9

0.44 1.00 0.44 2.78 0.11 0.11 0.00 1.78 0.44 1.00 4.00

ES

EF

LS

LF

1 2 3 4 5 6 7 8 9 10 11

0 0 0 8 6 3 3 9 9 13 16

8 6 3 13 9 7 5 16 13 17 25

1 0 2 16 6 5 14 9 12 21 16

9 6 5 21 9 9 16 16 16 25 25

1 0 2 8 0 2 11 0 3 8 0

Copyright 2006 John Wiley & Sons, Inc.

9-30

Earliest, Latest, and Slack


1 0 8 1
8

4 8 5 16 21 8 9 7 9 5 6 3 6
9 16

13

Critical Path
10 13 17

1 0

3
Finish

Start

2 0 6 0

16
11 16 25

9
7

3 0 3 2

6 3 4 5

9 9 13 4 12 16

9 16 25

7 3 5 2 14 16

Copyright 2006 John Wiley & Sons, Inc.

9-31

Total project variance 2 = 22 + 52 + 82 + 112 = 1.00 + 0.11 + 1.78 + 4.00 = 6.89 weeks

Copyright 2006 John Wiley & Sons, Inc.

9-32

Probabilistic Network Analysis


Determine probability that project is completed within specified time Z= where x-

= tp = project mean time = project standard deviation


x = proposed project time Z = number of standard deviations x is from mean

Copyright 2006 John Wiley & Sons, Inc.

9-33

Normal Distribution Of Project Time


Probability

= tp
Copyright 2006 John Wiley & Sons, Inc.

Time
9-34

Southern Textile Example


What is the probability that the project is completed within 30 weeks?
P(x 30 weeks)

= 6.89 weeks
2

Z=
=

x-

6.89

= 2.62 weeks
= 25 x = 30
Time (weeks)

30 - 25 2.62

= 1.91
From Table A.1, (appendix A) a Z score of 1.91 corresponds to a probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719
Copyright 2006 John Wiley & Sons, Inc. 9-35

Southern Textile Example


What is the probability that the project is completed within 22 weeks? x- 2 = 6.89 weeks Z= P(x 22 weeks)

6.89

= 2.62 weeks
x = 22 = 25

22 - 25 2.62

= -1.14
Time (weeks)

From Table A.1 (appendix A) a Z score of -1.14 corresponds to a probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271
Copyright 2006 John Wiley & Sons, Inc. 9-36

Project Crashing
Crashing

reducing project time by expending additional resources


an amount of time an activity is reduced cost of reducing activity time reduce project duration at minimum cost
9-37

Crash time

Crash cost

Goal

Copyright 2006 John Wiley & Sons, Inc.

Project Crashing: Example


2 8 1
12

4
12

7 4
3 4 6 4

5 4

Copyright 2006 John Wiley & Sons, Inc.

9-38

Project Crashing: Example (cont.)


$7,000 $6,000
Crash cost

$5,000 $4,000

Crashed activity Slope = crash cost per week

$3,000
$2,000 $1,000
Crash time

Normal activity

Normal cost

Normal time

| 2

| 4

| 6

| 8

| 10

| 12

| 14

Weeks

Copyright 2006 John Wiley & Sons, Inc.

9-39

Normal Activity and Crash Data


NORMAL TIME (WEEKS) CRASH TIME (WEEKS) NORMAL COST CRASH COST TOTAL ALLOWABLE CRASH TIME (WEEKS) CRASH COST PER WEEK

ACTIVITY

1 2 3 4 5 6 7

12 8 4 12 4 4 4

7 5 3 9 1 1 3

$3,000 2,000 4,000 50,000 500 500 15,000

$5,000 3,500 7,000 71,000 1,100 1,100 22,000

5 3 1 3 3 3 1

$400 500 3,000 7,000 200 200 7,000

$75,000
Copyright 2006 John Wiley & Sons, Inc.

$110,700
9-40

$500
2 8 1
12

$7000 4
12

$700 7 4 6 4 $200 $500 2 8

Project Duration: 36 weeks

FROM

$400

3 4 $3000

5 4 $200

$7000 4
12

$700

TO
Project Duration: 31 weeks Additional Cost: $2000

1
7

7 4
6 4 $200

$400

3 4

5 4 $200

$3000

Copyright 2006 John Wiley & Sons, Inc.

9-41

Time-Cost Relationship
Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs

Copyright 2006 John Wiley & Sons, Inc.

9-42

Time-Cost Tradeoff
Minimum cost = optimal project time Total project cost Indirect cost Cost ($)

Direct cost Crashing Project duration Time

Copyright 2006 John Wiley & Sons, Inc.

9-43

Copyright 2006 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permission Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein.
Copyright 2006 John Wiley & Sons, Inc. 9-44

Anda mungkin juga menyukai