Project Management
Operations Management - 5th Edition
Roberta Russell & Bernard W. Taylor, III
Lecture Outline
Project Planning Project Scheduling Project Control CPM/PERT Probabilistic Activity Times Project Crashing and Time-Cost Trade-off
Copyright 2006 John Wiley & Sons, Inc. 9-2
What is a Project?
Project
Examples
9-3
Project Elements
Objective Scope Contract requirements Schedules Resources Personnel Control Risk and problem analysis
9-4
made up of individuals from various areas and departments within a company a team structure with members from functional areas, depending on skills required
Matrix organization
Project Manager
9-5
Project Scope
Scope statement
Statement of work
9-7
a chart that shows which organizational units are responsible for work items shows who is responsible for work in a project
9-8
Project Scheduling
Steps
Techniques
9-9
Gantt Chart
Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack
9-10
Month 4
10
Select paint
Select carpet Finish work
3 Month
9-11
Project Control
Time management Cost management Quality management Performance management
a standard procedure for numerically measuring a projects progress, forecasting its completion date and cost and measuring schedule and budget variation
9-12
CPM/PERT
Critical Path Method (CPM)
DuPont & Remington-Rand (1956) Deterministic task times Activity-on-node network construction
US Navy, Booz, Allen & Hamilton Multiple task time estimates Activity-on-arrow network construction
9-13
Project Network
Activity-on-node (AON)
Node
2 3
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points in time completion or beginning of an activity in a project
Event
Branch
9-14
Lay foundation
Dummy
3
Design house and obtain financing
1
Order and receive materials
Build house
Finish work
4
Select paint 1
3 1
6
Select carpet
9-15
Concurrent Activities
Lay foundation
3
Lay foundation Dummy 2 1 Order material (b) Correct precedence relationship 0
3 2
Order material
9-16
2 2 Start 1 3 3 1 5 1
4 3
Finish work
7 1 6 1
Select carpet
Select paint
9-17
Critical Path
2 2 Start 1 3 3 1 5 1 6 1 4 3 7 1
A: B: C: D:
Critical path
2 2
Start
4 3
Finish at 9 months
1 3 3 1
Start at 3 months
7 1 6 1
Start at 6 months
Finish
5 1
9-19
Mode Configuration
Activity number Earliest start
Earliest finish
1
3
0
0
3
3
Latest finish
Activity duration
Latest start
9-20
Forward Pass
Start at the beginning of CPM/PERT network to determine the earliest activity times Earliest Start Time (ES)
earliest time an activity can start ES = maximum EF of immediate predecessors earliest time an activity can finish earliest start time plus activity time
EF= ES + t
9-21
Build house
Start
2 2 1 1 0 3
5 4 3 5 8
7
1 6 3 3 4 5 1
Select pain
Finish work
1 5 6
Select carpet
1
Order and receive materials
9-22
Backward Pass
Determines latest activity times by starting at the end of CPM/PERT network and working forward Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors
9-23
2
2 1 0 3
3
3
5
5 4 3 5 5 8 8 7 8 9
3
6 3 1 3 4 4 5 1 6 7 7 8
Finish work
5
1
5
6
6
7
Select carpet
Select pain
9-24
Activity Slack
Activity
*1 *2 3 *4 5 6 *7
LS
0 3 4 5 6 7 8
ES
0 3 3 5 5 6 8
LF
3 5 5 8 7 8 9
EF
3 5 4 8 6 7 9
Slack S
0 0 1 0 1 1 0
* Critical Path
9-25
a probability distribution traditionally used in CPM/PERT a + 4m + b Mean (expected time): t= 6 Variance: where a = optimistic estimate m = most likely time estimate b = pessimistic time estimate
b-a = 6
9-26
t
Time
a
Time
P(time)
a
Copyright 2006 John Wiley & Sons, Inc.
m=t
Time
b
9-27
1
6,8,10 System development
2,4,12
8
Manual testing 3,7,11
Start
2
3,6,9 Position recruiting
Finish
5
2,3,4 Job Training
9
2,4,6 System testing
3
1,3,5
6
3,4,5 Orientation
7
2,2,2
9-28
a 6 3 1 2 2 3 2 3 2 1 1
m 8 6 3 4 3 4 2 7 4 4 10
b 10 9 5 12 4 5 2 11 6 7 13
t 8 6 3 5 3 4 2 7 4 4 9
2 0.44 1.00 0.44 2.78 0.11 0.11 0.00 1.78 0.44 1.00 4.00
1 2 3 4 5 6 7 8 9 10 11
9-29
t 8 6 3 5 3 4 2 7 4 4 9
0.44 1.00 0.44 2.78 0.11 0.11 0.00 1.78 0.44 1.00 4.00
ES
EF
LS
LF
1 2 3 4 5 6 7 8 9 10 11
0 0 0 8 6 3 3 9 9 13 16
8 6 3 13 9 7 5 16 13 17 25
1 0 2 16 6 5 14 9 12 21 16
9 6 5 21 9 9 16 16 16 25 25
1 0 2 8 0 2 11 0 3 8 0
9-30
4 8 5 16 21 8 9 7 9 5 6 3 6
9 16
13
Critical Path
10 13 17
1 0
3
Finish
Start
2 0 6 0
16
11 16 25
9
7
3 0 3 2
6 3 4 5
9 9 13 4 12 16
9 16 25
7 3 5 2 14 16
9-31
Total project variance 2 = 22 + 52 + 82 + 112 = 1.00 + 0.11 + 1.78 + 4.00 = 6.89 weeks
9-32
9-33
= tp
Copyright 2006 John Wiley & Sons, Inc.
Time
9-34
= 6.89 weeks
2
Z=
=
x-
6.89
= 2.62 weeks
= 25 x = 30
Time (weeks)
30 - 25 2.62
= 1.91
From Table A.1, (appendix A) a Z score of 1.91 corresponds to a probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719
Copyright 2006 John Wiley & Sons, Inc. 9-35
6.89
= 2.62 weeks
x = 22 = 25
22 - 25 2.62
= -1.14
Time (weeks)
From Table A.1 (appendix A) a Z score of -1.14 corresponds to a probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271
Copyright 2006 John Wiley & Sons, Inc. 9-36
Project Crashing
Crashing
Crash time
Crash cost
Goal
4
12
7 4
3 4 6 4
5 4
9-38
$5,000 $4,000
$3,000
$2,000 $1,000
Crash time
Normal activity
Normal cost
Normal time
| 2
| 4
| 6
| 8
| 10
| 12
| 14
Weeks
9-39
ACTIVITY
1 2 3 4 5 6 7
12 8 4 12 4 4 4
7 5 3 9 1 1 3
5 3 1 3 3 3 1
$75,000
Copyright 2006 John Wiley & Sons, Inc.
$110,700
9-40
$500
2 8 1
12
$7000 4
12
FROM
$400
3 4 $3000
5 4 $200
$7000 4
12
$700
TO
Project Duration: 31 weeks Additional Cost: $2000
1
7
7 4
6 4 $200
$400
3 4
5 4 $200
$3000
9-41
Time-Cost Relationship
Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs
9-42
Time-Cost Tradeoff
Minimum cost = optimal project time Total project cost Indirect cost Cost ($)
9-43
Copyright 2006 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permission Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein.
Copyright 2006 John Wiley & Sons, Inc. 9-44