1 PADA PELAKSANAAN PEKERJAAN PEMBUATAN SALURAN PRIMER UNTUK


IRIGASI , SEPANJANG 2 KM, DENGAN BENTUK SALURAN TRAPEZIUM
DENGAN LEBAR BAGIAN DASAR ADALAH 3,00 METER, DAN KEMIRINGAN
SALURAN 1 : 1, SERTA TINGGI SALURAN 1,50 M. DENGAN JENIS TANAH PADA
UMUMNYA ADALAH TANAH BERCAMPUR KERIKIL.
UNTUK PEKERJAAN TERSEBUT, KONTRAKTOR PELAKSANA DIHADAPKAN
PADA PILIHAN ALAT BERAT KARENA KETERBATASAN WAKTU YANG
DISEDIAKAN, YAKNI ADA 2 Unit EXCAVATOR TYPE S DENGAN BC = 0.8 M3,
DAN 1 Unit WHEEL LOADER Type M DENGAN BC = 2,4 M3.
MATERIAL HASIL GALIAN DIANGKUT UNTUK DIBAWA KETEMPAT
PEMBUANGAN DENGAN JARAK 4 KM, DARI LOKASI PENGGALIAN DENGAN
DT KAPASITAS 8,0 M3
JIKA SAUDARA SEBAGAI PELAKSANA PEKERJAAN TERSEBUT, JENIS ALAT
YANG MANA YANG AKAN SAUDARA GUNAKAN, BERAPA WAKTU YANG
PERLUKAN UNTUK PENYELESAIAN PEKERJAAN TERSEBUT, SEBUTKAN
ALASAN PEMILIHAN ALAT.

KEMENTERIAN PENDIDIKAN DAN KEBUDAYAAN


UNIVERSITAS LAMBUNG MANGKURAT

FAKULTAS TEKNIK
Jalan Brigjen H. Hasan Basri Banjarmasin Kalimantan Selatan 70123
Telepon (0511) 3304503 Faximili (0511) 3304503

PT.ANZ BANK
GEDUNG ANZ SQUARE Lt.6
THAMRIN NINE DEVELOPMENT
JLN. MH. THAMRIN KAV. 9 10
JAKARTA PUSAT (10230)
Up. Alam/Andhika

Anda mungkin juga menyukai