COATING PIPA, TIANG PANCANG & PIPA SUPPORT WALKWAY PIPA SYFON SERTA
REKONDISI SUPPORT & LANTAI BETON PENYANGGA
EDITION 1: 09 SEPTEMBER 29 SEPTEMBER
Prepared for
Prepared by
Issue Date
Edition Number
Revision Number
Ed 1-Rev 1.0
Document Control
Copyright PT Bumi Mas Jaya Perkasa 2016. All rights reserved
Revision History
Date
Revision Author
29/09/2016
1.0
Veva Santi D ,
Fauzi Hidayat
Details
Document issued, progres report for period 09
September 2016 29 September 2016
Page 2 of 9
Ed 1-Rev 1.0
1.0 SCOPE
Dalam Laporan ini, pihak kontraktor PT BUMI MAS JAYA PERKASA melaporkan perkembangan
pekerjaan Coating Pipa, Tiang Pancang, & Pipa Support Walkway Pipa Syfon Serta Rekondisi Support &
Lantai Beton Penyangga dilapangan secara garis besar sudah tahap pekerjaan wrapping FRP tiang
pancang syfon beserta intakenya yang bagian underwater, bobok concrete bottom slab, penggantian
tulangan slab, dan grouting. Pekerjaan scaffolding masih lanjut karena sistem pemasangannya paralel.
1.1 Objectives
Laporan ini dibuat untuk penjelasan kemajuan progres dan tahapan pekerjaan yang sudah berjalan di
lapangan dari 09 September 2016 29 September 2016, progres berada dibawah kurva rencana
karena proses pekerjaannya terutama grouting yang memiliki bobot cukup besar masih belum selesai
akibat ombak laut yang naik sehingga menyulitkan aplikasi dilapangan sehingga pekerjaan terlambat
dari yang di rencanakan.
1.2 Deliverables
Dalam laporan ini, pihak PT BUMI MAS JAYA PERKASA melaporkan progress lapangan secara
persentase per item pekerjaan, progress cara S-curve yang membandingkan antara Plan & Actual
berikut dengan penjelasannya,dan melampirkan gambar untuk menjelaskan secara sepesifik dan detail
daerah yang sudah tergarap atau terselesaikan oleh pihak lapangan dari PT BUMI MAS JAYA PERKASA.
Page 3 of 9
Ed 1-Rev 1.0
I
1
2
3
II
A
4
5
6
B
7
8
III
C
9
10
URAIAN PEKERJAAN
16
PEKERJAAN PERSIAPAN
Dokumentasi Perijinan
Mobilisasi
Scaffolding Construction
PEKERJAAN BETON
REPAIR CONCRETE (BOTTOM SLAB)
Bobok kedalaman min 100 mm
Ganti tulangan (M25 Cold Galvanizing)
Grouting (Semen mortar min K500)
REPAIR CONCRETE (WALL SLAB)
Bobok kedalaman min 100 mm
Grouting (Semen mortar min K500)
APLIKASI FRP
BOTTOM & WALL SLAB
Surface Preparation (Hand Tool Cleaning)
Wrapping FRP Glass Fiber Biaxial (1 layer)
TIANG PANCANG & PIPA INTAKE 5
JALUR
Surface Preparation (Sand Blasting)
Wrapping FRP + Primer 1208 (2 layer)
Coating (Polyurethane) diatas permukaan air
50 micron (tiang pancang)
Coating (Polyurethane) Lantai dan selimut
beton pipa intake 50 micron
PEKERJAAN AKHIR
Uninstall Access
(Stagging & Scaffolding)
House Keeping
17
D
11
12
13
14
IV
15
TOTAL
Rencana
Durasi (hari)
Actual
Bobot
Persentase
116
88
7
21
71
1.000
5.000
2.000
100.00%
100.00%
100.00%
15
10
21
1.500
2.250
10.969
75.00%
75.00%
36.56%
10
15
87
0.000
0.000
0.00%
0.00%
7
7
0.000
0.000
0.00%
0.00%
15
45
2.000
15.000
100.00%
100.00%
0.000
0.00%
1.000
100.00%
0.000
0.00%
0.000
0.00%
0.000
0.00%
7
6
34
30
40.72
Page 4 of 9
Ed 1-Rev 1.0
Dibawah ini dijelaskan perkembangan proyek dilapangan dengan S Cuve yang membandingkan
antara Plan & Actual.
Rencana
Actual
Dari hasil perhitungan S Curve di atas posisi Actual berada di bawah dari Planing ( Behind
Schedule).
3.0 CONCLUSION AND OUTLOOK
Dari keterangan diatas progres pekerjaan sampai tanggal 29 September 2016 diperhitungkan tidak
memberikan progres yang cukup baik, dikarenakan wrapping FRP, bobok concrete bottom slab,
penggantian tulangan slab dan grouting slab mengalami keterlambatan, untuk menanggapi
keterlambatan
progress
tersebut
pihak
kontraktor
sedang
mengusahakan
mempercepat
pengerjaannya di lapangan dengan cara apabila ombak surut pekerja dikomandokan untuk langsung
mengerjakan pekerjaan yang tertunda dan dikejar progressnya dengan diberikan waktu lembur sampai
hari minggu agar bisa mengejar pekerjaan lainnya.
Page 5 of 9
Ed 1-Rev 1.0
Date: 09 September 22
September 2016
Sheet: 1 of 4
Page 6 of 9
Ed 1-Rev 1.0
Date: 09 September 22
September 2016
Sheet: 2 of 4
Page 7 of 9
Ed 1-Rev 1.0
Date: 09 September 22
September 2016
Sheet: 3 of 4
Page 8 of 9
Ed 1-Rev 1.0
Date: 09 September 22
September 2016
Sheet: 4 of 4
Page 9 of 9