IMPORATANT ASPECTS
SKB
SKB
SKB
CC
COMP
GAS TURBINE
GUILOTINE DAMPER
S T A C K
H R S G
DIFFUSER
OPEN CYCLE GT EFFICIENCY IS LOW. WITH HIGH COST OF FUEL, OPEN CYCLE MODE FOR GT OPERATION IS UNACCEPTABLE. GT EXHAUST TEMPERATURE IN ADVANCE CLASS GT SUCH AS FRAME 9FA IS IN EXCESS OF 600C HENCE IS NEVER RUN IN OPEN CYCLE MODE. THIS, PERHAPS, IS THE REASON THAT AT COMBINED CYCLE PLANT SUCH AS AT VEMAGIRI WE DO NOT HAVE BYPASS STACK
HIGH GT EXHAUST TEMPERATURE PUTS VERY SEVERE OPERATING CONDITIONS ON HRSG. OUTAGE OF HRSG THEREFORE FORCES SHUT-DOWN OF THE GT.
SKB
M A I N S T A C K
INLET DUCT
HPSH
LPEV
LPEC
SKB
EVA
SH
TURNING VANES
SKB
FOR LOW SULFUR FUELS DESIGN STACK TEMPERATURE CAN BE 120 130 C AND FOR VERY CLEAN FUELS SUCH AS NATURAL GAS, IT CAN BE AS LOW AS 100 110 C.
ACTUAL STACK TEMPERATURE VERY NEAR DESIGN TEMPERATURE INDICATES VERY STRONG POSSIBLITY OF EXCELLENT HEAT TRANSFER IN THE HEAT EXCHANGER TRAINS IN THE FLUE GAS PATH.
SKB
SKB
INSULATION
BOTH INLET DUCT AS WELL AS BOILER CASING REQUIRES INSULATION AS THE GAS TEMPERATURES ARE VERY HIGH ( OF THE ORDER OF 600+C) THE INSULATION CAN BE INTERNAL OR EXTERNAL FOR FLUE GAS TEMPERAURE > 570C, USE OF EXTERNAL INSULATION WILL REQUIRE USE OF AUSTENITIC STEELS WHICH ARE QUITE EXPENSIVE AND ALSO DIFFICULT TO WELD. THEY ARE ALSO LIABLE TO STRESS RELIEF CRACKING. ALSO ALLUMINIUM CLADDING IS REQUIRED TO MINIMIZE HEAT LOSS AS WELL AS FOR PROTECTION FROM WEATHER EFFECTS. APPARENTLY EXTERNAL INSULATION IS MORE PROBLEMATIC.
SKB
INSULATION ..
DURING ITS PASSAGE, THE FLUE GAS COOLS DOWN. THUS IN EXTERNALLY INSULATED HRSG, CHEAPER ALLOY STEELS CAN BE USED IN LOW TEMPERATURE ZONE. HOWEVER THIS NECESSIATES USE OF EXPANSION JOINT TO TAKE CARE OF DIFFERENTIAL COEFFICIENTS OF EXPANSION EXPANSION JOINTS PROVIDED FOR ABOVE MENTIONED PURPOSE AT TIMES, IS A SOURCE OF SEVERAL COMPLEX PROBLEMS PERSONALLY RECOMMEND INTERNAL INSULATION ONLY.
SKB
INTERNAL INSULATION
USE OF CHEAPER MATERIAL OF CONSTUCTION OF INLET DUCT AND BOILER CASING NO NECESSITY OF LARGE FLEXIBLE JOINTS IN BOILER CASING AS ARE REQUIRED FOR EXTERNAL INSULATION TUBE LEAKS IN EVAPORATOR CAN CAUSE IMPINGEMENT OF HIGH VELOCITY JETS ON ROOF INSULATION. GAPS IN INSULATION CAN CAUSE HOT SPOTS AND DISTORTIONS
SKB
LAYOUT
PLAYS A VERY IMPORTANT ROLE FROM FLOW DISTRIBUTION POINT OF VIEW. IN CASE OF CONSTRAINTS IN THE PLOT SIZE, THE GT EXHAUST CAN BE AT RIGHT ANGLE TO THE DIFFUSER. CONSEQUENTLY FLOW CORRECTORS SUCH AS TURNING VANES ARE REQUIRED TO BE INSTALLED. ANY ERRORS IN DESIGN & ERECTION OF THESE CAN CAUSE SEVERE DISTORTION OF BOILER DUCT. IN CASE IT IS NOT POSSIBLE TO MAKE DIFFUSER AND THE BOILER INLET DUCT CO-LINEAR, FLOW STABILIZERS SUCH AS PERFORATED PLATE OR TURNING VANES MUST BE PROVIDED. A NON-UNIFORM FLOW DISTRIBUTION WILL OFTEN CAUSE STRUCTURAL DEFORMATION AND FAILURES OF BOILER CASING AND ALSO PRESSURE PARTS. THIS GREATLY REDUCES EFFECTIVE LIFE OF HRSG.
SKB
BYEPASS STACK
DAMPER
DIFFUSER
IDEAL LAYOUT
SKB
SKB
BYEPASS STACK
DIFFUSER
Cold bottom
EFFECT OF OFFSET IS TO CAUSE DUCT TO DISTORT AND ALSO MAY CAUSE FAILURE OF THE JOINT
SKB
CASE STUDY : OFFSET BOILER INLET DUCT AND USE OF DIFFERENT MATERIALS FOR BOILER CASING
ALLOY STEEL
FAILURES OF JOINT
SKB
SKB
BYEPASS STACK
DAMPER
TURNING VANE
DIFFUSER
SKB
BYEPASS STACK
DAMPER
PERFORATED PLATE
TURNING VANE
DIFFUSER
TURNING VANES
SKB
HRSG DUCT
SKB
SKB
SKB
SKB
CC
STEAM TO STG
COMP
GAS TURBINE
GUILOTINE DAMPER
422C
S T A C K
155 MIN
H R S G
T E M P E R A T U R E
60C DROP
GT SYNCRONIZED
DIFFUSER
COLD START GT EXHAUST TEMP PROFILE. THE HRSG PARTS WILL EXPERIENCE THIS IN EVERY COLD START
~18 min.
11 min
TIME
SKB
SKB
SKB
CONCLUSIONS
HRSG IS A CRITICAL CONSTITUENT OF COMBINED CYCLE POWER PLANTS SINCE ITS OUTAGE MEANS A TREMENDOUS DROP IN THE HEAT RATE OF THE OVERALL PLANT AND GENERATION COST BECOME PROHIBITIVLY HIGH IT IS NECESSARY TO GIVE TOP PRIORITY TO LAY OUT RELATED ISSUES. IN CASE IT IS NOT POSSIBLE TO KEEP GT AND HRSG CO-LINEAR, FLOW STRAIGHTENING DEVICES MUST BE INSTALLED. MAJORITY OF THE PROBLEMS SUCH AS BUCKLING OF DUCT/BOILER CASING ARE DUE TO FLOW IMBALANCES. DEVICES SUCH AS TURNING VANES, PERFORATED PLATES MUST BE USED TO REMOVE THESE IMBALANCES. HEAT TRANSFER AND TEMPERATURE DISTRIBUTION IN THE FLUE GAS PATH ARE THE MOST IMPORTANT PARAMETERS THAT DECIDE RELIABILITY AND AVAILABILITY OF HRSG
SKB
GT EXH. TEMP TG
SUPPOSE 140000 lb/hr GAS AT TEMP.980F ENTERS HRSG GENERATING STEAM AT 200 psi. FEED WATER TEMP. IS 230 F , BLOW DOWN 5%. ASUME SP.HEAT OF GAS AT EVAPORATOR 0.27 AND AT ECONOMIZER 0.253. LET US SIMULATE THERMAL DESIGN. NORMALLY PINCH POINT AND APPROACH TEMP. IS IN THE RANGE 15-30 F.LET US CHOOSE 20 FOR PINCH AND 15 FOR APPROACH. SATURATION TEMP. =388. THERFORE GAS TEMP LEAVING EVAPORATOR = 388+20=408.TEMP OF WATER ENTERING EVA.=38815=373 F.
PINCH POINT
STACK TEMP T2
APPROACH TEMP.
ASSUMING 1% LOSS, EVAPORATOR DUTY = 140000.0.99.0.27.(980-408) =21.4MMBTU/hr.ENTHALPY ABOSRBED BY STEAM =(1199-345)+0.05.(362-345) =855 BTU/lb. STEAM GENERATED = 21.106/855 = 25000lb/hr. ECONOMIZER DUTY =25000.1.05.(345-198) = 3.84.106BTU/hr. GAS TEMPERATURE DROP = 3840000 / (140000.0.253.0.99) = 109F. TEMPERATURE OF GAS LEAVING THE STACK =408 -109 = 299 F ~ 150C. WE THUS HAVE SIMULATED THE DESIGN. KNOWING THE GAS TEMPERATURE PROFILE AND WATER/ STEAM PARAMETERS, WE CAN JUDGE THE PERFORMANCE OF HRSG.
ECO IN t1
SKB
SUPPOSE 140000 lb/hr GAS AT TEMP.980F ENTERS HRSG GENERATING STEAM AT P. FEED WATER TEMP. IS 230 F. ASUME SP.HEAT OF GAS AT EVAPORATOR 0.27 AND AT ECONOMIZER 0.253. LET US EVALUATE THE EXIT GAS TEMPERATURES FOR VARIOUS STEAM PRESSURES. WgCPg(Tg1 Tg3) = WS(hso hw2) IN SH AND EVAPORATOR ZONE. CONSIDERING NOW THE ENTIRE HRSG
Tg3
PINCH POINT
WgCPg(Tg1-Tg4) = WS(hso-hw1) FROM THE ABOVE EQUATIONS WE OBTAIN (Tg1-Tg3) / (Tg1-Tg4) = (hso-hw2) / (hso-hw1) = X. WE NOW EVLUATE EFFECT OF INCREASING STEAM PRESSURE FROM 100 TO 600 PSI ON STACK TEMPERAURE. PRESS STEAM T SAT.T X 100 250 400 400 600 600 SAT SAT SAT 600 SAT 750 EXIT T 338 0.904 300 406 0.833 313 448 0.790 353 448 0.800 367 490 0.740 373 490 0.773 398
ECO IN tw1
THIS SHOWS CLEARLY THE REASON FOR MULTIPLE PRESSURE WHEN MAIN STEAM PRESSURE IS HIGH SO THAT BEST HEAT EXTRACTION FROM FLUE GAS IS POSSIBLE
SKB
A CASE STUDY
SKB
SKB
593C 545.5
564
DESIGN
ACTUAL
335 282 317 271 174 211 160
260
SH1
SH2
HPEV
HPEC
IPEV
HP/IPECO
SKB
194
189
181
207
IPECO HPECO
333 350
HPECO IPECO
307 306
THE TEMPERATURE DISTRIBUTION SHOWS A VERY HIGH BIAS OF FLUE GAS FLOW TOWARDS IPECO SIDE. TEMPERATURE DROP ACROSS IPEV NOT PROPER IPECO CONTINUES TO STEAM HEAT PICK UP IN HPEV IS QUITE LESS AND LESS STEAM IS GENERATED NECESSARY TO INCREASE HP FEED FLOW HEAVY ATTEMPERATION IN SH TO CONTROL SH TEMPERATURE
IPEV
322 292
IPEV
287 354
HPECO
361 352
HPECO HPEVA
328 368
HPEVA
482 452
NA
467
SH1 SH2
560
SH1 SH2
564
SKB
SKB
30 B,115C,13.3 / 23.5,121,14
IPECO HPECO
333 350
TO HPECO2
HPECO IPECO
307 306
IPEV
322 292
IPEV
287 119,301,57 121,302,71 452 NA 354
29,250,12.2 / 23.5,198,14
HPECO
361 352
HPECO HPEVA
328 368
P ACROSS HPECO = 9 BAR ?? HP/IP FEED TEMP. 115 AGAINST 121. IP STEAM TO PROCESS AT A TEMPARATURE OF 190 AGAINST 200.7C. LOW DEAERATOR PRESSURE WHICH CAN INCREASE HP STEAM PARAMETERS TO ST ARE 72 BAR, 494 C AND 57 TPH AGAINST 98 B, 514 AND 71TPH
HPEVA
482
467
SH1 SH2
560
SH1 SH2
564
PERFORATED PLATE
SUGGESTIONS
INSTALL FLOW STRAIGHTNER INSTALL PERFORATED PLATE INCREASE DEAERATOR PRESS. INVESTIGATE AND CORRECT EXCESSIVE PRESSURE DROP IN HP FEED LINE INCREASE HPEVA AREA (10%)
FLOW STRAIGHTNER
TURNING VANES
SKB
593C 545.5
564
DESIGN
ACTUAL
ACHIEVABLE
317
335
282
260
SH1
SH2
HPEV
HPEC
IPEV
HP/IPECO
SKB
CASE STUDY
SKB
SKB
MODULE 2
MODULE 3
LP BOILER 2 TRAINS HP ECONOMIZER 1 TRAIN DA BOILERS 4 TRAINS FAILURES AT TOP BENDS IN THE LAST TRAIN OF DA BOILER HIGH STACK TEMPERATURE
SKB
600
500
400
300
HIGH HEAT PICK UP IN SH1 LESS IN SH2 VERY LOW HEAT PICK UP IN DA BOILER. VERY LOW T ACROSS LPSH (~1.6C DESIGN). LOW T ACROSS HPE1 AND HPE2
TACT 63 35 180 35 33 10 20
DIF -54 27 ~ 24 ~ 10 24
SKB
200
100
SH1
SH2
HPB
HPE1
LPSH
LPB
HPE2
DA BOILER
RECOMMENDATIONS
OUTER MOST EXPERIENCES MINIMUM GAS TEMPERATURE. ADDITIONALLY THIS TUBE RECEIVES MAXIMUM WATER FLOW. THE TUBE THERFORE HAS LARGE WATER CONTENT. THIS WATER CAUSES IMPINGEMENT AND THINNING OF THE TUBE BY EROSION. THE LAST ROW CAN BE TOTALLY REMOVED SINCE THE REMINING THREE ROWS ARE SUFFICIENT IT IS BETTER TO REMOVE ABOUT 10% TUBES IN SH1 7-10% INCREASE HPECO2 SURFACE AREA
SKB
5 BURNERS
SCREEN TUBES
FIRED HRSG
SKB
SKB
SKB
CONCLUSIONS
COMPARED TO CONVENTIONAL COAL FIRED BOILER LIFE EXPENDITURE IN HRSG IS VERY FAST DUE TO FACTORS SUCH AS RAPID START UP AND VERY HIGH LOADING RATES. HRSG DESIGNS FOR THIS PURPOSE ARE REQUIRED TO BE TAILOR MADE SO THAT THE AGGRESSIVE START UPS AS WELL AS LOADING RATES DO NOT CAUSE PREMATURE FAILURES AND LIFE EXPIRY. COMPARED TO CONVENTIONAL BOILER R&M ACTIVITIES FOR HRSG MUST START MUCH EARLIER.WE CAN IDENTIFY THE PROBLEM AREAS IN HRSG BY STUDYING THE PRESENT FLUE GAS TEMPERATURE PROFILE, WATER AND STEAM PARAMETERS WITH REFERENCE TO THE SAME AS GIVEN IN HMBD SUPPLIED BY OEM. STACK TEMPERATURE IS ONE PARAMETER WHICH TO A LARGE EXTENT WOULD INDICATE THE QUALITY OF PERFORMANCE OF THE HRSG
SKB