PROGRESS REPORT - 1

COATING PIPA, TIANG PANCANG & PIPA SUPPORT WALKWAY PIPA SYFON SERTA
REKONDISI SUPPORT & LANTAI BETON PENYANGGA
EDITION 1: 23 MEI 7 JUNI

Prepared for
Prepared by

Issue Date
Edition Number
Revision Number

: PT KRAKATAU DAYA LISTRIK


: PT BUMI MAS JAYA PERKASA
Ruko Barcelona, Jl. Parasel, Palem Raja Raya Selatan No.01, Perumahan
Palem Semi, Karawaci, Tangerang, Indonesia
: 07 JUNI 2016
:1
: 1.0

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

Document Control
Copyright PT Bumi Mas Jaya Perkasa 2016. All rights reserved
Revision History
Date
Revision
07/06/2016

1.0

Author

Details

Veva Santi D ,
Fauzi Hidayat

Document issued, progres report for period 23 Mei


2016 7 Juni 2016

PT.BUMI MAS JAYA PERKASA | Confidential

Page 2 of 8

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

1.0 SCOPE
Dalam Laporan ini, pihak kontraktor PT BUMI MAS JAYA PERKASA melaporkan perkembangan
pekerjaan Coating Pipa, Tiang Pancang, & Pipa Support Walkway Pipa Syfon Serta Rekondisi Support &
Lantai Beton Penyangga dilapangan secara garis besar masih tahap pemasangan scaffolding.
1.1 Objectives
Laporan ini dibuat untuk penjelasan kemajuan progres dan tahapan pekerjaan yang sudah berjalan di
lapangan dari 23 Mei 2016 07 Juni 2016, progres diawal berada lebih atas karena proses mobilisasi
yang cepat sedangkan menuju pertengahan sampai tanggal 7 juni berada di behind schedule dari
planning dikarenakan untuk penggerjaan selimut beton bagian atas belum berjalan akibat masih
difokuskan pada pengerjaan pemasangan scaffolding.
1.2 Deliverables
Dalam laporan ini, pihak PT BUMI MAS JAYA PERKASA melaporkan progress lapangan secara
persentase per item pekerjaan, progress cara S-curve yang membandingkan antara Plan & Actual
berikut dengan penjelasannya,dan melampirkan gambar untuk menjelaskan secara sepesifik dan detail
daerah yang sudah tergarap atau terselesaikan oleh pihak lapangan dari PT BUMI MAS JAYA PERKASA.

PT.BUMI MAS JAYA PERKASA | Confidential

Page 3 of 8

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

2.0 SCONSTRUCTION PROGRESS


Dibawah ini perkembangan pekerjaan secara persentase yang dijabarkan secara peritem
pekerjaan, yang sudah terupdate di tanggal 07 Juni 2016.

NO

URAIAN PEKERJAAN

Rencana
Durasi
(hari)

Planning

Actual

Bobot

Persentase

Bobot

Persentase

PEKERJAAN PERSIAPAN

116

Dokumentasi Perijinan

88

100.00%

0.222

22.22%

Mobilisasi

100.00%

5.000

100.00%

Scaffolding Construction

21

100.00%

1.143

57.14%

II

PEKERJAAN BETON

71

REPAIR CONCRETE (BOTTOM SLAB)

Bobok kedalaman min 100 mm

15

100.00%

0.000

0.00%

Ganti tulangan (M25 Cold Galvanizing)

10

100.00%

0.000

0.00%

Grouting (Semen mortar min K500)

21

30

100.00%

0.000

0.00%

REPAIR CONCRETE (WALL SLAB)

Bobok kedalaman min 100 mm

10

100.00%

0.000

0.00%

Grouting (Semen mortar min K500)

15

25

100.00%

0.000

0.00%

III

APLIKASI FRP

87

BOTTOM & WALL SLAB

Surface Preparation (Hand Tool Cleaning)

100.00%

0.000

0.00%

10

Wrapping FRP Glass Fiber Biaxial (1 layer)

100.00%

0.000

0.00%

TIANG PANCANG & PIPA INTAKE 5 JALUR

11

Surface Preparation (Sand Blasting)

15

100.00%

0.000

0.00%

12

Wrapping FRP + Primer 1208 (2 layer)

45

15

100.00%

0.000

0.00%

13

Coating (Polyurethane) diatas permukaan air 50 micron (tiang


pancang)

100.00%

0.000

0.00%

14

Coating (Polyurethane) Lantai dan selimut beton pipa intake 50 micron

100.00%

0.000

0.00%

IV

PEKERJAAN AKHIR

34

15

Uninstall Access

30

100.00%

0.000

0.00%

(Stagging & Scaffolding)


16

House Keeping

100.00%

0.000

0.00%

17

Final Test & Report

100.00%

0.000

0.00%

TOTAL

PT.BUMI MAS JAYA PERKASA | Confidential

100

6.365

Page 4 of 8

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

Dibawah ini dijelaskan perkembangan proyek dilapangan dengan S Cuve yang membandingkan
antara Plan & Actual.

Dari hasil perhitungan S Curve di atas posisi Actual berada di bawah dari Planing ( Behind

Schedule).
3.0 CONCLUSION AND OUTLOOK
Dari keterangan diatas progres pekerjaan sampai tanggal 07 Juni 2016 diperhitungkan tidak
memberikan progres yang cukup baik, dikarenakan pekerjaan selimut beton bagian atas belum
terlaksana akibat masih focus pada pemasangan scaffolding , untuk menanggapi keterlambatan
progress tersebut, pihak kontraktor sedang mengusahakan mempercepat pengerjaan scaffolding di
lapangan agar bisa mengejar pekerjaan selimut beton dan pekerjaan lainnya.

APPENDIX A: CONSTRUCTION PROGRESS PHOTOS


Untuk melengkapi penjelasan di atas, terlampir foto-foto kegiatan di lapangan dan gambar penjelasan
secara detail daerah yang sudah tergarap. Dari tanggal 23 Mei 2016 07 Juni 2016.

PT.BUMI MAS JAYA PERKASA | Confidential

Page 5 of 8

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

COATING PIPA, TIANG PANCANG


& PIPA SUPPORT WALKWAY PIPA
SYFON
PT. KRAKATAU DAYA LISTRIK
JOB DESCRIPTION:
PEMASANGAN SCAFFOLDING

PT.BUMI MAS JAYA PERKASA | Confidential

Date: 23 Mei 07 Juni 2016


Sheet: 1 of 3

Page 6 of 8

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

COATING PIPA, TIANG PANCANG


& PIPA SUPPORT WALKWAY PIPA
SYFON
PT. KRAKATAU DAYA LISTRIK
JOB DESCRIPTION:
PEMASANGAN SCAFFOLDING

PT.BUMI MAS JAYA PERKASA | Confidential

Date: 23 Mei 07 Juni 2016


Sheet: 2 of 3

Page 7 of 8

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

COATING PIPA, TIANG PANCANG


& PIPA SUPPORT WALKWAY PIPA
SYFON
PT. KRAKATAU DAYA LISTRIK
JOB DESCRIPTION:
PEMASANGAN SCAFFOLDING

PT.BUMI MAS JAYA PERKASA | Confidential

Date: 23 Mei 07 Juni 2016


Sheet: 3 of 3

Page 8 of 8