PROGRESS REPORT - 7

COATING PIPA, TIANG PANCANG & PIPA SUPPORT WALKWAY PIPA SYFON SERTA
REKONDISI SUPPORT & LANTAI BETON PENYANGGA
EDITION 1: 09 SEPTEMBER 29 SEPTEMBER

Prepared for
Prepared by

Issue Date
Edition Number
Revision Number

: PT KRAKATAU DAYA LISTRIK


: PT BUMI MAS JAYA PERKASA
Ruko Barcelona, Jl. Parasel, Palem Raja Raya Selatan No.01, Perumahan
Palem Semi, Karawaci, Tangerang, Indonesia
: 29 SEPTEMBER 2016
:1
: 1.0

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

Document Control
Copyright PT Bumi Mas Jaya Perkasa 2016. All rights reserved
Revision History
Date
Revision Author
29/09/2016

1.0

Veva Santi D ,
Fauzi Hidayat

PT.BUMI MAS JAYA PERKASA | Confidential

Details
Document issued, progres report for period 09
September 2016 29 September 2016

Page 2 of 9

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

1.0 SCOPE
Dalam Laporan ini, pihak kontraktor PT BUMI MAS JAYA PERKASA melaporkan perkembangan
pekerjaan Coating Pipa, Tiang Pancang, & Pipa Support Walkway Pipa Syfon Serta Rekondisi Support &
Lantai Beton Penyangga dilapangan secara garis besar sudah tahap pekerjaan wrapping FRP tiang
pancang syfon beserta intakenya yang bagian underwater, bobok concrete bottom slab, penggantian
tulangan slab, dan grouting. Pekerjaan scaffolding masih lanjut karena sistem pemasangannya paralel.
1.1 Objectives
Laporan ini dibuat untuk penjelasan kemajuan progres dan tahapan pekerjaan yang sudah berjalan di
lapangan dari 09 September 2016 29 September 2016, progres berada dibawah kurva rencana
karena proses pekerjaannya terutama grouting yang memiliki bobot cukup besar masih belum selesai
akibat ombak laut yang naik sehingga menyulitkan aplikasi dilapangan sehingga pekerjaan terlambat
dari yang di rencanakan.
1.2 Deliverables
Dalam laporan ini, pihak PT BUMI MAS JAYA PERKASA melaporkan progress lapangan secara
persentase per item pekerjaan, progress cara S-curve yang membandingkan antara Plan & Actual
berikut dengan penjelasannya,dan melampirkan gambar untuk menjelaskan secara sepesifik dan detail
daerah yang sudah tergarap atau terselesaikan oleh pihak lapangan dari PT BUMI MAS JAYA PERKASA.

PT.BUMI MAS JAYA PERKASA | Confidential

Page 3 of 9

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

2.0 SCONSTRUCTION PROGRESS


Dibawah ini perkembangan pekerjaan secara persentase yang dijabarkan secara peritem
pekerjaan, yang sudah terupdate di tanggal 29 September 2016.
NO

I
1
2
3
II
A
4
5
6
B
7
8
III
C
9
10

URAIAN PEKERJAAN

16

PEKERJAAN PERSIAPAN
Dokumentasi Perijinan
Mobilisasi
Scaffolding Construction
PEKERJAAN BETON
REPAIR CONCRETE (BOTTOM SLAB)
Bobok kedalaman min 100 mm
Ganti tulangan (M25 Cold Galvanizing)
Grouting (Semen mortar min K500)
REPAIR CONCRETE (WALL SLAB)
Bobok kedalaman min 100 mm
Grouting (Semen mortar min K500)
APLIKASI FRP
BOTTOM & WALL SLAB
Surface Preparation (Hand Tool Cleaning)
Wrapping FRP Glass Fiber Biaxial (1 layer)
TIANG PANCANG & PIPA INTAKE 5
JALUR
Surface Preparation (Sand Blasting)
Wrapping FRP + Primer 1208 (2 layer)
Coating (Polyurethane) diatas permukaan air
50 micron (tiang pancang)
Coating (Polyurethane) Lantai dan selimut
beton pipa intake 50 micron
PEKERJAAN AKHIR
Uninstall Access
(Stagging & Scaffolding)
House Keeping

17

Final Test & Report

D
11
12
13
14
IV
15

TOTAL

PT.BUMI MAS JAYA PERKASA | Confidential

Rencana
Durasi (hari)

Actual
Bobot

Persentase

116
88
7
21
71

1.000
5.000
2.000

100.00%
100.00%
100.00%

15
10
21

1.500
2.250
10.969

75.00%
75.00%
36.56%

10
15
87

0.000
0.000

0.00%
0.00%

7
7

0.000
0.000

0.00%
0.00%

15
45

2.000
15.000

100.00%
100.00%

0.000

0.00%

1.000

100.00%

0.000

0.00%

0.000

0.00%

0.000

0.00%

7
6
34
30

40.72

Page 4 of 9

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

Dibawah ini dijelaskan perkembangan proyek dilapangan dengan S Cuve yang membandingkan
antara Plan & Actual.
Rencana
Actual

Dari hasil perhitungan S Curve di atas posisi Actual berada di bawah dari Planing ( Behind

Schedule).
3.0 CONCLUSION AND OUTLOOK
Dari keterangan diatas progres pekerjaan sampai tanggal 29 September 2016 diperhitungkan tidak
memberikan progres yang cukup baik, dikarenakan wrapping FRP, bobok concrete bottom slab,
penggantian tulangan slab dan grouting slab mengalami keterlambatan, untuk menanggapi
keterlambatan

progress

tersebut

pihak

kontraktor

sedang

mengusahakan

mempercepat

pengerjaannya di lapangan dengan cara apabila ombak surut pekerja dikomandokan untuk langsung
mengerjakan pekerjaan yang tertunda dan dikejar progressnya dengan diberikan waktu lembur sampai
hari minggu agar bisa mengejar pekerjaan lainnya.

APPENDIX A: CONSTRUCTION PROGRESS PHOTOS


Untuk melengkapi penjelasan di atas, terlampir foto-foto kegiatan di lapangan dan gambar penjelasan
secara detail daerah yang sudah tergarap. Dari tanggal 09 September 2016 29 September 2016.

PT.BUMI MAS JAYA PERKASA | Confidential

Page 5 of 9

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

COATING PIPA, TIANG PANCANG


& PIPA SUPPORT WALKWAY PIPA
SYFON
PT. KRAKATAU DAYA LISTRIK
JOB DESCRIPTION:
Bobok bottom slab, pelapisan tulangan dengan cat anti karat,
penggantian tulangan dan grouting

PT.BUMI MAS JAYA PERKASA | Confidential

Date: 09 September 22
September 2016
Sheet: 1 of 4

Page 6 of 9

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

COATING PIPA, TIANG PANCANG


& PIPA SUPPORT WALKWAY PIPA
SYFON
PT. KRAKATAU DAYA LISTRIK
JOB DESCRIPTION:
Bobok bottom slab, pelapisan tulangan dengan cat anti karat,
penggantian tulangan dan grouting

PT.BUMI MAS JAYA PERKASA | Confidential

Date: 09 September 22
September 2016
Sheet: 2 of 4

Page 7 of 9

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

COATING PIPA, TIANG PANCANG


& PIPA SUPPORT WALKWAY PIPA
SYFON
PT. KRAKATAU DAYA LISTRIK
JOB DESCRIPTION:
Wrapping FRP pipa syfon dan Intake termasuk finish coating
sampling

PT.BUMI MAS JAYA PERKASA | Confidential

Date: 09 September 22
September 2016
Sheet: 3 of 4

Page 8 of 9

Ed 1-Rev 1.0

PROGRESS REPORT: SYFON - KDL

COATING PIPA, TIANG PANCANG


& PIPA SUPPORT WALKWAY PIPA
SYFON
PT. KRAKATAU DAYA LISTRIK
JOB DESCRIPTION:
Wrapping FRP pipa syfon dan Intake termasuk finish coating
sampling

PT.BUMI MAS JAYA PERKASA | Confidential

Date: 09 September 22
September 2016
Sheet: 4 of 4

Page 9 of 9