Anda di halaman 1dari 17

KEGIATAN : PENGEMBANGAN RUMAH SEHAT SEDERHANA

PEKERJAAN : PEMBANGUNAN RUMAH RUMAH SEHAT SEDERHANA 15 UNIT


LOKASI : KABUPATEN ACEH JAYA
NOMOR PAKET : RSS/AJA/OTS/255
TAHUN : 2009
JUMLAH HARGA
(Rp.)
A. PEKERJAAN PERSIAPAN 525,000.00
B. PEKERJAAN TANAH & PONDASI 3,907,637.00
C. PEKERJAAN BETON BERTULANG 9,613,266.60
D. PEKERJAAN PASANGAN DAN PLESTERAN 10,932,360.00
E. PEKERJAAN DINDING CALSIUM SILICATE BOARD -
F. PEKERJAAN LANTAI 1,032,541.40
G. PEKERJAAN ATAP DAN PLAFOND 20,555,550.60
H. PEKERJAAN KOSEN PINTU, JENDELA DAN KUNCI 7,163,296.00
I. PEKERJAAN PENGECATAN 3,222,991.00
J. PEKERJAAN INSTALASI LISTRIK 2,447,000.00
K. PEKERJAAN SANITAIR 2,701,000.00
Biaya Untuk 1 Unit 62,100,642.60
Dibulatkan 62,100,000.00
Total Biaya untuk 15 Unit 931,500,000.00
Terbilang : Sembilan Ratus Tiga Puluh Satu J uta Lima Ratus Ribu Rupiah
Teunom, 10 Juli 2009
Penawar,
CV. ELANG MAS
DASRIL A. RAHMAN IBRAHIM
Direktur
NO. URAIAN PEKERJAAN
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENGEMBANGAN RUMAH SEHAT SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH RUMAH SEHAT SEDERHANA 15 UNIT
LOKASI : KABUPATEN ACEH JAYA
NOMOR PAKET : RSS/AJA/OTS/255
TAHUN : 2009
1. SNI.T.01.2.a 1 m3 Galian Tanah Biasa Sedalam 1 M
0.0400 Mandor @ Rp. 52,000.00 Rp. 2,080.00
0.4000 Pekerja @ Rp. 37,000.00 Rp. 14,800.00
Jumlah Rp. 16,880.00
Dibulatkan Rp. 16,880.00
2. SNI.T.01.2.i 1 m3 Urugan Tanah Kembali
0.0190 Mandor @ Rp. 52,000.00 Rp. 988.00
0.1920 Pekerja @ Rp. 37,000.00 Rp. 7,104.00
Jumlah Rp. 8,092.00
Dibulatkan Rp. 8,090.00
3. SNI.T.02.1.n 1 m3 Urugan Pasir
1.2000 Pasir Urug @ Rp. 64,000.00 Rp. 76,800.00
0.3000 Pekerja @ Rp. 37,000.00 Rp. 11,100.00
0.0100 Mandor @ Rp. 52,000.00 Rp. 520.00
Jumlah Rp. 88,420.00
Dibulatkan Rp. 88,420.00
4. Anl. A.18 1 m3 Timbunan Tanah
1.2000 Tanah Timbunan @ Rp. 64,000.00 Rp. 76,800.00
0.3000 Pekerja @ Rp. 37,000.00 Rp. 11,100.00
0.0100 Mandor @ Rp. 52,000.00 Rp. 520.00
Jumlah Rp. 88,420.00
Dibulatkan Rp. 88,420.00
5. SNI.T.02.1.m 1 m3 Pasangan Batu Kosong (Aanstamping)
1.2000 Batu Belah @ Rp. 164,000.00 Rp. 196,800.00
0.3000 Pasir Urug @ Rp. 64,000.00 Rp. 19,200.00
0.0390 Mandor @ Rp. 52,000.00 Rp. 2,028.00
0.0390 Kepala Tukang @ Rp. 64,000.00 Rp. 2,496.00
0.3900 Tukang Batu @ Rp. 53,000.00 Rp. 20,670.00
0.7800 Pekerja @ Rp. 37,000.00 Rp. 28,860.00
Jumlah Rp. 270,054.00
Dibulatkan Rp. 270,050.00
6. SNI.T.02.1.d 1 m3 Pasangan Pondasi Batu Gunung / Batu Kali 1 : 4
1.1000 Batu Gunung @ Rp. 164,000.00 Rp. 180,400.00
0.5200 Pasir Pasang @ Rp. 69,000.00 Rp. 35,880.00
4.0750 Semen PC @ Rp. 46,000.00 Rp. 187,450.00
0.0750 Mandor @ Rp. 52,000.00 Rp. 3,900.00
0.0600 Kepala Tukang @ Rp. 64,000.00 Rp. 3,840.00
0.6000 Tukang Batu @ Rp. 53,000.00 Rp. 31,800.00
1.5000 Pekerja @ Rp. 37,000.00 Rp. 55,500.00
Jumlah Rp. 498,770.00
Dibulatkan Rp. 498,770.00
7. SNI.T.03.1.l 1 m2 Pasangan Bata Merah Teb. 1/2 Bata, 1 Pc : 2 Ps
70.0000 Batu Bata @ Rp. 510.00 Rp. 35,700.00
0.4738 Semen PC @ Rp. 46,000.00 Rp. 21,794.80
0.0380 Pasir Pasang @ Rp. 69,000.00 Rp. 2,622.00
0.0150 Mandor @ Rp. 52,000.00 Rp. 780.00
0.0100 Kepala Tukang @ Rp. 64,000.00 Rp. 640.00
0.1000 Tukang Batu @ Rp. 53,000.00 Rp. 5,300.00
0.3200 Pekerja @ Rp. 37,000.00 Rp. 11,840.00
Jumlah Rp. 78,676.80
Dibulatkan Rp. 78,680.00
Org
Org
DAFTAR ANALISA
Org
m3
Org
Org
m3
Org
m3
Org
Org
m3
Org
Org
Org
Org
m3
m3
Org
Org
Org
Org
zak
bh
zak
m3
Org
Org
Org
Org
8. SNI.T.03.1.n 1 m2 Pasangan Bata Merah Teb. 1/2 Bata, 1 Pc : 4 Ps
70.0000 Bata Merah @ Rp. 510.00 Rp. 35,700.00
0.2875 Semen PC @ Rp. 46,000.00 Rp. 13,225.00
0.0430 Pasir Pasang @ Rp. 69,000.00 Rp. 2,967.00
0.0150 Mandor @ Rp. 52,000.00 Rp. 780.00
0.0100 Kepala Tukang @ Rp. 64,000.00 Rp. 640.00
0.1000 Tukang Batu @ Rp. 53,000.00 Rp. 5,300.00
0.3200 Pekerja @ Rp. 37,000.00 Rp. 11,840.00
Jumlah Rp. 70,452.00
Dibulatkan Rp. 70,450.00
9. SNI.T.03.3.b 1 m2 Plesteran, 1 Pc : 2 Ps Teb. 15 mm
0.2130 Semen PC @ Rp. 46,000.00 Rp. 9,798.00
0.0170 Pasir Pasang @ Rp. 69,000.00 Rp. 1,173.00
0.0100 Mandor @ Rp. 52,000.00 Rp. 520.00
0.0150 Kepala Tukang @ Rp. 64,000.00 Rp. 960.00
0.1500 Tukang Batu @ Rp. 53,000.00 Rp. 7,950.00
0.2000 Pekerja @ Rp. 37,000.00 Rp. 7,400.00
Jumlah Rp. 27,801.00
Dibulatkan Rp. 27,800.00
10. SNI.T.03.3.d 1 m2 Plesteran, 1 Pc : 4 Ps Teb. 15 mm
0.1300 Semen PC @ Rp. 46,000.00 Rp. 5,980.00
0.0200 Pasir Pasang @ Rp. 69,000.00 Rp. 1,380.00
0.0100 Mandor @ Rp. 52,000.00 Rp. 520.00
0.0150 Kepala Tukang @ Rp. 64,000.00 Rp. 960.00
0.1500 Tukang Batu @ Rp. 53,000.00 Rp. 7,950.00
0.2000 Pekerja @ Rp. 37,000.00 Rp. 7,400.00
Jumlah Rp. 24,190.00
Dibulatkan Rp. 24,190.00
11. Anl. G.67 1 m3 Lantai Beton Tumbuk 1 : 3 : 5
0.8700 Batu Kerikil @ Rp. 69,000.00 Rp. 60,030.00
0.5200 Pasir Pasang @ Rp. 69,000.00 Rp. 35,880.00
5.4500 Semen PC @ Rp. 46,000.00 Rp. 250,700.00
0.0800 Mandor @ Rp. 52,000.00 Rp. 4,160.00
0.0250 Kepala Tukang @ Rp. 64,000.00 Rp. 1,600.00
0.2500 Tukang @ Rp. 53,000.00 Rp. 13,250.00
1.6500 Pekerja @ Rp. 37,000.00 Rp. 61,050.00
Jumlah Rp. 426,670.00
Dibulatkan Rp. 426,670.00
12. Anl. F.26 Mengerjakan 1 m3 Kayu untuk Kosen Jendela/Pintu
1.2000 Kayu Seumantok @ Rp. 2,668,000.00 Rp. 3,201,600.00
18.0000 Tukang @ Rp. 53,000.00 Rp. 954,000.00
2.0000 Kepala Tukang @ Rp. 64,000.00 Rp. 128,000.00
6.0000 Pekerja @ Rp. 37,000.00 Rp. 222,000.00
0.3000 Mandor @ Rp. 52,000.00 Rp. 15,600.00
Jumlah Rp. 4,521,200.00
Dibulatkan Rp. 4,521,200.00
13. Anl. F.38 Mengerjakan 1 m2 Papan Listplank
0.0110 Kayu Klas II @ Rp. 2,668,000.00 Rp. 29,348.00
0.0500 Paku Kayu @ Rp. 14,000.00 Rp. 700.00
0.2200 Tukang @ Rp. 53,000.00 Rp. 11,660.00
0.0220 Kepala Tukang @ Rp. 64,000.00 Rp. 1,408.00
0.1100 Pekerja @ Rp. 37,000.00 Rp. 4,070.00
0.0050 Mandor @ Rp. 52,000.00 Rp. 260.00
Jumlah Rp. 47,446.00
Dibulatkan Rp. 47,450.00
14. SNI.DT.91.0011.6.24 Memasang 1 m2 Dinding Pemisah
12.0000 Sekrup @ Rp. 100.00 Rp. 1,200.00
0.8600 Calsiboard 6 mm @ Rp. 74,000.00 Rp. 63,640.00
0.6000 Tukang @ Rp. 53,000.00 Rp. 31,800.00
0.0600 Kepala Tukang @ Rp. 64,000.00 Rp. 3,840.00
0.2000 Pekerja @ Rp. 37,000.00 Rp. 7,400.00
0.0100 Mandor @ Rp. 52,000.00 Rp. 520.00
Jumlah Rp. 108,400.00
Dibulatkan Rp. 108,400.00
bh
zak
m3
Org
Org
Org
Org
zak
m3
Org
Org
Org
Org
Org
zak
m3
Org
Org
Org
Org
m3
m3
zak
Org
Org
Org
m3
Org
Org
Org
Org
m3
kg
buah
lembar
Org
Org
Org
Org
Org
Org
Org
Org
15. SNI.DT.91.0011.6.10 1 m2 Jalusi Kusen
0.0600 Kayu Klas II @ Rp. 2,668,000.00 Rp. 160,080.00
0.1500 Paku Kayu @ Rp. 14,000.00 Rp. 2,100.00
2.0000 Tukang @ Rp. 53,000.00 Rp. 106,000.00
0.2000 Kepala Tukang @ Rp. 64,000.00 Rp. 12,800.00
0.5000 Pekerja @ Rp. 37,000.00 Rp. 18,500.00
0.0250 Mandor @ Rp. 52,000.00 Rp. 1,300.00
Jumlah Rp. 300,780.00
Dibulatkan Rp. 300,780.00
16. Anl. Supl. VII 1 m2 Plafond Multiplek 3 mm
0.3900 Multiplek 3 mm @ Rp. 64,000.00 Rp. 24,960.00
0.1000 Paku Biasa 2" - 5" @ Rp. 14,000.00 Rp. 1,400.00
0.0250 Kepala Tukang @ Rp. 64,000.00 Rp. 1,600.00
0.2500 Tukang Kayu @ Rp. 53,000.00 Rp. 13,250.00
0.1500 Pekerja @ Rp. 37,000.00 Rp. 5,550.00
0.0750 Mandor @ Rp. 52,000.00 Rp. 3,900.00
Jumlah Rp. 50,660.00
Dibulatkan Rp. 50,660.00
17. Anl. Supl. IXa 1 m2 Cat Tembok/Dinding/Plafond (3x)
0.2600 Cat Tembok 2x @ Rp. 15,600.00 Rp. 4,056.00
0.1000 Plamur @ Rp. 16,100.00 Rp. 1,610.00
0.1000 Cat Dasar @ Rp. 13,800.00 Rp. 1,380.00
0.0025 Mandor @ Rp. 52,000.00 Rp. 130.00
0.0630 Tukang Cat @ Rp. 53,000.00 Rp. 3,339.00
0.0063 Kepala Tukang @ Rp. 64,000.00 Rp. 403.20
0.0200 Pekerja @ Rp. 37,000.00 Rp. 740.00
Jumlah Rp. 11,658.20
Dibulatkan Rp. 11,660.00
18. Anl. K10+K23+K28 1 m2 Mengecat Kosen/Pintu/Jendela/Listplank/Kanopi
0.2000 Cat Menie @ Rp. 13,800.00 Rp. 2,760.00
0.1500 Plamur @ Rp. 16,100.00 Rp. 2,415.00
0.1700 Cat Dasar @ Rp. 13,800.00 Rp. 2,346.00
0.2600 Cat Warna 2x @ Rp. 18,400.00 Rp. 4,784.00
0.0090 Tukang Cat @ Rp. 53,000.00 Rp. 477.00
0.0060 Kepala Tukang @ Rp. 64,000.00 Rp. 384.00
0.0700 Pekerja @ Rp. 37,000.00 Rp. 2,590.00
0.0025 Mandor @ Rp. 52,000.00 Rp. 130.00
Jumlah Rp. 15,886.00
Dibulatkan Rp. 15,890.00
19. Anl. Supl.V 1 m3 Beton Bertulang
a. (Anl. G.41) Beton Cor 1 : 2 : 3
Bahan
0.7800 Kerikil @ Rp. 69,000.00 Rp. 53,820.00
0.5200 Pasir Pasangan @ Rp. 69,000.00 Rp. 35,880.00
5.8000 Semen PC @ Rp. 46,000.00 Rp. 266,800.00
Jumlah (a) Rp. 356,500.00
Upah Pekerja
1.6500 Pekerja @ Rp. 37,000.00 Rp. 61,050.00
0.0800 Mandor @ Rp. 52,000.00 Rp. 4,160.00
0.2500 Tukang @ Rp. 53,000.00 Rp. 13,250.00
0.0250 Kepala Tukang @ Rp. 64,000.00 Rp. 1,600.00
Jumlah (b) Rp. 80,060.00
Jumlah (a + b) Rp. 436,560.00
Dibulatkan Rp. 436,560.00
b. (Anl. G.41a) Beton Cor 1 : 1 1/2 : 2 1/2
Bahan
0.7800 Kerikil @ Rp. 69,000.00 Rp. 53,820.00
0.4700 Pasir Pasangan @ Rp. 69,000.00 Rp. 32,430.00
9.6500 Semen PC @ Rp. 46,000.00 Rp. 443,900.00
Jumlah (a) Rp. 530,150.00
Upah Pekerja
1.6500 Pekerja @ Rp. 37,000.00 Rp. 61,050.00
0.0800 Mandor @ Rp. 52,000.00 Rp. 4,160.00
0.2500 Tukang @ Rp. 53,000.00 Rp. 13,250.00
0.0250 Kepala Tukang @ Rp. 64,000.00 Rp. 1,600.00
Jumlah (b) Rp. 80,060.00
Jumlah (a + b) Rp. 610,210.00
Dibulatkan Rp. 610,210.00
kg
Org
m3
Org
Org
Org
lbr
kg
Org
Org
Org
Org
kg
kg
Org
Org
Org
Org
kg
kg
kg
kg
Org
Org
Org
Org
kg
m3
m3
zak
m3
Org
Org
Org
Org
m3
zak
Org
Org
Org
Org
c. Anl. 1.2.b Upah Pekerja Besi tiap 1 kg Besi Polos
0.0070 Pekerja @ Rp. 37,000.00 Rp. 259.00
0.0070 Tukang Besi @ Rp. 53,000.00 Rp. 371.00
0.0007 Kepala Tukang @ Rp. 64,000.00 Rp. 44.80
0.0003 Mandor @ Rp. 52,000.00 Rp. 15.60
1.0500 Besi Beton Polos @ Rp. 10,350.00 Rp. 10,867.50
0.0150 Kawat Beton @ Rp. 12,000.00 Rp. 180.00
Jumlah Rp. 11,737.90
Dibulatkan Rp. 11,740.00
d. Anl. F.8.a : 1 m2 Pasang Bekisting untuk Pondasi
0.0400 Kayu Terentang @ Rp. 2,024,000.00 Rp. 80,960.00
0.3000 Paku @ Rp. 14,000.00 Rp. 4,200.00
0.1000 Minyak Bekisting @ Rp. 13,800.00 Rp. 1,380.00
0.2600 Tukang @ Rp. 53,000.00 Rp. 13,780.00
0.0260 Kepala Tukang @ Rp. 64,000.00 Rp. 1,664.00
0.3000 Pekerja @ Rp. 37,000.00 Rp. 11,100.00
0.0050 Mandor @ Rp. 52,000.00 Rp. 260.00
Jumlah Rp. 113,344.00
Dibulatkan Rp. 113,340.00
e. Anl. F.8.b : 1 m2 Pasang Bekisting untuk Sloof
0.0450 Kayu Terentang @ Rp. 2,024,000.00 Rp. 91,080.00
0.3000 Paku @ Rp. 14,000.00 Rp. 4,200.00
0.1000 Minyak Bekisting @ Rp. 13,800.00 Rp. 1,380.00
0.2600 Tukang @ Rp. 53,000.00 Rp. 13,780.00
0.0260 Kepala Tukang @ Rp. 64,000.00 Rp. 1,664.00
0.3000 Pekerja @ Rp. 37,000.00 Rp. 11,100.00
0.0050 Mandor @ Rp. 52,000.00 Rp. 260.00
Jumlah Rp. 123,464.00
Dibulatkan Rp. 123,460.00
f. Anl. F.8.c : 1 m2 Pasang Bekisting untuk Kolom
0.0400 Kayu Terentang @ Rp. 2,024,000.00 Rp. 80,960.00
0.4000 Paku @ Rp. 14,000.00 Rp. 5,600.00
0.2000 Minyak Bekisting @ Rp. 13,800.00 Rp. 2,760.00
0.0150 Balok Kayu @ Rp. 2,300,000.00 Rp. 34,500.00
0.3500 Plywood tebal 9 mm @ Rp. 120,000.00 Rp. 42,000.00
2.0000 Dolken Kayu 8 - 10/4 m @ Rp. 18,000.00 Rp. 36,000.00
0.3300 Tukang @ Rp. 53,000.00 Rp. 17,490.00
0.0330 Kepala Tukang @ Rp. 64,000.00 Rp. 2,112.00
0.3000 Pekerja @ Rp. 37,000.00 Rp. 11,100.00
0.0060 Mandor @ Rp. 52,000.00 Rp. 312.00
Jumlah Rp. 232,834.00
Dibulatkan Rp. 232,830.00
g. Anl. F.8.d : 1 m2 Pasang Bekisting untuk Balok
0.0400 Kayu Terentang @ Rp. 2,024,000.00 Rp. 80,960.00
0.4000 Paku @ Rp. 14,000.00 Rp. 5,600.00
0.2000 Minyak Bekisting @ Rp. 13,800.00 Rp. 2,760.00
0.0180 Balok Kayu @ Rp. 2,300,000.00 Rp. 41,400.00
0.3500 Plywood tebal 9 mm @ Rp. 120,000.00 Rp. 42,000.00
2.0000 Dolken Kayu 8 - 10/4 m @ Rp. 18,000.00 Rp. 36,000.00
0.3300 Tukang @ Rp. 53,000.00 Rp. 17,490.00
0.0330 Kepala Tukang @ Rp. 64,000.00 Rp. 2,112.00
0.3200 Pekerja @ Rp. 37,000.00 Rp. 11,840.00
0.0060 Mandor @ Rp. 52,000.00 Rp. 312.00
Jumlah Rp. 240,474.00
Dibulatkan Rp. 240,470.00
h. Anl. F.8.e : 1 m2 Pasang Bekisting untuk Lantai
0.0400 Kayu Terentang @ Rp. 2,024,000.00 Rp. 80,960.00
0.4000 Paku @ Rp. 14,000.00 Rp. 5,600.00
0.2000 Minyak Bekisting @ Rp. 13,800.00 Rp. 2,760.00
0.0150 Balok Kayu @ Rp. 2,300,000.00 Rp. 34,500.00
0.3500 Plywood tebal 9 mm @ Rp. 120,000.00 Rp. 42,000.00
6.0000 Dolken Kayu 8 - 10/4 m @ Rp. 18,000.00 Rp. 108,000.00
0.3300 Tukang @ Rp. 53,000.00 Rp. 17,490.00
0.0330 Kepala Tukang @ Rp. 64,000.00 Rp. 2,112.00
0.3200 Pekerja @ Rp. 37,000.00 Rp. 11,840.00
0.0060 Mandor @ Rp. 52,000.00 Rp. 312.00
Jumlah Rp. 305,574.00
Dibulatkan Rp. 305,570.00
Org
m3
Org
Org
Org
kg
kg
m3
kg
ltr
Org
Org
Org
Org
kg
ltr
Org
Org
Org
Org
m3
kg
ltr
Org
Org
Org
Org
m3
lbr
btg
m3
kg
ltr
m3
Org
Org
lbr
btg
Org
Org
m3
kg
ltr
m3
Org
Org
lbr
btg
Org
Org
R E K A P I T U L A S I
Anl. Supl. Va Beton Bertulang 1 : 2 : 3
Untuk Sloof 15/20 Besi Polos = 147,28 kg/m3
Anl. G.41 (Beton Cor 1 : 2 : 3) @ Rp. 436,560.00 Rp. 436,560.00
Anl. 1.2.b (Upah Pekerja dan Bahan Besi Polos 147,28 x @ Rp. 11,740.00 Rp. 1,729,067.20
Anl. F.8.b (Pasang Bekisting untuk Sloof 0,5 x 13,333 x @ Rp. 123,460.00 Rp. 823,046.09
Jumlah Rp. 2,988,673.29
Dibulatkan Rp. 2,988,670.00
Anl. Supl. Vb Beton Bertulang 1 : 2 : 3
Untuk Balok Gantung 15/20 Besi Polos = 209,24 kg/m3
Anl. G.41 (Beton Cor 1 : 2 : 3) @ Rp. 436,560.00 Rp. 436,560.00
Anl. 1.2.b (Upah Pekerja dan Bahan Besi Polos 209,24 x @ Rp. 11,740.00 Rp. 2,456,477.60
Anl. F.8.d (Pasang Bekisting untuk Balok 0,5 x 16,666 x @ Rp. 240,470.00 Rp. 2,003,836.51
Jumlah Rp. 4,896,874.11
Dibulatkan Rp. 4,896,870.00
Anl. Supl. Vd Beton Bertulang 1 : 2 : 3
Untuk Kolom Teras 20/20 Besi Polos = 93,95 kg/m3
Anl. G.41 (Beton Cor 1 : 2 : 3) @ Rp. 436,560.00 Rp. 436,560.00
Anl. 1.2.b (Upah Pekerja dan Bahan Besi Polos 93,95 x @ Rp. 11,740.00 Rp. 1,102,973.00
Anl. F.8.c (Pasang Bekisting untuk Kolom 0,5 x 19,11 x @ Rp. 232,830.00 Rp. 2,224,690.65
Jumlah Rp. 3,764,223.65
Dibulatkan Rp. 3,764,220.00
Anl. Supl. Vd.1 Beton Bertulang 1 : 2 : 3
Untuk Kolom Praktis 13/13 Besi = 195,95 kg/m3
Anl. G.41 (Beton Cor 1 : 2 : 3) @ Rp. 436,560.00 Rp. 436,560.00
Anl. 1.2.b (Upah Pekerja dan Bahan Besi Polos 195,95 x @ Rp. 11,740.00 Rp. 2,300,453.00
Anl. F.8.c (Pasang Bekisting untuk Kolom 0,25 x 15,384 x @ Rp. 232,830.00 Rp. 895,464.18
Jumlah Rp. 3,632,477.18
Dibulatkan Rp. 3,632,480.00
Anl. Supl. Vb.1 Beton Bertulang 1 : 2 : 3
Untuk Ring Balok dan Top Gevel 13/15 Besi = 173,10 kg/m3
Anl. G.41 (Beton Cor 1 : 2 : 3) @ Rp. 436,560.00 Rp. 436,560.00
Anl. 1.2.b (Upah Pekerja dan Bahan Besi Polos 173,10 x @ Rp. 11,740.00 Rp. 2,032,194.00
Anl. F.8.d (Pasang Bekisting untuk Balok 0,5 x 10 x @ Rp. 240,470.00 Rp. 1,202,350.00
Jumlah Rp. 3,671,104.00
Dibulatkan Rp. 3,671,100.00
Teunom, 10 Juli 2009
Penawar,
CV. ELANG MAS
DASRIL A. RAHMAN IBRAHIM
Direktur
KEGIATAN : PENGEMBANGAN RUMAH SEHAT SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH RUMAH SEHAT SEDERHANA 15 UNIT
LOKASI : KABUPATEN ACEH JAYA
NOMOR PAKET : RSS/AJA/OTS/255
TAHUN : 2009
HARGA SATUAN
(Rp.)
A. UPAH
1 Kepala Tukang 64,000.00 /Hari
2 Tukang 53,000.00 /Hari
3 Pekerja 37,000.00 /Hari
4 Mandor 52,000.00 /Hari
B. BAHAN
1 Batu Kali/Batu Belah (Sungai/Gunung) 164,000.00 /M3
2 Batu Bata 510.00 /Buah
3 Besi Beton Polos 10,350.00 /Kg
4 Cat Tembok 15,600.00 /Kg
5 Cat Dasar 13,800.00 /Kg
6 Cat Menie 13,800.00 /Kg
7 Cat Kayu/Minyak Synthetic Enamel (Kuda Terbang) 18,400.00 /Kg
8 Sekrup 100.00 /Buah
9 Kloset Jongkok (Terpasang) 202,000.00 /Buah
10 Daun Pintu Panel 80 x 200 cm 368,000.00 /Buah
11 Pintu Kamar Mandi PVC 322,000.00 /Buah
12 Daun Jendela Uk. 50 x 120 cm 198,000.00 /Buah
13 Plamur Tembok 16,100.00 /Kg
14 Engsel Pintu 7,000.00 /Bh
15 Engsel Jendela 5,000.00 /Bh
16 Pacok Jendela 9,000.00 /Bh
17 Hak Angin 9,000.00 /Bh
18 Kayu/Papan Bekisting 2,024,000.00 /M3
19 Kayu Sembarang Keras 2,300,000.00 /M3
20 Kayu Klas II 2,668,000.00 /M3
21 Kawat Ikat 12,000.00 /Kg
22 Kayu Dolken 18,000.00 /Btg
23 Kerikil Beton 69,000.00 /M3
24 Minyak Bekisting 13,800.00 /Liter
25 Multiplek 3 mm 64,000.00 /Lbr
26 Gypsum 59,800.00 /M2
27 Pasir Urug 64,000.00 /M3
28 Pasir Pasang 69,000.00 /M3
29 Paku Kayu 14,000.00 /Kg
30 Semen PC Andalas @ 40 Kg 46,000.00 /Zak
31 Tanah Timbun 64,000.00 /M3
32 Handel Jendela 7,000.00 /Bh
33 Kunci Pintu 184,000.00 /Bh
34 Bak Mandi Fibre Glass (Terpasang) 322,000.00 /Bh
35 Kran Air + Instalasi (Terpasang) 69,000.00 /Bh
36 Floor Drain + Pipa Pembuang (Terpasang) 64,000.00 /Bh
37 Septictank + Peresapan + Instalasi (Terpasang) 2,044,000.00 /Bh
38 Box Zekering MCB 2 Group 202,000.00 /Bh
39 Lampu Hemat Energi 18 Watt 60,000.00 /Bh
40 Lampu Hemat Energi 10 Watt 41,000.00 /Bh
41 Pekerjaan Titik Api/Cahaya + Instalasi 138,000.00 /Bh
42 Stop Kontak + Instalasi 152,000.00 /Bh
43 Saklar Ganda 37,000.00 /Bh
44 Saklar Tunggal 32,000.00 /Bh
45 Plywood 9 mm 120,000.00 /Lbr
46 Calsiboard 6 mm 74,000.00 /Lbr
Teunom, 10 Juli 2009
Penawar,
CV. ELANG MAS
DASRIL A. RAHMAN IBRAHIM
Direktur
NO. U R A I A N SATUAN
DAFTAR HARGA UPAH DAN BAHAN
JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULE)
KEGIATAN : PENGEMBANGAN RUMAH SEHAT SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH RUMAH SEHAT SEDERHANA 15 UNIT
LOKASI : KABUPATEN ACEH JAYA
NOMOR PAKET : RSS/AJA/OTS/255
TAHUN : 2009
JUMLAH JANGKA WAKTU PELAKSANAAN
NO. HARGA BOBOT BULAN KE-I BULAN KE-II BULAN KE-III BULAN KE-IV
(Rp.) I II III IV I II III IV I II III IV I II III IV
A. PEKERJAAN PERSIAPAN 525,000.00 0.845 0.14 0.14 0.14 0.14 0.14 0.14
B. PEKERJAAN TANAH & PONDASI 3,907,637.00 6.292 1.26 1.26 1.26 1.26 1.26
C. PEKERJAAN BETON BERTULANG 9,613,266.60 15.480 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72 1.72
D. PEKERJAAN PASANGAN DAN PLESTERAN 10,932,360.00 17.604 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76 1.76
E. PEKERJAAN DINDING CALSIUM SILICATE BOARD - -
F. PEKERJAAN LANTAI 1,032,541.40 1.663 0.28 0.28 0.28 0.28 0.28 0.28
G. PEKERJAAN ATAP DAN PLAFOND 20,555,550.60 33.100 3.68 3.68 3.68 3.68 3.68 3.68 3.68 3.68 3.68
H. PEKERJAAN KOSEN PINTU, JENDELA DAN KUNCI 7,163,296.00 11.535 1.65 1.65 1.65 1.65 1.65 1.65 1.65
I. PEKERJAAN PENGECATAN 3,222,991.00 5.190 1.04 1.04 1.04 1.04 1.04
J. PEKERJAAN INSTALASI LISTRIK 2,447,000.00 3.940 0.66 0.66 0.66 0.66 0.66 0.66
K. PEKERJAAN SANITAIR 2,701,000.00 4.349 0.72 0.72 0.72 0.72 0.72 0.72
Biaya untuk 1 Unit 62,100,642.60 100.000
Dibulatkan 62,100,000.00
Total Biaya untuk 15 Unit 931,500,000.00
Minggu 0.14 1.40 2.98 4.74 4.74 10.06 9.46 9.60 9.60 8.47 9.20 7.48 9.78 8.02 3.45 0.87
Kumulatif 0.14 1.54 4.52 9.26 14.00 24.06 33.52 43.13 52.73 61.20 70.40 77.88 87.66 95.69 99.13 100.00
Teunom, 10 Juli 2009
Penawar,
CV. ELANG MAS
DASRIL A. RAHMAN IBRAHIM
Direktur
URAIAN PEKERJAAN KET.
RENCANA
0 %
10 %
20 %
30 %
40 %
50 %
60 %
70 %
80 %
90 %
100
KEGIATAN : PENGEMBANGAN RUMAH SEHAT SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH RUMAH SEHAT SEDERHANA 15 UNIT
LOKASI : KABUPATEN ACEH JAYA
NOMOR PAKET : RSS/AJA/OTS/255
TAHUN : 2009
HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.)
1 3 4 5 6 7
A. PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan 1.00 Ls Taksir 150,000.00 150,000.00
2 Pengukuran dan Pemasangan Bowplank 1.00 Ls Taksir 175,000.00 175,000.00
3 Adm / Dokumentasi 1.00 Ls Taksir 200,000.00 200,000.00
525,000.00
B. PEKERJAAN TANAH & PONDASI
1 Galian Tanah Pondasi 5.60 m3 SNI.T.01.2a 16,880.00 94,528.00
2 Urugan Pasir Bawah Pondasi dan Lantai 3.50 m3 SNI.T.01.2n 88,420.00 309,470.00
3 Pondasi Batu Gunung 1 : 4 5.30 m3 SNI.T.01.2d 498,770.00 2,643,481.00
4 Urugan Kembali 1.40 m3 SNI.T.01.2i 8,090.00 11,326.00
5 Urugan Tanah 9.60 m3 Anl. A.18 88,420.00 848,832.00
3,907,637.00
C. PEKERJAAN BETON BERTULANG
1 Beton Bertulang Sloof 15/20 cm 1.06 m3 Anl. Supl. Va 2,988,670.00 3,167,990.20
2 Beton Bertulang Kolom Teras 20/20 cm 0.12 m3 Anl. Supl. Vd 3,764,220.00 451,706.40
3 Beton Bertulang Kolom Praktis 13/13 cm 0.70 m3 Anl. Supl. Vd.1 3,632,480.00 2,542,736.00
4 Beton Bertulang Ring Balok 13/15 cm 0.94 m3 Anl. Supl. Vb.1 3,671,100.00 3,450,834.00
9,613,266.60
D. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Batu Bata 1 : 4 92.00 m2 SNI.T.03.1.n 70,450.00 6,481,400.00
2 Plesteran 1 : 4 184.00 m2 SNI.T.03.3.d 24,190.00 4,450,960.00
10,932,360.00
E. PEKERJAAN DINDING CALSIUM SILICATE BOARD
1 Rangka Dinding Galvanized - m2 Taksir - -
2 Dinding Calsium Silicate Board T = 6 mm - m2 Taksir - -
-
F. PEKERJAAN LANTAI
1 Lantai Beton Cor 1 : 3 : 5 T = 7 cm 2.42 m3 Anl. G.67 426,670.00 1,032,541.40
1,032,541.40
G. PEKERJAAN ATAP DAN PLAFOND
1 Rangka Kuda-kuda Baja Ringan Galvanized 62.00 m2 Taksir 120,000.00 7,440,000.00
2 Rangka Plafond Galvanized 52.06 m2 Taksir 82,500.00 4,294,950.00
3 Penutup Atap Galvanized T = 0,25 mm 62.00 m2 Taksir 95,000.00 5,890,000.00
4 Listplank Triplek Lapis Seng 6.18 m2 Anl. F.38 47,450.00 293,241.00
5 Pasangan Plafond Gypsum 52.06 m2 Anl. Supl. VII 50,660.00 2,637,359.60
20,555,550.60
H. PEKERJAAN KOSEN PINTU, JENDELA DAN KUNCI
1 Kayu Kosen Pintu, Jendela + Jalusi 0.58 m3 Anl. F. 26 4,521,200.00 2,622,296.00
2 Daun Pintu Panel Uk. 80 x 200 cm 4.00 Bh Taksir 368,000.00 1,472,000.00
3 Daun Pintu Double Triplek Uk. 80 x 200 - Bh Taksir - -
4 Pintu Kamar Mandi PVC 1.00 Bh Taksir 322,000.00 322,000.00
5 Daun Jendela Kaca Uk. 50 x 120 cm 7.00 Bh Taksir 198,000.00 1,386,000.00
6 Triplek Penutup Kusen Pintu - Ls Taksir - -
7 Engsel Pintu 10.00 Bh Taksir 7,000.00 70,000.00
8 Engsel Jendela 14.00 Bh Taksir 5,000.00 70,000.00
9 Pacok Jendela 14.00 Bh Taksir 9,000.00 126,000.00
10 Hak Angin 14.00 Bh Taksir 9,000.00 126,000.00
11 Kunci Pintu 5.00 Bh Taksir 184,000.00 920,000.00
12 Handel Jendela 7.00 Bh Taksir 7,000.00 49,000.00
7,163,296.00
I. PEKERJAAN PENGECATAN
1 Cat Tembok 184.00 m2 Supl. IXa 11,660.00 2,145,440.00
2 Cat Plafond 28.50 m2 Supl. IXa 11,660.00 332,310.00
3 Cat Mengkilat Kosen, Pintu dan Jendela 16.00 m2 Anl.K.10+K23+28 15,890.00 254,240.00
4 Cat Listplank Kayu 6.10 m2 Anl.K.10+K23+28 15,890.00 96,929.00
5 Cat Ambang Pintu dan Jendela 16.50 m2 Anl.K.10+K23+28 15,890.00 262,185.00
6 Cat Jalusi Kayu 8.30 m2 Anl.K.10+K23+28 15,890.00 131,887.00
3,222,991.00
ANALISA
2
RENCANA ANGGARAN BIAYA (RAB)
Sub Total A
NO. URAIAN PEKERJAAN VOLUME SAT.
Sub Total B
Sub Total C
Sub Total D
Sub Total F
Sub Total E
Sub Total G
Sub Total H
Sub Total I
HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.)
1 3 4 5 6 7
J. PEKERJAAN INSTALASI LISTRIK
1 Box Zekering MCB 2 Group 1.00 m3 Taksir 202,000.00 202,000.00
2 Lampu Hemat Energi 18 Watt (Philip) 3.00 Bh Taksir 60,000.00 180,000.00
3 Lampu Hemat Energi 10 Watt (Philip) 2.00 Bh Taksir 41,000.00 82,000.00
4 Pekerja Titik Api/Cahaya + Instalasi 9.00 Titik Taksir 138,000.00 1,242,000.00
5 Stop Kontak 4.00 Bh Taksir 152,000.00 608,000.00
6 Saklar Ganda 1.00 Bh Taksir 37,000.00 37,000.00
7 Saklar Tunggal 3.00 Bh Taksir 32,000.00 96,000.00
2,447,000.00
K. PEKERJAAN SANITAIR
1 Bak Mandi Fiber Glass (Terpasang) 1.00 Ls Taksir 322,000.00 322,000.00
2 Kloset Jongkok (Terpasang) 1.00 Bh Taksir 202,000.00 202,000.00
3 Kran Air + Instalasi (Terpasang) 1.00 Ls Taksir 69,000.00 69,000.00
4 Floor Drain + Pipa Pembuang (Terpasang) 1.00 Ls Taksir 64,000.00 64,000.00
5 Septictank & Peresapan + Instalasi (Terpasang) 1.00 Bh Taksir 2,044,000.00 2,044,000.00
2,701,000.00
Teunom, 10 Juli 2009
Penawar,
CV. ELANG MAS
DASRIL A. RAHMAN IBRAHIM
Direktur
NO. URAIAN PEKERJAAN VOLUME SAT.
2
Sub Total J
Sub Total K
ANALISA
KEGIATAN : PENGEMBANGAN RUMAH SEHAT SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH RUMAH SEHAT SEDERHANA 15 UNIT
LOKASI : KABUPATEN ACEH JAYA
NOMOR PAKET : RSS/AJA/OTS/255
TAHUN : 2009
Jenis Pekerjaan : Pembersihan Lapangan
TENAGA KERJA
Volume Pekerjaan : 1.00 Ls
Lama Waktu Pelaksanaan : 5.00 Hari
Satuan Minggu : 0.71 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Pengukuran dan Pemasangan Bowplank
TENAGA KERJA
Volume Pekerjaan : 1.00 LS
Lama Waktu Pelaksanaan : 5.00 Hari
Satuan Minggu : 0.71 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Adm / Dokumentasi
TENAGA KERJA
Volume Pekerjaan : 1.00 LS
Lama Waktu Pelaksanaan : 30.00 Hari
Satuan Minggu : 4.29 Minggu
DIBULATKAN 5.00 Minggu
Jenis Pekerjaan : Galian Tanah Pondasi
TENAGA KERJA
Volume Pekerjaan : 5.60 m3
Faktor Tenaga Kerja : 0.44 OH/m3
Produksi Harian Tenaga Kerja : 2.27 m3/Hari
Jumlah Tenaga Kerja : 3.00 Orang
Lama Waktu Pelaksanaan : 0.82 Hari
Satuan Minggu : 0.12 Minggu
DIBULATKAN 1.00 Minggu
KUANTITAS SATUAN
ANALISA TEKNIK
URAIAN
URAIAN KUANTITAS SATUAN
NO URAIAN
NO
NO URAIAN KUANTITAS SATUAN
NO
KUANTITAS SATUAN
Analisa Teknik 11
ANALISA TEKNIK
Jenis Pekerjaan : Urugan Pasir Bawah Pondasi dan Lantai
TENAGA KERJA
Volume Pekerjaan : 3.50 m3
Faktor Tenaga Kerja : 0.21 OH/m3
Produksi Harian Tenaga Kerja : 4.74 m3/Hari
Jumlah Tenaga Kerja : 3.00 Orang
Lama Waktu Pelaksanaan : 0.25 Hari
Satuan Minggu : 0.04 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Pondasi Batu Gunung 1 : 4
TENAGA KERJA
Volume Pekerjaan : 5.30 m
3
Faktor Tenaga Kerja : 1.51 OH/m3
Produksi Harian Tenaga Kerja : 0.66 m3/Hari
Jumlah Tenaga Kerja : 3.00 Orang
Lama Waktu Pelaksanaan : 2.67 Hari
Satuan Minggu : 0.38 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Urugan Kembali
TENAGA KERJA
Volume Pekerjaan : 1.40 m
3
Faktor Tenaga Kerja : 1.29 OH/m3
Produksi Harian Tenaga Kerja : 0.78 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 0.36 Hari
Satuan Minggu : 0.05 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Beton Bertulang Sloof 15/20 cm
TENAGA KERJA
Volume Pekerjaan : 1.06 m
3
Faktor Tenaga Kerja : 14.54 OH/m3
Produksi Harian Tenaga Kerja : 0.07 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 3.08 Hari
Satuan Minggu : 0.44 Minggu
DIBULATKAN 1.00 Minggu
KUANTITAS SATUAN URAIAN
NO URAIAN KUANTITAS SATUAN
NO
NO KUANTITAS SATUAN URAIAN
NO URAIAN KUANTITAS SATUAN
Analisa Teknik 12
ANALISA TEKNIK
Jenis Pekerjaan : Beton Bertulang Kolom Teras 20/20 cm
TENAGA KERJA
Volume Pekerjaan : 0.12 m
3
Faktor Tenaga Kerja : 14.54 OH/m3
Produksi Harian Tenaga Kerja : 0.07 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 0.35 Hari
Satuan Minggu : 0.05 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Beton Bertulang Kolom Praktis 13/13 cm
TENAGA KERJA
Volume Pekerjaan : 0.70 m
3
Faktor Tenaga Kerja : 14.54 OH/m3
Produksi Harian Tenaga Kerja : 0.07 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 2.04 Hari
Satuan Minggu : 0.29 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Beton Bertulang Ring Balok 13/15 cm
TENAGA KERJA
Volume Pekerjaan : 0.94 m
3
Faktor Tenaga Kerja : 14.54 OH/m3
Produksi Harian Tenaga Kerja : 0.07 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 2.73 Hari
Satuan Minggu : 0.39 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Pasangan Batu Bata 1 : 4
TENAGA KERJA
Volume Pekerjaan : 92.00 m2
Faktor Tenaga Kerja : 0.67 OH/m2
Produksi Harian Tenaga Kerja : 1.48 m2/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 12.40 Hari
Satuan Minggu : 1.77 Minggu
DIBULATKAN 2.00 Minggu
NO URAIAN
KUANTITAS SATUAN
NO URAIAN
SATUAN
KUANTITAS
KUANTITAS SATUAN
KUANTITAS
SATUAN
NO URAIAN
NO URAIAN
Analisa Teknik 13
ANALISA TEKNIK
Jenis Pekerjaan : Plesteran 1 : 4
TENAGA KERJA
Volume Pekerjaan : 184.00 m2
Faktor Tenaga Kerja : 0.64 OH/m2
Produksi Harian Tenaga Kerja : 1.56 m2/Hari
Jumlah Tenaga Kerja : 10.00 Orang
Lama Waktu Pelaksanaan : 11.78 Hari
Satuan Minggu : 1.68 Minggu
DIBULATKAN 2.00 Minggu
Jenis Pekerjaan : Rangka Kuda-kuda Baja Ringan Galvanized
TENAGA KERJA
Volume Pekerjaan : 62.00 m
3
Faktor Tenaga Kerja : 0.31 OH/m3
Produksi Harian Tenaga Kerja : 3.23 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 3.84 Hari
Satuan Minggu : 0.55 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Rangka Plafond Galvanized
TENAGA KERJA
Volume Pekerjaan : 52.06 m
3
Faktor Tenaga Kerja : 0.31 OH/m3
Produksi Harian Tenaga Kerja : 3.23 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 3.23 Hari
Satuan Minggu : 0.46 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Penutup Atap Galvanized T = 0,25 mm
TENAGA KERJA
Volume Pekerjaan : 62.00 m
3
Faktor Tenaga Kerja : 6.75 OH/m3
Produksi Harian Tenaga Kerja : 0.15 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 83.70 Hari
Satuan Minggu : 11.96 Minggu
DIBULATKAN 12.00 Minggu
NO SATUAN
KUANTITAS SATUAN
KUANTITAS
URAIAN NO
SATUAN
NO URAIAN KUANTITAS SATUAN
NO
URAIAN
URAIAN
KUANTITAS
Analisa Teknik 14
ANALISA TEKNIK
Jenis Pekerjaan : Listplank Triplek Lapis Seng
TENAGA KERJA
Volume Pekerjaan : 6.18 m
3
Faktor Tenaga Kerja : 14.10 OH/m3
Produksi Harian Tenaga Kerja : 0.07 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 17.43 Hari
Satuan Minggu : 2.49 Minggu
DIBULATKAN 3.00 Minggu
Jenis Pekerjaan : Pasangan Plafond Gypsum
TENAGA KERJA
Volume Pekerjaan : 52.06 m
3
Faktor Tenaga Kerja : 14.10 OH/m3
Produksi Harian Tenaga Kerja : 0.07 m3/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 146.81 Hari
Satuan Minggu : 20.97 Minggu
DIBULATKAN 21.00 Minggu
Jenis Pekerjaan : Kayu Kosen Pintu, Jendela + Jalusi
TENAGA KERJA
Volume Pekerjaan : 0.58 m2
Faktor Tenaga Kerja : 0.33 OH/m2
Produksi Harian Tenaga Kerja : 3.08 m2/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 0.04 Hari
Satuan Minggu : 0.01 Minggu
DIBULATKAN 1.00 Minggu
Jenis Pekerjaan : Cat Tembok
TENAGA KERJA
Volume Pekerjaan : 184.00 m2
Faktor Tenaga Kerja : 0.63 OH/m'
Produksi Harian Tenaga Kerja : 1.59 m'/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 23.18 Hari
Satuan Minggu : 3.31 Minggu
DIBULATKAN 4.00 Minggu
URAIAN KUANTITAS
SATUAN
SATUAN
NO URAIAN KUANTITAS SATUAN
NO
URAIAN KUANTITAS SATUAN
NO URAIAN KUANTITAS
NO
Analisa Teknik 15
ANALISA TEKNIK
Jenis Pekerjaan : Cat Plafond
TENAGA KERJA
Volume Pekerjaan : 28.50 m2
Faktor Tenaga Kerja : 1.17 OH/m2
Produksi Harian Tenaga Kerja : 0.85 m2/Hari
Jumlah Tenaga Kerja : 5.00 Orang
Lama Waktu Pelaksanaan : 6.69 Hari
Satuan Minggu : 0.96 Minggu
DIBULATKAN 1.00 Minggu
Teunom, 10 Juli 2009
CV. ELANG MAS
DASRIL A. RAHMAN IBRAHIM
Direktur
NO URAIAN KUANTITAS SATUAN
Analisa Teknik 16
KEGIATAN : PENGEMBANGAN RUMAH SEHAT SEDERHANA
PEKERJAAN : PEMBANGUNAN RUMAH RUMAH SEHAT SEDERHANA 15 UNIT
LOKASI : KABUPATEN ACEH JAYA
NOMOR PAKET : RSS/AJA/OTS/255
TAHUN : 2009
Start : 1-Jul-09 ID : 1
Finish : 31-Jul-09 Dur : 4 wks
Res :
Start : 8-Jul-09 ID : 2
Finish : 31-Jul-09 Dur : 3 wks
Res :
Start : 22-Jul-09 ID : 3
Finish : 7-Sep-09 Dur : 6 wks
Res :
Start : 8-Aug-09 ID : 4
Finish : 14-Sep-09 Dur : 9 wks
Res :
Start : 22-Sep-09 ID : 5
Finish : 14-Oct-09 Dur : 5 wks
Res :
Start : 22-Sep-09 ID : 6
Finish : 7-Oct-09 Dur : 2 wks
Res :
Start : 15-Sep-09 ID : 7
Finish : 21-Sep-09 Dur : 2 wks
Res :
Start : 15-Oct-09 ID : 8
Finish : 21-Oct-09 Dur : 1 wks
Res :
Start : 22-Oct-09 ID : 9
Finish : 31-Oct-09 Dur : 1 wks
Res :
Teunom, 10 Juli 2009
CV. ELANG MAS
DASRIL A. RAHMAN IBRAHIM
Direktur
Persiapan
Pekerjaan Dinding
Pekerjaan Daun Pintu & Jendela
Pekerjaan WC / KM
Pekerjaan Pondasi
Pek. Beton Bertulang
Pekerjaan Atap & Plafond
Pekerjaan Lantai
Pekerjaan Instalasi Listrik