Anda di halaman 1dari 27

A.

UPAH KERJA
UPAH KERJA
Rp.
1 Pekerja tidak terlatih Org / Hari 65,000.00
2 Pekerja semi terlatih Org / Hari 68,500.00
3 Pekerja terlatih Org / Hari 65,000.00
4 M a n d o r Org / Hari 90,000.00
5 Tukang besi Konstruksi Org / Hari 72,000.00
6 Tukang Besi Tulangan Org / Hari 72,000.00
7 Kepala Tukang Besi Org / Hari 103,500.00
8 Tukang kayu Kasar Org / Hari 72,500.00
9 Tukang Kayu Halus Org / Hari 72,500.00
10 Kepala Tukang Kayu Org / Hari 103,500.00
11 Tukang semen Org / Hari 90,000.00
12 Tukang aspal Org / Hari 90,000.00
13 Tukang Gali Org / Hari 90,000.00
14 Tukang batu Kasar Org / Hari 90,000.00
15 Tukang Batu Halus Org / Hari 90,000.00
16 Kepala Tukang Batu Org / Hari 103,500.00
17 Tukang cat biasa Org / Hari 72,500.00
18 Tukang Cat Duco Org / Hari 71,500.00
19 Kepala Tukang Cat Org / Hari 103,500.00
20 Tukang Listrik Org / Hari 90,000.00
21 Kepala Tukang Listrik Org / Hari 103,500.00
22 Tukang pelitur Org / Hari 90,000.00
23 Kepala Tukang Org / Hari 103,500.00
24 Juru Ukur Org / Hari 90,000.00
25 Pembantu Juru Ukur Org / Hari 64,500.00
26 Operator Org / Hari 75,000.00
27 Pembantu Operatur Org / Hari 90,000.00
28 Operator semi terlatih Org / Hari 90,000.00
29 Operator Alat Berat Org / Hari 90,000.00
30 Mekanik Org / Hari 650,000.00
31 Supir Org / Hari 90,000.00
32 Pembantu Supir Org / Hari 90,000.00
33 Pembantu mekanik Org / Hari 90,000.00
34 Pengemudi Org / Hari 95,000.00
35 Penjaga malam Org / Hari 50,000.00
B. BAHAN / MATERIAL
I. BAHAN PENGISI
1 Tanah urug / tanah datang M
3
131,500.00
2 Pasir Urug M
3
155,000.00
3 Pasir Beton / Pasang (Lokal) M
3
163,000.00
4 Pasir Beton / Pasang (Pilihan) M
3
158,500.00
5 Tanah Kong (Hitam) M
3
140,000.00
6 Batu Kong M
3
180,000.00
7 Bt Kerikil Sei Tdk Tersaring M
3
210,000.00
8 Tanah Kong (Hitam) M
3
160,000.00
9 Bt Kerikil Sei Tdk Tersaring M
3
250,000.00
10 Batu Belah Uk. 10/15 cm M
3
415,000.00
11 Batu Pecah Uk. 5/7 cm M
3
430,000.00
12 Batu Pecah Uk. 3/5 cm M
3
445,000.00
13 Batu Pecah Uk. 2/3 cm M
3
745,000.00
NO MATERIAL SATUAN HARGA MATERIAL
UPAH TENAGA KERJA DAN HARGA SATUAN MATERIAL / BAHAN
NO TENAGA KERJA SATUAN
NO MATERIAL SATUAN HARGA MATERIAL
14 Batu Pecah Uk. 1/2 cm M
3
750,000.00
15 Bt Uk.2/3cm (Psr1/2,Manual) M
3
580,000.00
16 Batu Uk. 1/2 cm (Psr 1/1) M
3
635,000.00
17 Bt Uk.2/3cm (Psr1/2, Mesin) M
3
575,000.00
18 Batu Uk. 0,5/1 cm M
3
612,000.00
19 Stone Dust M
3
535,000.00
20 Aspal Drum Kg 14,100.00
21 Semen Zak 81,500.00
22 Semen Kg 1,630.00
23 Alat Bantu Set 115,000.00
24 Minyak Tanah / Kerosine Ltr 14,250.00
25 Minyak Diesel/Solar (Subsidi) Ltr 6,500.00
26 Minyak Diesel/Solar (Non Subsidi) Ltr 12,875.00
27 Minyak Premium/Bensin (Non Subsidi) Ltr 10,500.00
28 Minyak Premium/Bensin (Subsidi) Ltr 6,875.00
29 Minyak Pelumas Ltr 22,500.00
30 Olie Mesin Kg 32,500.00
31 Olie Hidroulic Kg 38,500.00
32 Olie Transmisi Kg 40,500.00
33 Carby/Griace Kg 52,500.00
34 Air Cleaner Pcs 195,500.00
35 Filter Solar Pcs 158,500.00
36 Filter Olie Pcs 178,000.00
37 Batako Bh 2,850.00
38 Bata Merah Bh 1,100.00
39 Paving Block Bh 3,450.00
40 Rooster ( Kerawang beton ) Uk. 20 x 20 cm Bh 6,250.00
41 Buis beton setengah lingkaran dia 3- cm Bh 57,600.00
42 buis beton Uk. Dia 120 cm Bh 508,500.00
II. BAHAN KAYU
1 Ky Bel. tdk diktm15/15-20/20x4 m M3 14,100,000.00
2 Ky Bel. tdk diktm 12/12x4 m M3 11,600,000.00
3 Ky Bel. tdk diktm 10/10x4 m M3 11,800,000.00
4 Ky Bel. diketam 6/6 x 4 m M3 11,600,000.00
5 Ky Bel. diketam 7/7 x 4 m M3 13,750,000.00
6 Ky Bel. diketam 8/8 x 4 m M3 13,900,000.00
7 Ky Bel. diketam 9/9 x 4 m M3 12,950,000.00
8 Ky Belian diketam 10/10x4 m M3 11,450,000.00
9 Ky Belian diketam 12/12x4 m M3 11,550,000.00
10 Papan belian 2/14-2.5/16x4 m M3 14,050,000.00
11 Papan belian 3/14-4/16 x 4 m M3 14,550,000.00
12 Ppn bel. tdk diktm 3/14 x 4 m M3 14,175,000.00
13 Ppn bel. tdk diktm 1.2/14x4 m M3 14,005,000.00
14 Papan Lat 1.5/15 cm x 4 m M3 12,950,000.00
15 Ky Klas I :18/18-20/20cmx4m M3 4,750,000.00
16 12/12-14/14cmx4m M3 4,750,000.00
17 8/8-10/10cmx4 m M3 4,690,000.00
18 Papan Klas I 1.8 cm M3 4,450,000.00
19 Kayu Klas I: 2/18-5/18 cm x 4 m M3 4,250,000.00
20 Kasau 4/6-5/7 cm x 4 m M3 3,265,000.00
21 Reng seng 2/3-3/5cmx4m M3 3,650,000.00
22 Kayu Kls II 8/12 cm x 4 m M3 2,925,000.00
23 Kayu Kls II 4/6 cm x 4 m M3 2,225,000.00
24 Kayu Kls II 3/5 cm x 4 m M3 2,575,000.00
25 Papan Kls II 2/20 cm x 4 m M3 2,975,000.00
26 Kayu Kls III M3 1,635,000.00
27 Papan Kls III tebal 2 cm M3 1,975,000.00
28 Kayu Kls IV tebal 1.6 cm M3 1,475,000.00
29 Triplek 3 mm Lbr 71,000.00
30 Triplek 4 mm Lbr 90,000.00
31 Triplek 6 mm Lbr 125,000.00
32 Triplek 9 mm Lbr 172,000.00
NO MATERIAL SATUAN HARGA MATERIAL
33 Triplek 12 mm Lbr 244,000.00
34 Teakwood t. 3 mm Lbr 145,000.00
35 Teakwood t. 4 mm Lbr 162,500.00
36 Formika t. 0,03 mm Lbr 248,000.00
37 Multiplex t.6 mm Lbr 126,500.00
38 Mulltiplex t. 9 mm Lbr 168,000.00
39 MDF t. 9 mm Lbr 305,000.00
40 Kayu Bakar M3 82,500.00
41 Kayu Bulat Dia. 10/12 cm x 4 M Btg 11,500.00
42 Kayu Bulat Dia. 8/10 cm x 4 M Btg 9,500.00
43 Cerucuk Bentangor dia. 12/15 x 12 m' Btg 95,000.00
44 Dolken ( Cerucuk ) dia 5 s/d 7 cm Btg 12,000.00
45 Bambu dia 5/7 cm Btg 6,750.00
III. BAHAN BESI
1 Besi simpai roll putih Kg 47,500.00
2 Besi simpai roll Biru Kg 39,500.00
3 Besi Uk.o 6 mm Kg 15,775.00
4 Besi Uk.o 8 mm Kg 17,775.00
5 Besi Uk.o 10 mm Kg 19,925.00
6 Besi Uk.o 12 mm Kg 18,975.00
7 Besi Uk.o 16 mm Kg 17,100.00
8 Besi Uk.o 19 mm Kg 16,825.00
9 Besi Uk.o 22 mm Kg 17,525.00
10 Besi Uk.o 25 mm Kg 17,375.00
11 Besi Ulir Uk.o 8 mm Kg 17,800.00
12 Besi Ulir Uk.o 10 mm Kg 21,450.00
13 Besi Ulir Uk.o 12 mm Kg 20,150.00
14 Besi Ulir Uk.o 16 mm Kg 20,150.00
15 Besi Ulir Uk.o 19 mm Kg 19,150.00
16 Tiang Pipa Baja o 16 tebal 6.35 mm M' 2,250,000.00
17 Tiang Pipa Baja o 16 tebal 9.00 mm M' 3,072,555.00
18 Tiang Pipa Baja o 16 tebal 9.52 mm M' 3,365,000.00
19 Tiang Pipa Baja o 16 tebal 12.00 mm M' 4,200,000.00
20 Tiang Pancang Press Trees (Spoon Pile o 40 cm, berat=199 Kg/M') M' 690,000.00
21 Pot Bearing Tumpuan Jembatan Pelengkung
22 -. Type PN 6000, Horz 20% (berat = +/- 500 kg/bh) Buah 101,500,000.00
23 -. Type PN 6000, Horz 10% (berat = +/- 500 kg/bh) Buah 115,357,500.00
24 -. Type PN 10000, Horz 20% (berat = +/- 550 kg/bh) Buah 209,857,500.00
25 -. Type PN 10000, Horz 10% (berat = +/- 550 kg/bh) Buah 243,607,500.00
26 Expantion Joint Type Strip Seal SMM 100 (berat =+/- 50 kg/m) M' 9,603,000.00
27 Metal Deck untuk Lantai Jembatan (berat =+/- 20 kg/m) M2 171,450.00
28 Balok Gelegar I (Uk. Pj. 13,6 M, tinggi 90 CM) M' 44,926,000.00
29 Balok Gelegar I (Uk. Pj. 16,6 M, tinggi 90 CM) M' 43,473,000.00
30 Balok Gelegar I (Uk. Pj. 19,6 M, tinggi 90 CM) M' 39,800,000.00
31 Balok Gelegar I (Uk. Pj. 22,6 M, tinggi 125 CM) M' 39,980,000.00
32 Balok Gelegar I (Uk. Pj. 25,6 M, tinggi 125 CM) M' 39,600,000.00
33 Balok Gelegar I (Uk. Pj. 28,6 M, tinggi 160 CM) M' 51,820,000.00
34 Balok Gelegar I (Uk. Pj. 31,6 M, tinggi 160 CM) M' 51,835,000.00
35 Tegofilm tebal 15 mm untuk Bekisting Lbr 366,500.00
36 Rangka Baja Besi Siku untuk Perancah Kg 23,600.00
37 Pengaku Inf 220 x 100 mm Kg 53,000.00
38 Besi Beton U-24 Kg 19,800.00
39 Besi Beton U-39 Kg 21,250.00
40 Besi Siku Rata - Rata Kg 21,500.00
41 Besi Plat Rata - Rata 1 s/d 5 mm Kg 21,100.00
42 Besi Plat Rata - Rata 6 s/d 10 mm Kg 21,100.00
43 Besi Plat Rata - Rata 11 s/d 16 mm Kg 21,050.00
44 Plat Strip Kg 19,800.00
45 Mur Baut biasa 4 s/d 6 cm Kg 2,250.00
46 Besi Hallow 40.40.4 mm Kg 16,950.00
47 Besi Hallow 80.80.4 mm Kg 17,000.00
48 Besi Tempa m2 346,000.00
NO MATERIAL SATUAN HARGA MATERIAL
49 Rangka atap baja ringan m2 248,000.00
50 Kawat ikat beton Kg 18,700.00
51 Kawat Duri 10 Kg Kg 68,500.00
52 Kawat Duri 30 Kg Kg 158,000.00
53 Kawat Harmonika M2 41,500.00
54 Kawat Nyamuk / Besi Roll 325,000.00
55 Kawat plastik M2 21,500.00
56 Kawat Semen Kg 19,500.00
57 Kawat anyam Roll 430,000.00
58 Kawat Benrat Kg 18,600.00
59 Ram Kawat Ayam Kg 21,100.00
60 Saringan Pasir Uk.55 ( 30 m ) Roll 545,000.00
61 Baut Baja Kg 20,500.00
62 Baut o 5/8 -25 cm Btg 10,000.00
63 Baut o 5/8 -30 cm Btg 12,000.00
64 B e u g e l Btg 40,000.00
65 Baja Tulangan Kg 19,800.00
66 Baja konstruksi / profil Kg 53,000.00
67 Saringan air pembuang Bh 29,650.00
68 Besi Penguras Bh 26,000.00
69 Paku Besi Kg 17,500.00
70 Paku Jembatan Kg 38,500.00
71 Paku seng R R T Kg 24,800.00
72 Paku ulir aluminium Kg 72,500.00
73 Paku campuran Kg 17,200.00
74 Kunci Pintu 2 Slaag/besar Bh 98,000.00
75 Kunci pintu kecil Bh 48,800.00
76 Kait angin Bh 9,800.00
77 Handle jendela Bh 6,900.00
78 Slot Pintu 4" Bh 2,600.00
79 Slot Jendela 3" Bh 2,000.00
80 List Propil Gipsum M' 48,500.00
81 Wire Mesh D-5 mm M2 46,500.00
82 Wire Mesh D-6 mm M2 58,500.00
83 Plastik Beton M2 2,950.00
III. BAHAN ALUMINIUM
1 Kusen Alm 3" CA M' 164,500.00
2 Kusen Alm 3" PC M' 112,500.00
3 Rangka jendela Alm. CA M' 114,500.00
4 Rangka jendela Alm. PC M' 125,400.00
5 Rangka Pintu Alm. CA M' 145,200.00
6 Rangka Pintu Alm. PC M' 157,500.00
7 Kusen & Pintu PVC Toilet unt 685,500.00
8 Kunci tanam 2 slag (setaraf Belluci) bh 17,500.00
9 Kunci tanam 1 slag bh 22,500.00
10 Kunci tanam antik bh 48,500.00
11 Kunci tanam biasa bh 24,500.00
12 Kunci silinder bh 205,000.00
13 Engsel 3" bh 17,200.00
14 Engsel 4" bh 24,500.00
15 Engsel 4" Besi bh 42,500.00
16 Rel Pintu Lipat 4 pintu Zinkalume Lokal unt 775,500.00
17 Handle Pintu ex Solid bh 198,500.00
18 Handle Pintu ex Solid ; termasuk kunci bh 415,000.00
19 Pull Handle Pintu ex Solid set 180,000.00
20 Ring Kunci Ex Solid bh 44,500.00
21 Handle pintu type HRE 75.01 ex CISA bh 298,000.00
22 Selinder CISA type 08510 ex CISA bh 315,000.00
23 Door Stoper bh 91,000.00
24 Door Closer bh 193,500.00
25 Slot Tanam bh 99,000.00
26 Kait Angin bh 11,400.00
27 Grendel bh 19,800.00
28 Handle knob + Kunci ex Alpha bh 122,500.00
NO MATERIAL SATUAN HARGA MATERIAL
29 Pull Handle pintu set 418,000.00
30 Handle Jendela bh 19,500.00
30 Slot Besi bh 28,500.00
31 Karet m 24,500.00
III. BAHAN ATAP
1 Atap Sirap Belian Lbr 1,850.00
2 Atap Mabang Lbr 1,000.00
3 Seng Gelombang BJLS 020 Lbr 54,500.00
4 Seng Gelombang BJLS 030 Lbr 84,500.00
5 Genteng Metal 25 mm Lbr 46,500.00
6 Genteng Metal 30 mm Lbr 52,000.00
7 Genteng Metal 35 mm Lbr 92,500.00
8 Genteng Metal Spiro Lbr 41,050.00
9 Genteng Metal type Prima Lbr 90,050.00
10 Gebteng Keramik bh 6,500.00
11 Nok Genteng Keramik bh 5,010.00
12 Nok Genteng Metal bh 95,040.00
13 Seng Datar BJLS 020 Lbr 65,000.00
14 Seng Datar BJLS 030 Lbr 84,500.00
15 Aluminium Plat 030 Lbr 108,500.00
16 GRC / Kalsiboard (tbl 6 mm) Lbr 102,500.00
17 GRC / Kalsiboard (tbl 4 mm) Lbr 77,500.00
18 Atap Zincalume Lbr 141,500.00
19 Paku Atap Zincalume Btg 1,250.00
20 Tutup Paerabung Zincalume M' 141,500.00
21 Polycarbonate t. 8 mm m2 115,000.00
IV. BAHAN FINISHING/CAT
1 Amplas Kayu Lbr 2,250.00
2 Amplas Besi Lbr 4,100.00
3 Oker Kg 58,000.00
4 Dempul Kg 17,050.00
5 Dempul Besi / Kayu Kg 34,500.00
6 Cat Dasar Kg 27,500.00
7 Thiner ( Pengencer ) Kg 8,100.00
8 Thiner ( Pengencer ) Kg 22,500.00
9 Cat Kilat Ltr 49,000.00
10 Plamur Kg 16,100.00
11 Plamur Tembok Kg 19,300.00
12 Plamur Kayu Kg 34,400.00
13 Cat Tembok Kg 35,500.00
14 Cat Tembok Catylac Kg 38,000.00
15 Cat Kayu / Besi Glotex Kg 52,800.00
16 Cat Kayu / Besi ex SEIV Kg 52,800.00
17 Cat Kayu / Besi ex MOWILEX Kg 92,500.00
18 cat Kayu / Besi ex DULUX ICI Kg 98,500.00
19 Meni kayu ex nippon Kg 42,000.00
20 Soda Api Kg 46,200.00
21 Sabun / cream pembersih kotoran Kg 185,000.00
22 Teak Oil ltr 54,500.00
23 wood filler Kg 47,500.00
24 sending sealer Kg 12,000.00
25 wood stain Kg 16,000.00
26 clear melamik/Plitur Kg 62,000.00
27 Kwas Bh 38,500.00
28 Vernis Kg 135,500.00
29 Teer Kg 38,000.00
30 Cat Dasar Emulsion ex Dulux 97,000.00
31 Cat Akhir Emulsion ex Dulux 98,000.00
32 Cat WheatherCoat ex Dulux 37,000.00
33 Cat Dasar Emulsion ex Mowilex 23,000.00
34 Cat Akhir Emulsion ex Mowilex 97,000.00
35 Cat WheatherCoat ex Mowilex 98,000.00
NO MATERIAL SATUAN HARGA MATERIAL
36 Cat Dasar Emulsion ex Vinilex 35,500.00
37 Cat Akhir Emulsion ex Vinilex 24,500.00
38 Cat WheatherCoat ex Vinilex 2,800.00
39 Lem Kayu 32,000.00
40 Seal Tape 1,950.00
41 Pelumas 36,000.00
42 Kawat Las 26,160.00
43 Sealent Clear Neutral ( 300 ml ) 33,000.00
44 minyak Bekisting 4,500.00
45 Pasangan ijuk 6,600.00
V. BAHAN LAIN - LAIN
1 Keramik Warna m2 68,750.00
2 Keramik Polos 20/20 cm m2 59,750.00
3 Keramik 20/20 cm KW1 ex Masterina m2 53,750.00
4 Keramik 20/20 cm KW2 ex Masterina m2 50,250.00
5 Keramik 30/30 cm KW1 ex masterina m2 63,750.00
6 Keramik 30 / 30 cm ex Masterina m2 57,150.00
7 Keramik 40/40 cm KW1 ex Masterina m2 83,750.00
8 Keramik 40/40 cm KW2 ex Masterina m2 76,250.00
9 Keramik 60/60 cm Polish ex Masterina m2 110,250.00
10 Keramik 60/60 cm Anti Gores m2 245,750.00
11 Granite Tile 40 / 40 cm Polish ex Granito tile m2 224,500.00
12 Batu Tempel m2 262,500.00
13 Paving Blok Type segi enam t.6 cm ( 20 x 20cm ) Natural m2 3,025.00
14 Plint Keramik type segi enam t. 6 cm ( 20 x 20 cm )Natural m2 11,500.00
15 Plint Keramik 8/30 cm ex Ggranito m2 21,000.00
16 Dinding Keramik 20 x 20 cm m2 66,500.00
17 Dinding Keramik 20 x 25 cm m2 68,500.00
18 Ornamen Profil m2 162,500.00
19 Marmer m2 486,500.00
20 Wood Flooring m2 358,500.00
21 Karpet m2 248,500.00
22 Keramik Granitto Kpg 24,500.00
23 Lis Keramik Kpg 6,500.00
24 Wallpaper m2 142,000.00
25 Klosed Jongkok Polos Bh 148,000.00
26 Klosed Jongkok Warna Bh 150,000.00
27 Wastafel Bh 625,000.00
28 Wastafel LW 240 CJ ex Tato Bh 1,710,000.00
29 Kloset duduk CW 600 J / SW 660 J ex Toto Bh 2,305,000.00
30 Kloset Jongkok type CE 6 ex Toto Bh 340,000.00
31 Urinoir type U 57 M ex Toto Bh 1,605,000.00
32 Bak air Fiberglass uk. 55x55x60 cm Bh 525,000.00
33 Shower Spray type type THX 20 NBPIV ex Toto Bh 235,000.00
34 Shower set type TX 423 sZ ex toto Bh 785,500.00
35 Floordrain type TX 1B ex Toto Bh 158,000.00
36 Tempat sabun S 11 N Bh 57,500.00
37 Kran Zink type T 30 AR13NV7N ex Toto Bh 392,500.00
38 Kitchenzink Stailless Steel 1 lubang Bh 325,000.00
39 Kran Dinding type T 23 B13V7N ex Toto Bh 148,500.00
40 Kaca Cermin Bh 287,500.00
41 Gypsumboard t.9 mm ex Jaya board Lbr 81,500.00
42 List Profil 5 cm Gypsum m 22,500.00
43 Rangka Plafon metal Furing m 118,500.00
44 Tempat Sabun Warna Bh 95,500.00
45 Floor Drain Bh 24,000.00
46 Waterprofing Coating ex Sika 112,200.00
47 Tengki Fiber Glass 1 M3 Bh 1,850,000.00
48 Kaca Polos 4.3 mm m2 98,500.00
49 Kaca Polos 4.5 mm m2 125,000.00
50 Kaca Polos 3 mm m 111,000.00
51 Kaca Polos 4 mm m 122,500.00
52 Kaca Polos 5 mm m 156,600.00
NO MATERIAL SATUAN HARGA MATERIAL
53 Kaca Polos 5 mm m 158,400.00
54 Kaca Polos 6 mm m 211,200.00
55 Kaca Polos 8 mm m 343,200.00
56 Kaca Polos 10 mm m 462,000.00
57 Kaca Motif warna m2 337,500.00
58 Kaca Patri 5 mm m2 3,525,000.00
59 Paku 1 s/d 3 cm kg 33,000.00
60 Paku 4 s/d 7 cm kg 20,800.00
61 Paku 8 s/d 12 cm kg 20,800.00
62 Paku Skrup kg 92,500.00
63 Paku Asbes / Seng kg 28,800.00
64 Paku Ripet kg 210.00
65 Paku Payung kg 210.00
66 Murboud kg 1,650.00
67 Besi Begel Kuda - Kuda kg 19,800.00
68 Klem Alm bh 15,840.00
69 Pipa GIV Medium size 1" Btg 93,300.00
70 Pipa GIV Medium size 2" Btg 344,900.00
71 Pipa GIV Medium size 3" Btg 584,700.00
72 Pipa GIV Medium size 4" Btg 835,000.00
73 Pipa GIV Medium size 6" Btg 1,300,000.00
74 Pipa PVC size 1" Btg 6,400.00
75 Pipa PVC SNI size 1" Btg 48,000.00
76 Pipa PVC SNI size 2" Btg 84,000.00
77 Pipa PVC SNI size 3" Btg 174,000.00
78 Pipa PVC SNI size 4" Btg 252,500.00
79 Pipa PVC SNI size 6" Btg 538,500.00
80 Pipa PVC dia 1/2" AW ex Wavin Btg 5,280.00
81 Pipa PVC dia 3/4" AW ex Wavin Btg 7,260.00
82 Pipa PVC dia 1" AW ex Wavin Btg 9,900.00
83 Pipa PVC dia 2" AW ex Wavin Btg 19,800.00
84 Pipa PVC dia 3" AW ex Wavin Btg 38,000.00
85 Pipa PVC dia 4" AW ex Wavin Btg 58,000.00
86 Piva PVC dia 3/4 D ex Wavin Btg 5,280.00
87 Piva PVC dia 1' D ex Wavin Btg 9,240.00
88 Piva PVC dia 2' D ex Wavin Btg 16,500.00
89 Piva PVC dia 3' D ex Wavin Btg 27,500.00
90 Piva PVC dia 4' D ex Wavin Btg 42,600.00
91 Stop Kran dia 1/2 ex Onda bh 33,000.00
92 Stop Kran dia 3/4 ex Onda bh 46,000.00
93 Stop Kran dia 1 ex Onda bh 58,000.00
94 Klep pipa dia 3/4 ex maspion bh 46,000.00
95 Klem pipa dia 3/4 ex maspion bh 33,000.00
96 Tangki air 1000 liter bh 1,875,000.00
97 Tangki air 500 liter bh 1,150,000.00
98 Pelampung otomatis bh 33,000.00
99 Roof Drain Metal bh 46,200.00
100 Septicktank biosel kap. 6000 m3 unt 7,875,000.00
101 Pengeboran sumur dalam m 87,500.00
102 Mesin jet pump kap. 250 watt unt 1,225,000.00
103 mesin pompa tekan kap. 150 watt unt 715,000.00
VI. BAHAN LISTRIK
1 PLTS SHS 50 WP Unit 8,275,000.00
2 Box Panel PVC isi 4 MCB bh 198,000.00
3 MCB 6 A bh 65,000.00
4 MCB 4 A bh 55,000.00
5 kabel NYY 2 x 2.5 mm2 m 17,750.00
6 Kabel NYN 3 x 2.5 mm3 m 22,500.00
7 Kebel Coax 3 c 75 ohm m 18,500.00
8 Kebel telephone 4 x 0.5 mm m 13,200.00
9 Isolasi bh 5,800.00
10 Klem bh 260.00
11 Mangkok Listrik bh 1,250.00
NO MATERIAL SATUAN HARGA MATERIAL
12 Outlet TV bh 58,500.00
13 Outlet Telephone bh 75,500.00
14 Sakalar Exhause bh 19,800.00
15 Down Light / PLC 13 W bh 150,000.00
16 Fitting Plafon + Lampu SL bh 95,000.00
17 Lampu TL 2 x 18 watt grille bh 329,000.00
18 Lampu TL 2 x 36 watt Grille bh 487,500.00
19 Pemadam Kebakaran Tabung 6 Kg unt 1,050,000.00
20 Penangkal Petir unt 3,250,000.00
21 Stop Kontak 100 Watt Bh 38,000.00
22 Sakelar Tunggal Bh 22,000.00
23 Sakelar Ganda Bh 28,500.00
24 Sakelar Triple Bh 22,000.00
25 Instalasi Titik Nyala Ttk 148,500.00
26 Kabel NYA 10 MM2 M' 17,500.00
27 Pipa Kabel M' 4,600.00
1. MEMBUAT 1 M
3
BETON MUTU f'c = 7,4 MPa ( K 100 ), SLUMP ( 12 2 ) CM, w/c = 0.87
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.1 PB.01
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 247.000 402,610.00
2 Pasir Pasang Kg 116.43 869.000 101,176.43
3 Kerikil Batu 2/ 3 cm Kg 551.85 999.000 551,300.00
4 Air Liter 0.00 215.000 0.00
Jumlah 1,055,086.43
C Jumlah A + B 1,197,454.43
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,197,454.43
2. MEMBUAT 1 M
3
BETON MUTU f'c = 9,8 MPa ( K 125 ), SLUMP ( 12 2 ) CM, w/c = 0.78
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.2 PB.02
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 276.000 449,880.00
2 Pasir Pasang Kg 116.43 828.000 96,402.86
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,012.000 558,474.07
4 Air Liter 0.00 215.000 0.00
Jumlah 1,104,756.93
C Jumlah A + B 1,247,124.93
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,247,124.93
PEKERJAAN BETON ( PB )
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
3. MEMBUAT 1 M
3
BETON MUTU f'c = 12,2 MPa ( K 150 ), SLUMP ( 12 2 ) CM, w/c = 0.72
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.3 PB.03
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 299.000 487,370.00
2 Pasir Pasang Kg 116.43 799.000 93,026.43
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,017.000 561,233.33
4 Air Liter 0.00 215.000 0.00
Jumlah 1,141,629.76
C Jumlah A + B 1,283,997.76
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,283,997.76
4. MEMBUAT 1 M
3
LANTAI KERJA BETON MUTU f'c = 7, 4 MPa ( K 100 ), SLUMP ( 3 - 6 ) CM, w/c = 0.87
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.4 PB.04
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.200 78,000.00
2 Mandor Org / Hari 90,000.00 0.060 5,400.00
3 Tukang Batu Org / Hari 90,000.00 0.200 18,000.00
4 Kepala Tukang Org / Hari 103,500.00 0.020 2,070.00
Jumlah 103,470.00
B BAHAN
1 Semen Kg 1,630.00 230.000 374,900.00
2 Pasir Pasang Kg 116.43 893.000 103,970.71
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,027.000 566,751.85
4 Air Liter 0.00 200.000 0.00
Jumlah 1,045,622.57
C Jumlah A + B 1,149,092.57
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,149,092.57
5. MEMBUAT 1 M
3
BETON MUTU f'c = 14, 5 MPa ( K 175 ), SLUMP ( 12 2 ) CM, w/c = 0.66
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.5 PB.05
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 326.000 531,380.00
2 Pasir Pasang Kg 116.43 760.000 88,485.71
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,029.000 567,855.56
4 Air Liter 0.00 215.000 0.00
Jumlah 1,187,721.27
C Jumlah A + B 1,330,089.27
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,330,089.27
6. MEMBUAT 1 M
3
BETON MUTU f'c = 16, 9 MPa ( K 200 ), SLUMP ( 12 2 ) CM, w/c = 0.61
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.6 PB.06
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 352.000 573,760.00
2 Pasir Pasang Kg 116.43 731.000 85,109.29
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,031.000 568,959.26
4 Air Liter 0.00 215.000 0.00
Jumlah 1,227,828.54
C Jumlah A + B 1,370,196.54
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,370,196.54
7. MEMBUAT 1 M
3
BETON MUTU f'c = 19, 3 MPa ( K 225 ), SLUMP ( 12 2 ) CM, w/c = 0.58
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.7 PB.07
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 371.000 604,730.00
2 Pasir Pasang Kg 116.43 698.000 81,267.14
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,047.000 577,788.89
4 Air Liter 0.00 215.000 0.00
Jumlah 1,263,786.03
C Jumlah A + B 1,406,154.03
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,406,154.03
8. MEMBUAT 1 M
3
BETON MUTU f'c = 21, 7 MPa ( K 250 ), SLUMP ( 12 2 ) CM, w/c = 0.56
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.8 PB.08
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 384.000 625,920.00
2 Pasir Pasang Kg 116.43 692.000 80,568.57
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,039.000 573,374.07
4 Air Liter 0.00 215.000 0.00
Jumlah 1,279,862.65
C Jumlah A + B 1,422,230.65
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,422,230.65
9. MEMBUAT 1 M
3
BETON MUTU f'c = 24,0 MPa ( K 275 ), SLUMP ( 12 2 ) CM, w/c = 0.53
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.9 PB.09
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 406.000 661,780.00
2 Pasir Pasang Kg 116.43 684.000 79,637.14
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,026.000 566,200.00
4 Air Liter 0.00 215.000 0.00
Jumlah 1,307,617.14
C Jumlah A + B 1,449,985.14
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,449,985.14
10. MEMBUAT 1 M
3
BETON MUTU f'c = 26,4 MPa ( K 300 ), SLUMP ( 12 2 ) CM, w/c = 0.52
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.10 PB.10
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 413.000 673,190.00
2 Pasir Pasang Kg 116.43 681.000 79,287.86
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,021.000 563,440.74
4 Air Liter 0.00 215.000 0.00
Jumlah 1,315,918.60
C Jumlah A + B 1,458,286.60
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,458,286.60
11. MEMBUAT 1 M
3
BETON MUTU f'c = 28,8 MPa ( K 325 ), SLUMP ( 12 2 ) CM, w/c = 0.49
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.11 PB.11
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 439.000 715,570.00
2 Pasir Pasang Kg 116.43 670.000 78,007.14
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,006.000 555,162.96
4 Air Liter 0.00 215.000 0.00
Jumlah 1,348,740.11
C Jumlah A + B 1,491,108.11
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,491,108.11
12. MEMBUAT 1 M
3
BETON MUTU f'c = 31,2 MPa ( K 350 ), SLUMP ( 12 2 ) CM, w/c = 0.48
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.12 PB.12
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 1.650 107,250.00
2 Mandor Org / Hari 90,000.00 0.083 7,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Kepala Tukang Org / Hari 103,500.00 0.028 2,898.00
Jumlah 142,368.00
B BAHAN
1 Semen Kg 1,630.00 448.000 730,240.00
2 Pasir Pasang Kg 116.43 667.000 77,657.86
3 Kerikil Batu 2/ 3 cm Kg 551.85 1,000.000 551,851.85
4 Air Liter 0.00 215.000 0.00
Jumlah 1,359,749.71
C Jumlah A + B 1,502,117.71
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,502,117.71
13. MEMBUAT 1 M
3
BETON KEDAP AIR DENGAN STROROX - 100
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.13 PB.13
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 2.100 136,500.00
2 Mandor Org / Hari 90,000.00 0.105 9,450.00
3 Tukang Batu Org / Hari 90,000.00 0.350 31,500.00
4 Kepala Tukang Org / Hari 103,500.00 0.035 3,622.50
Jumlah 181,072.50
B BAHAN
1 Semen Kg 1,630.00 400.000 652,000.00
2 Pasir Pasang M
3
116.43 0.480 55.89
3 Kerikil Batu 2/ 3 cm M
3
551.85 0.800 441.48
4 Strorox - 100 Kg 150,000.00 1.200 180,000.00
Jumlah 832,497.37
C Jumlah A + B 1,013,569.87
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 1,013,569.87
14. MEMBUAT 1 M
'
PVC WATERSTOP LEBAR 150 MM
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.14 PB.14
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.060 3,900.00
2 Mandor Org / Hari 90,000.00 0.003 270.00
3 Tukang Batu / Pipa Org / Hari 90,000.00 0.030 2,700.00
4 Kepala Tukang Org / Hari 103,500.00 0.003 310.50
Jumlah 7,180.50
B BAHAN
1 Waterstop Lebar 150 mm M' 85,000.00 1.050 89,250.00
Jumlah 89,250.00
C Jumlah A + B 96,430.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 96,430.50
15. MEMBUAT 1 M
'
PVC WATERSTOP LEBAR 200 MM
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.15 PB.15
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.070 4,550.00
2 Mandor Org / Hari 90,000.00 0.007 630.00
3 Tukang Batu / Pipa Org / Hari 90,000.00 0.035 3,150.00
4 Kepala Tukang Org / Hari 103,500.00 0.004 414.00
Jumlah 8,744.00
B BAHAN
1 Waterstop Lebar 200 mm M' 100,000.00 1.050 105,000.00
Jumlah 105,000.00
C Jumlah A + B 113,744.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 113,744.00
16. MEMBUAT 1 M
'
PVC WATERSTOP LEBAR 230 MM - 320 MM
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.16 PB.16
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.080 5,200.00
2 Mandor Org / Hari 90,000.00 0.004 360.00
3 Tukang Batu / Pipa Org / Hari 90,000.00 0.040 3,600.00
4 Kepala Tukang Org / Hari 103,500.00 0.004 414.00
Jumlah 9,574.00
B BAHAN
1 Waterstop Lebar 230 mm - 320 mm M' 125,000.00 1.050 131,250.00
Jumlah 131,250.00
C Jumlah A + B 140,824.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 140,824.00
17. PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.17 PB.17
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.070 4,550.00
2 Mandor Org / Hari 90,000.00 0.004 360.00
3 Tukang Besi Org / Hari 90,000.00 0.070 6,300.00
4 Kepala Tukang Org / Hari 103,500.00 0.007 724.50
Jumlah 11,934.50
B BAHAN
1 Besi Beton ( Polos / Ulir ) Kg 17,100.00 10.500 179,550.00
2 Kawat Beton Kg 18,700.00 0.150 2,805.00
Jumlah 182,355.00
C Jumlah A + B 194,289.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah Per 10 Kg 194,289.50
Jumlah Per 1 Kg 19,428.95
18. MEMASANG 10 KG KABEL PRESSTRESSED POLOS/STRAND
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.18 PB.18
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.050 3,250.00
2 Mandor Org / Hari 90,000.00 0.003 270.00
3 Tukang Besi Org / Hari 90,000.00 0.050 4,500.00
4 Kepala Tukang Org / Hari 103,500.00 0.005 517.50
Jumlah 8,537.50
B BAHAN
1 Besi Beton ( Polos / Ulir ) Kg 17,100.00 10.500 179,550.00
2 Kawat Beton Kg 18,700.00 0.100 1,870.00
Jumlah 181,420.00
C Jumlah A + B 189,957.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah Per 10 Kg 189,957.50
Jumlah Per 1 Kg 18,995.75
19. MEMASANG 10 KG JARING KAWAT BAJA/ WIRE MESH
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.19 PB.19
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.025 1,625.00
2 Mandor Org / Hari 90,000.00 0.001 90.00
3 Tukang Besi Org / Hari 90,000.00 0.025 2,250.00
4 Kepala Tukang Org / Hari 103,500.00 0.025 2,587.50
Jumlah 6,552.50
B BAHAN
1 Jaring Kawat Baja di Las Kg 21,851.50 10.200 222,885.34
2 Kawat Beton Kg 18,700.00 0.050 935.00
Jumlah 223,820.34
C Jumlah A + B 230,372.84
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah Per 10 Kg 230,372.84
Jumlah Per 1 Kg 23,037.28
20. MEMASANG 1 M
2
BEKISTING UNTUK PONDASI
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.20 PB.20
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.520 33,800.00
2 Mandor Org / Hari 90,000.00 0.026 2,340.00
3 Tukang Kayu Org / Hari 90,000.00 0.260 23,400.00
4 Kepala Tukang Org / Hari 103,500.00 0.026 2,691.00
Jumlah 62,231.00
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.040 65,400.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.300 5,160.00
3 Minyak Bekisting Liter 6,500.00 0.100 650.00
Jumlah 71,210.00
C Jumlah A + B 133,441.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 133,441.00
21. MEMASANG 1 M
2
BEKISTING UNTUK SLOOF
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.21 PB.21
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.520 33,800.00
2 Mandor Org / Hari 90,000.00 0.026 2,340.00
3 Tukang Kayu Org / Hari 90,000.00 0.260 23,400.00
4 Kepala Tukang Org / Hari 103,500.00 0.026 2,691.00
Jumlah 62,231.00
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.045 73,575.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.300 5,160.00
3 Minyak Bekisting Liter 6,500.00 0.100 650.00
Jumlah 79,385.00
C Jumlah A + B 141,616.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 141,616.00
22. MEMASANG 1 M
2
BEKISTING UNTUK KOLOM
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.22 PB.22
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.660 42,900.00
2 Mandor Org / Hari 90,000.00 0.033 2,970.00
3 Tukang Kayu Org / Hari 90,000.00 0.330 29,700.00
4 Kepala Tukang Org / Hari 103,500.00 0.033 3,415.50
Jumlah 78,985.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.040 65,400.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.400 6,880.00
3 Minyak Bekisting Liter 6,500.00 0.200 1,300.00
4 Balok Kayu Kls II M
3
3,265,000.00 0.015 48,975.00
5 Plywood Tebal 9 mm Lembar 168,000.00 0.350 58,800.00
6 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 2.000 19,000.00
Jumlah 200,355.00
C Jumlah A + B 279,340.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 279,340.50
23. MEMASANG 1 M
2
BEKISTING UNTUK BALOK
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.23 PB.23
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.660 42,900.00
2 Mandor Org / Hari 90,000.00 0.033 2,970.00
3 Tukang Kayu Org / Hari 90,000.00 0.330 29,700.00
4 Kepala Tukang Org / Hari 103,500.00 0.033 3,415.50
Jumlah 78,985.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.040 65,400.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.400 6,880.00
3 Minyak Bekisting Liter 6,500.00 0.200 1,300.00
4 Balok Kayu Kls II M
3
3,265,000.00 0.018 58,770.00
5 Plywood Tebal 9 mm Lembar 168,000.00 0.350 58,800.00
6 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 2.000 19,000.00
Jumlah 210,150.00
C Jumlah A + B 289,135.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 289,135.50
24. MEMASANG 1 M
2
BEKISTING UNTUK LANTAI
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.24.a PB.24
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.660 42,900.00
2 Mandor Org / Hari 90,000.00 0.033 2,970.00
3 Tukang Kayu Org / Hari 90,000.00 0.330 29,700.00
4 Kepala Tukang Org / Hari 103,500.00 0.033 3,415.50
Jumlah 78,985.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.040 65,400.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.400 6,880.00
3 Minyak Bekisting Liter 6,500.00 0.200 1,300.00
4 Balok Kayu Kls II M
3
3,265,000.00 0.015 48,975.00
5 Papan Kayu Kls III M
3
1,975,000.00 0.015 29,427.50
6 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 6.000 57,000.00
Jumlah 208,982.50
C Jumlah A + B 287,968.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 287,968.00
25. MEMASANG 1 M
2
BEKISTING UNTUK DINDING
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.25 PB.25
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.660 42,900.00
2 Mandor Org / Hari 90,000.00 0.033 2,970.00
3 Tukang Kayu Org / Hari 90,000.00 0.330 29,700.00
4 Kepala Tukang Org / Hari 103,500.00 0.033 3,415.50
Jumlah 78,985.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.030 49,050.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.400 6,880.00
3 Minyak Bekisting Liter 6,500.00 0.200 1,300.00
4 Balok Kayu Kls II M
3
3,265,000.00 0.020 65,300.00
5 Plywood Tebal 9 mm Lembar 1,975,000.00 0.350 691,250.00
6 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 3.000 28,500.00
7 Spacer Buah 0.00 4.000 0.00
Jumlah 842,280.00
C Jumlah A + B 921,265.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 921,265.50
26. MEMASANG 1 M
2
BEKISTING UNTUK TANGGA
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.26 PB.26
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.660 42,900.00
2 Mandor Org / Hari 90,000.00 0.033 2,970.00
3 Tukang Kayu Org / Hari 90,000.00 0.330 29,700.00
4 Kepala Tukang Org / Hari 103,500.00 0.033 3,415.50
Jumlah 78,985.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.030 49,050.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.400 6,880.00
3 Minyak Bekisting Liter 6,500.00 0.150 975.00
4 Balok Kayu Kls II M
3
3,265,000.00 0.015 48,975.00
5 Plywood Tebal 9 mm Lembar 1,975,000.00 0.350 691,250.00
6 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 2.000 19,000.00
Jumlah 816,130.00
C Jumlah A + B 895,115.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 895,115.50
27. MEMASANG 1 M
2
JEMBATAN UNTUK PENGECORAN BETON
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.27 PB.27
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.150 9,750.00
2 Mandor Org / Hari 90,000.00 0.008 720.00
3 Tukang Kayu Org / Hari 90,000.00 0.050 4,500.00
4 Kepala Tukang Org / Hari 103,500.00 0.005 517.50
Jumlah 15,487.50
B BAHAN
1 Kayu Kls III ( Papan ) M
3
1,975,000.00 0.026 52,140.00
2 Paku 5 cm - 10 cm Kg 17,200.00 0.600 10,320.00
3 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 0.500 4,750.00
Jumlah 67,210.00
C Jumlah A + B 82,697.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 82,697.50
28. MEMBUAT 1 M
3
PONDASI BETON BERTULANG 150 Kg BESI + BEKISTING
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.28 PB.28
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 5.300 344,500.00
2 Mandor Org / Hari 90,000.00 0.265 23,850.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Tukang Kayu Org / Hari 90,000.00 1.300 117,000.00
5 Tukang Besi Org / Hari 90,000.00 1.050 94,500.00
6 Kepala Tukang Org / Hari 103,500.00 0.262 27,117.00
Jumlah 631,717.00
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.200 327,000.00
2 Paku 5 cm - 10 cm Kg 17,200.00 1.500 25,800.00
3 Minyak Bekisting Liter 6,500.00 0.400 2,600.00
4 Besi Beton Polos Kg 19,800.00 157.500 3,118,500.00
5 Kawat Beton Kg 18,700.00 2.250 42,075.00
6 Semen Kg 1,630.00 336.000 547,680.00
7 Pasir Pasang M
3
163,000.00 0.540 88,020.00
8 Kerikil M
3
745,000.00 0.810 603,450.00
Jumlah 4,755,125.00
C Jumlah A + B 5,386,842.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 5,386,842.00
29. MEMBUAT 1 M
3
SLOOF BETON BERTULANG 200 Kg BESI + BEKISTING ( PB.29 )
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI DT - 91 - 0008 - 2007 - 6.29
PB.29
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 5.650 367,250.00
2 Mandor Org / Hari 90,000.00 0.283 25,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Tukang Kayu Org / Hari 90,000.00 1.560 140,400.00
5 Tukang Besi Org / Hari 90,000.00 1.400 126,000.00
6 Kepala Tukang Org / Hari 103,500.00 0.323 33,430.50
Jumlah 717,300.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.270 441,450.00
2 Paku 5 cm - 12 cm Kg 17,200.00 2.000 34,400.00
3 Minyak Bekisting Liter 6,500.00 0.600 3,900.00
4 Besi Beton Polos Kg 19,800.00 210.000 4,158,000.00
5 Kawat Beton Kg 18,700.00 3.000 56,100.00
6 Semen Kg 1,630.00 336.000 547,680.00
7 Pasir Pasang M
3
163,000.00 0.540 88,020.00
8 Kerikil M
3
745,000.00 0.810 603,450.00
Jumlah 5,933,000.00
C Jumlah A + B 6,650,300.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 6,650,300.50
30. MEMBUAT 1 M
3
KOLOM BETON BERTULANG 300 Kg BESI + BEKISTING
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.30 PB.30
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 7.050 458,250.00
2 Mandor Org / Hari 90,000.00 0.353 31,770.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Tukang Kayu Org / Hari 90,000.00 1.650 148,500.00
5 Tukang Besi Org / Hari 90,000.00 2.100 189,000.00
6 Kepala Tukang Org / Hari 103,500.00 0.403 41,710.50
Jumlah 893,980.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.400 654,000.00
2 Paku 5 cm - 12 cm Kg 17,200.00 4.000 68,800.00
3 Minyak Bekisting Liter 6,500.00 2.000 13,000.00
4 Besi Beton Polos Kg 19,800.00 315.000 6,237,000.00
5 Kawat Beton Kg 18,700.00 4.500 84,150.00
6 Semen Kg 1,630.00 336.000 547,680.00
7 Pasir Pasang M
3
163,000.00 0.540 88,020.00
8 Kerikil M
3
745,000.00 0.810 603,450.00
9 Balok Kayu Kls II M
3
3,265,000.00 0.150 489,750.00
10 Plywood Tebal 9 mm Lembar 1,975,000.00 0.350 691,250.00
11 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 20.000 190,000.00
Jumlah 9,667,100.00
C Jumlah A + B 10,561,080.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 10,561,080.50
31. MEMBUAT 1 M
3
BALOK BETON BERTULANG 200 Kg BESI + BEKISTING
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.31 PB.31
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 6.350 412,750.00
2 Mandor Org / Hari 90,000.00 0.318 28,620.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Tukang Kayu Org / Hari 90,000.00 1.650 148,500.00
5 Tukang Besi Org / Hari 90,000.00 1.400 126,000.00
6 Kepala Tukang Org / Hari 103,500.00 0.333 34,465.50
Jumlah 775,085.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.320 523,200.00
2 Paku 5 cm - 12 cm Kg 17,200.00 3.200 55,040.00
3 Minyak Bekisting Liter 6,500.00 1.600 10,400.00
4 Besi Beton Polos Kg 19,800.00 210.000 4,158,000.00
5 Kawat Beton Kg 18,700.00 3.000 56,100.00
6 Semen Kg 1,630.00 336.000 547,680.00
7 Pasir Pasang M
3
163,000.00 0.540 88,020.00
8 Kerikil M
3
745,000.00 0.810 603,450.00
9 Balok Kayu Kls II M
3
3,265,000.00 0.140 457,100.00
10 Plywood Tebal 9 mm Lembar 1,975,000.00 2.800 5,530,000.00
11 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 16.000 152,000.00
Jumlah 12,180,990.00
C Jumlah A + B 12,956,075.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 12,956,075.50
32. MEMBUAT 1 M
3
KOLOM BETON BERTULANG 150 Kg BESI + BEKISTING
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.32 PB.32
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 5.300 344,500.00
2 Mandor Org / Hari 90,000.00 0.265 23,850.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Tukang Kayu Org / Hari 90,000.00 1.300 117,000.00
5 Tukang Besi Org / Hari 90,000.00 1.050 94,500.00
6 Kepala Tukang Org / Hari 103,500.00 0.262 27,117.00
Jumlah 631,717.00
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.320 523,200.00
2 Paku 5 cm - 12 cm Kg 17,200.00 3.200 55,040.00
3 Minyak Bekisting Liter 6,500.00 1.600 10,400.00
4 Besi Beton Polos Kg 19,800.00 157.500 3,118,500.00
5 Kawat Beton Kg 18,700.00 2.250 42,075.00
6 Semen Kg 1,630.00 336.000 547,680.00
7 Pasir Pasang M
3
163,000.00 0.540 88,020.00
8 Kerikil M
3
745,000.00 0.810 603,450.00
9 Balok Kayu Kls II M
3
3,265,000.00 0.140 457,100.00
10 Plywood Tebal 9 mm Lembar 1,975,000.00 2.800 5,530,000.00
11 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 32.000 304,000.00
Jumlah 11,279,465.00
C Jumlah A + B 11,911,182.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 11,911,182.00
33. MEMBUAT 1 M
3
DINDING BETON BERTULANG 150 Kg BESI + BEKISTING
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.33 PB.33
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 5.300 344,500.00
2 Mandor Org / Hari 90,000.00 0.265 23,850.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Tukang Kayu Org / Hari 90,000.00 1.300 117,000.00
5 Tukang Besi Org / Hari 90,000.00 1.050 94,500.00
6 Kepala Tukang Org / Hari 103,500.00 0.262 27,117.00
Jumlah 631,717.00
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.240 392,400.00
2 Paku 5 cm - 12 cm Kg 17,200.00 3.200 55,040.00
3 Minyak Bekisting Liter 6,500.00 1.600 10,400.00
4 Besi Beton Polos Kg 19,800.00 157.500 3,118,500.00
5 Kawat Beton Kg 18,700.00 2.250 42,075.00
6 Semen Kg 1,630.00 336.000 547,680.00
7 Pasir Pasang M
3
163,000.00 0.540 88,020.00
8 Kerikil M
3
745,000.00 0.810 603,450.00
9 Balok Kayu Kls II M
3
3,265,000.00 0.140 457,100.00
10 Plywood Tebal 9 mm Lembar 1,975,000.00 2.800 5,530,000.00
11 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 24.000 228,000.00
Jumlah 11,072,665.00
C Jumlah A + B 11,704,382.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 11,704,382.00
34. MEMBUAT 1 M
3
DINDING BETON BERTULANG 200 Kg BESI + BEKISTING
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.34 PB.34
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 5.650 367,250.00
2 Mandor Org / Hari 90,000.00 0.283 25,470.00
3 Tukang Batu Org / Hari 90,000.00 0.275 24,750.00
4 Tukang Kayu Org / Hari 90,000.00 1.560 140,400.00
5 Tukang Besi Org / Hari 90,000.00 1.400 126,000.00
6 Kepala Tukang Org / Hari 103,500.00 0.323 33,430.50
Jumlah 717,300.50
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.250 408,750.00
2 Paku 5 cm - 12 cm Kg 17,200.00 3.000 51,600.00
3 Minyak Bekisting Liter 6,500.00 1.200 7,800.00
4 Besi Beton Polos Kg 19,800.00 210.000 4,158,000.00
5 Kawat Beton Kg 18,700.00 3.000 56,100.00
6 Semen Kg 1,630.00 336.000 547,680.00
7 Pasir Pasang M
3
163,000.00 0.540 88,020.00
8 Kerikil M
3
745,000.00 0.810 603,450.00
9 Balok Kayu Kls II M
3
3,265,000.00 0.105 342,825.00
10 Plywood Tebal 9 mm Lembar 1,975,000.00 2.500 4,937,500.00
11 Dolken 8 - 10 cm Panjang 4 Meter Batang 9,500.00 14.000 133,000.00
Jumlah 11,334,725.00
C Jumlah A + B 12,052,025.50
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 12,052,025.50
35. MEMBUAT 1 M' KOLOM PRAKTIS BETON BERTULANG 11 x 11 CM
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.35 PB.35
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.180 11,700.00
2 Mandor Org / Hari 90,000.00 0.009 810.00
3 Tukang Batu Org / Hari 90,000.00 0.020 1,800.00
4 Tukang Kayu Org / Hari 90,000.00 0.020 1,800.00
5 Tukang Besi Org / Hari 90,000.00 0.020 1,800.00
6 Kepala Tukang Org / Hari 103,500.00 0.006 621.00
Jumlah 18,531.00
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.002 3,270.00
2 Paku 5 cm - 12 cm Kg 17,200.00 0.010 172.00
3 Minyak Bekisting Liter 6,500.00 0.000 0.00
4 Besi Beton Polos Kg 19,800.00 3.000 59,400.00
5 Kawat Beton Kg 18,700.00 0.450 8,415.00
6 Semen Kg 1,630.00 4.000 6,520.00
7 Pasir Pasang M
3
163,000.00 0.006 978.00
8 Kerikil M
3
745,000.00 0.009 6,705.00
Jumlah 85,460.00
C Jumlah A + B 103,991.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 103,991.00
36. MEMBUAT 1 M' RING BALOK BETON BERTULANG 10 x 15 CM
Analisa Biaya Konstruksi ( ABK ) berdasarkan SNI 7394 - 2008 - 6.36 PB.36
HARGA BIAYA
NO. U R A I A N SATUAN SATUAN INDEKS SATUAN
( Rp ) ( Rp )
A TENAGA KERJA
1 Pekerja Org / Hari 65,000.00 0.297 19,305.00
2 Mandor Org / Hari 90,000.00 0.015 1,350.00
3 Tukang Batu Org / Hari 90,000.00 0.033 2,970.00
4 Tukang Kayu Org / Hari 90,000.00 0.033 2,970.00
5 Tukang Besi Org / Hari 90,000.00 0.033 2,970.00
6 Kepala Tukang Org / Hari 103,500.00 0.010 1,035.00
Jumlah 30,600.00
B BAHAN
1 Kayu Kls III M
3
1,635,000.00 0.003 4,905.00
2 Paku 5 cm - 12 cm Kg 17,200.00 0.020 344.00
3 Minyak Bekisting Liter 6,500.00 0.000 0.00
4 Besi Beton Polos Kg 19,800.00 3.600 71,280.00
5 Kawat Beton Kg 18,700.00 0.050 935.00
6 Semen Kg 1,630.00 5.500 8,965.00
7 Pasir Pasang M
3
163,000.00 0.009 1,467.00
8 Kerikil M
3
745,000.00 0.015 11,175.00
Jumlah 99,071.00
C Jumlah A + B 129,671.00
D Biaya Umum & Keuntungan = % x C 0.00
Jumlah 129,671.00