JADW AL PENYELESAIAN PEKERJAAN DALAM KURUN WAKTU BERSAMAAN UNTUK MAKSIMAL 20 (DUA PULUH) LOKASI

SITAC & CME TOWER PT . DAYAMITRA TELEKOMUNIKASI


AREA JATENG DIY & JAWA TIMUR
ID Task Name Duration Start Finish Predecessors '10 Jan 2, '11 Jan 9, '11 Jan 16, '11 Jan 23, '11 Jan 30, '11 Feb 6, '11 Feb 13, '11 Feb 20, '11 Feb 27, '11 Mar 6, '11 Mar 13, '11 Mar 20, '11 Mar 27, '11
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
1 Pekerjaan Sitac & CME Tower 72 days? Mon 1/10/11 Tue 3/22/11
2 Pekerjaan Pra Implementasi / Sitac 65 days? Mon 1/10/11 Tue 3/15/11
3 Ready For Construction 27 days? Mon 1/10/11 Sat 2/5/11
4 Penentuan Kandidat Lokasi 5 days Mon 1/10/11 Fri 1/14/11
5 SPMK/PO SITAC & Penerbitan Titik Nominal Lokasi dari DMT 0 days Mon 1/10/11 Mon 1/10/11 1/10/2011
6 SSR ( Pencarian Kandidat Lokasi ) 3 days Mon 1/10/11 Wed 1/12/11 5 1/10/2011 1/12/2011
7 Persetujuan SSR oleh DMT 0 days Wed 1/12/11 Wed 1/12/11 6 1/12/2011
8 Negosiasi Harga Lahan / Penerbitan BAK 2 days Thu 1/13/11 Fri 1/14/11 7 1/13/2011 1/14/2011
9 Perijinan Lingkungan & Rekom Camat 12 days Sat 1/15/11 Wed 1/26/11
10 Ijin Warga Termasuk Persetujuan RT-RW 7 days Sat 1/15/11 Fri 1/21/11 8 1/15/2011 1/21/2011
11 Rekomendasi Lurah & Camat 2 days Tue 1/25/11 Wed 1/26/11 10,13 1/25/2011 1/26/2011
12 Legalitas , Pembayaran Lahan & IMB 19 days? Tue 1/18/11 Sat 2/5/11
13 Pengumpulan Data Lahan 7 days Tue 1/18/11 Mon 1/24/11 10SS+3 days 1/18/2011 1/24/2011
14 Pengajuan Data Lahan ke DMT 1 day? Thu 1/27/11 Thu 1/27/11 13,11 1/27/2011 1/27/2011
15 Verikasi Data Lahan / Dokumen Sitac oleh DMT 0 days Thu 1/27/11 Thu 1/27/11 14 1/27/2011
16 Penerbitan PKS oleh DMT 0 days Thu 1/27/11 Thu 1/27/11 15 1/27/2011
17 Penandatanganan PKS & Legalisir PKS oleh Notaris 2 days Fri 1/28/11 Sat 1/29/11 16 1/28/2011 1/29/2011
18 Pengiriman Dokumen PKS yang Telah Terligalisir 1 day Sun 1/30/11 Sun 1/30/11 17 1/30/2011 1/30/2011
19 Pembayaran Lahan oleh DMT 0 days Sun 1/30/11 Sun 1/30/11 18 1/30/2011
20 Pemasukan Dokumen Perijinan / Resi Perijinan / Ijin Prinsip 7 days Sun 1/30/11 Sat 2/5/11 17 1/30/2011 2/5/2011
21 RFC Setelah Pembayaran Lahan dan Resi Perijinan 0 days Sat 2/5/11 Sat 2/5/11 19,20,28 2/5/2011
22 IMB Terbit 45 days Sun 1/30/11 Tue 3/15/11 17 1/30/2011 3/15/2011
23 Pekerjaan Implementasi ( Tower CME ) 54 days Thu 1/27/11 Tue 3/22/11
24 Ready for Intallation 43 days Thu 1/27/11 Fri 3/11/11
25 Persiapan 12 days Thu 1/27/11 Tue 2/8/11
26 SPMK/PO CME oleh DMT 0 days Thu 1/27/11 Thu 1/27/11 15 1/27/2011
27 Soiltest (Sondir & Booring Report) 3 days Fri 1/28/11 Sun 1/30/11 26 1/28/2011 1/30/2011
28 As Plan Drawing oleh DMT 0 days Sun 1/30/11 Sun 1/30/11 27 1/30/2011
29 Koordinasi Persiapan Team 1 day Sun 2/6/11 Sun 2/6/11 21,28 2/6/2011 2/6/2011
30 Pembersihan Lokasi 2 days Mon 2/7/11 Tue 2/8/11 29 2/7/2011 2/8/2011
31 Bouwplank 1 day Tue 2/8/11 Tue 2/8/11 30SS+1 day 2/8/2011 2/8/2011
32 Pengadaan Air Kerja 1 day Tue 2/8/11 Tue 2/8/11 30SS+1 day 2/8/2011 2/8/2011
33 Tower , Shelter CKD , ME & PLN 43 days Fri 1/28/11 Fri 3/11/11
34 Tower 31 days Wed 2/9/11 Fri 3/11/11
35 Pondasi Tower (Asumsi Pondasi Standard/Dangkal) 21 days Wed 2/9/11 Tue 3/1/11 31
36 Galian 7 days Wed 2/9/11 Tue 2/15/11 31 2/9/2011 2/15/2011
37 Lantai Kerja 2 days Mon 2/14/11 Tue 2/15/11 36SS+5 days 2/14/2011 2/15/2011
38 Pembesian 7 days Sun 2/13/11 Sat 2/19/11 31SS+5 days 2/13/2011 2/19/2011
39 Bekesting 5 days Wed 2/16/11 Sun 2/20/11 38SS+3 days 2/16/2011 2/20/2011
40 Setting Angkur 1 day Mon 2/21/11 Mon 2/21/11 39,38 2/21/2011 2/21/2011
41 Pengecoran 1 day Tue 2/22/11 Tue 2/22/11 40 2/22/2011 2/22/2011
42 Masa Pengeringan 5 days Wed 2/23/11 Sun 2/27/11 41 2/23/2011 2/27/2011
43 Urugan Tanah Kembali 2 days Mon 2/28/11 Tue 3/1/11 42SS+5 days 2/28/2011 3/1/2011
44 Ereksi Tower 20 days Sat 2/19/11 Fri 3/11/11
45 Material Angkur & Tower on Site 0 days Sat 2/19/11 Sat 2/19/11 40FF-2 days 2/19/2011
46 Sortir Material di Lokasi 2 days Sun 2/20/11 Mon 2/21/11 45 2/20/2011 2/21/2011
47 Ereksi Tower 9 days Mon 2/28/11 Tue 3/8/11 46,42 2/28/2011 3/8/2011
48 Pengecatan & Grounding Tower 3 days Wed 3/9/11 Fri 3/11/11 47 3/9/2011 3/11/2011
49 Shelter CKD 10 days Wed 3/2/11 Fri 3/11/11
50 Pondasi Shelter 2 days Wed 3/2/11 Thu 3/3/11 43 3/2/2011 3/3/2011
51 Masa Pengeringan 5 days Fri 3/4/11 Tue 3/8/11 50 3/4/2011 3/8/2011
52 Material Shelter on Site oleh DMT 0 days Sun 3/6/11 Sun 3/6/11 51FF-2 days 3/6/2011
53 Installasi Shelter oleh DMT 0 days Sun 3/6/11 Sun 3/6/11 52 3/6/2011
54 Installasi ME 5 days Mon 3/7/11 Fri 3/11/11 53 3/7/2011 3/11/2011
55 PLN (Asumsi Ada Penambahan Jaringan) 39 days Fri 1/28/11 Mon 3/7/11
56 Joint Survey dengan PLN 2 days Fri 1/28/11 Sat 1/29/11 15 1/28/2011 1/29/2011
57 Penerbitan Persetujuan Gambar Instalasi oleh PLN 7 days Sun 1/30/11 Sat 2/5/11 56 1/30/2011 2/5/2011
58 Penerbitan Surat Keterangan OB oleh PLN 14 days Sun 1/30/11 Sat 2/12/11 56 1/30/2011 2/12/2011
59 Persetujuan Instalasi PLN oleh DMT 0 days Sat 2/12/11 Sat 2/12/11 58 2/12/2011
60 Pekerjaan Installasi PLN 21 days Sun 2/13/11 Sat 3/5/11 59 2/13/2011 3/5/2011
61 Penandatangan Surat Hibah dan SPJ BTL oleh DMT 0 days Sat 3/5/11 Sat 3/5/11 60 3/5/2011
62 PLN ON 2 days Sun 3/6/11 Mon 3/7/11 61 3/6/2011 3/7/2011
63 Pagar & Halaman 16 days Wed 3/2/11 Thu 3/17/11
64 Pagar Type A 14 days Wed 3/2/11 Tue 3/15/11 43 3/2/2011 3/15/2011
65 Pagar Type B 14 days Wed 3/2/11 Tue 3/15/11 43 3/2/2011 3/15/2011
66 Paving 6 days Sat 3/12/11 Thu 3/17/11 48 3/12/2011 3/17/2011
67 Serah Terima Pekerjaan 5 days Fri 3/18/11 Tue 3/22/11
68 Proses Pra-ATP 1 day Fri 3/18/11 Fri 3/18/11 62,66 3/18/2011 3/18/2011
69 Penyelesaian Panding Item (Jika Ada) 3 days Sat 3/19/11 Mon 3/21/11 68 3/19/2011 3/21/2011
70 Uji Terima 1 day Tue 3/22/11 Tue 3/22/11 69 3/22/2011 3/22/2011