PRESENTATION ON ERECTION OF BOILER

KIRAN KUMAR ONI

BOILER PACKAGES Structures Pressure parts Non pressure parts Ducting Rotating equipment ESP

Structure for handling of Eco. Coils from Zero mtr. to 43.5 mtrs

COLUMN ERECTION
In order to have a strong and safe structural footing the columns are to be erected very carefully. It can not be transported and erected in single piece. Utmost care is taken in the pre-assembly stage to maintain the matching of column end faces & to achieve verticality with in tolerance limits.

COLUMN ERECTION

COLUMN ERECTION
Once the column erection is over up to the full height, the cross beams are placed securely over the columns which supports the main boiler. After that anchor point called ceiling girder on the top of the boiler is constructed on all the sides of the boiler so that load transfer could take place

In the process of Modulization of Boiler Furnace & Back Pass on the ground S/S Heavy Girder installation (Using Crane) 2 month after Starting S/S

Heavy Girder Lifting

S/S Heavy Girder installation (Using Crane) 6 month after starting S/S

Heavy Girder Installation

Heavy Girder Installation

Module Assy on the Ground

Modulization/Concurrent Erection Method

Typical Construction Method

? ?

? ?

Sequence of Modulization / Concurrent Installation


Install Heavy Girder after Panel Erection

BOILER DRUM ERECTION


WORKS TO BE COMPLETED BEFORE LIFTING THE BOILER DRUM AUXILARY PREPARATION WORK FOR DRUM LIFTING welding of cat head structure at roof level making ready of winches with anchoring arrangements fixing of main pulleys, auxiliary pulleys &guide pulleys

TECHNICAL DETAILS DRUM over all length : 24.216m weight (with out internals) : 234MT Elevation (drum center) : 72.508m No.of lifting lungs : 2 (for stage I lifting) : 2 (for stage II lifting) No.of suspension rod U-type : 2 length&width of pulley blocks : 1700&700mm

BOILER DRUM LIFTING


Drum is to be lifted in horizontal position

Initially drum is to be lifted at a height of 68mtrs The level of the drum centre is to be verified by water level to ensure exact elevation of 72.511mtr

PRESSURE PARTS
Pressure parts is divided in to two passes Erection of headers and water wall panel One side of water wall require 35 to 40 panels Boiler walls are checked verticality and axially with respect to boiler drum position

CONSTRUCTIONOF HEADERS

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation


Install Heavy Girder after Panel Erection

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation

Assemble RH Final & SH Final Tube Module

Sequence of Modulization / Concurrent Installation

Install Jack for Drum

Sequence of Modulization / Concurrent Installation

DRUM LIFTING

Sequence of Modulization / Concurrent Installation

Install Downcomer pipes (6ea)

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation

Prepare the Assembling of SH DIV. Module

Assemble Back Pass Module (Hanger rods, roof panel, LTRH)

Sequence of Modulization / Concurrent Installation

Lift the Subassembled SH DIV. Module

Sequence of Modulization / Concurrent Installation

Install the Jack for SHP & RHP

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation

Install the Jack for Back Pass Module Lifting

Sequence of Modulization / Concurrent Installation

Install the Wire for Back Pass Module Lifting

Sequence of Modulization / Concurrent Installation

1st Lifting of Back Pass Module

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation

Assemble the Back Pass Wall Panel

Sequence of Modulization / Concurrent Installation

SH tube bundle lifting

Lower panel lifting Assemble Back Pass LTRH Arch lifting

Sequence of Modulization / Concurrent Installation

Sequence of Modulization / Concurrent Installation

Assemble Eco Tube, Eco Header

Sequence of Modulization / Concurrent Installation

Back Pass Module Final Lifting

Sequence of Modulization / Concurrent Installation

Install the Burner windbox, Low water panel, Hopper panel, Water inlet header, Suction inlet piping.