Anda di halaman 1dari 1

TANDA TERIMA

PEMINJAMAN DOKUMEN

Pembangunan GI 150 kV Pelabuhan Ratu Baru


Kontrak No. 171.PJ/133/UIPJJB/2011

N
Dokumen Keterangan
o
1 Laporan Bulanan 5 (lima) buku
a. November 2012
b. Agustus 2013
c. September 2013
d. September 2015
e. Oktober 2015
2 Rekomendasi BAPP 21,150% 2 (dua) buku
Rekomendasi BAPP 28,208 %
3 Serah Terima Lahan GI 150 kV Pelabuhan Ratu 1 (satu) buku
4 FAT Report 27 (dua puluh tujuh)
a. FO Plesiochoronous Digital Hierarchy (2) bendel
b. Protection and Control Bus Coupler (2)
c. Protection and Control Line 1 (2)
d. Server Panel and SAS (2)
e. Protection and Control Bus Protection (2)
f. Marshalling Kiosk Line 1 (2)
g. Marshalling Kiosk Line 2 (2)
h. Marshalling Kiosk Transformer (2)
i. Marshalling Kiosk Bus Coupler (2)
j. 400/380 VAC Distribution Board EQ3401 (2)
k. 400/380 VAC Distribution Board EQ3402 (2)
l. 48 VDC Distribution Board EQ3421 (2)
m. 110 VDC Distribution Board EQ3411 (2)
n. Daftar Hadir FAT (1)

Jakarta, November 2016

.. ..