Anda di halaman 1dari 2

ANALISA PENDUKUNG

MATA PEMBAYARAN 6.1.2 / M


No.

U R A I A N

SATUAN

KOEFISIAN

A.
1
2
3
4

UPAH
Mandor
Kepala Tukang
Tukang
Pekerja Terlatih

OH
OH
OH
OH

0.02
0.01
0.02
0.04

B.
1
2
3

MATERIAL
Kayu utk Perancah
Beton Cyclop
Paku

M
M
Kg

0.12
0.10
0.23

C.

PERALATAN

Harga Satuan Rp.

J. HARGA
(Rp.)

TOTAL HARGA
(Rp.)

84,000.00
77,000.00
72,000.00
58,000.00

1,680.00
770.00
1,440.00
2,320.00

2,751,000.00
1,017,885.68
23,000.00

330,120.00
101,788.57
5,221.11

443,339.68