BILL OF QUANTITY (BOQ)

REKAPITULASI

PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN


KEGIATAN : PEMBANGUNAN JALAN
PEKERJAAN : PENGAWASAN TEKNIS JALAN WUTUN-NOBO
TAHUN ANGGARAN : 2017

NO URAIAN JUMLAH (Rp)


I BIAYA LANGSUNG PERSONIL 49,712,250.00
A TENAGA AHLI 25,830,875.00
B TENAGA PENUNJANG 12,184,375.00
C TENAGA PENDUKUNG 11,697,000.00
II BIAYA LANGSUNG NON PERSONIL 32,106,000.00
A BIAYA PERJALANAN, UANG HARIAN 24,780,000.00
B SEWA KENDARAAN DAN OPERASIONAL 500,000.00
C BIAYA SEWA KANTOR PROYEK 1,050,000.00
D PERALATAN 1,900,000.00
E BIAYA ATK 2,251,000.00
F BIAYA FASILITAS KANTOR 500,000.00
G BIAYA KOMUNIKASI 250,000.00
H BIAYA PELAPORAN 875,000.00

J JUMLAH I + II 81,818,250.00
K PPN (10% X C) 8,181,825.00
L TOTAL (C + D) 90,000,075.00
M JUMLAH DIBULATKAN 90,000,000.00

Terbilang : SEMBILAN PULUH JUTA RUPIAH

Larantuka, .
CV/PT..

NAMA JELAS
Jabatan
REKAPITULASI

KEGIATAN : PEMBANGUNAN JALAN


PEKERJAAN : PENGAWASAN TEKNIS JALAN WUTUN-NOBO
TAHUN ANGGARAN : 2017

I. BIAYA LANGSUNG PERSONIL


JUMLAH
MAN HARGA
NO POSISI PERSONIL JUMLAH (Rp)
MONTH SATUAN (Rp)
(ORANG)
A. TENAGA AHLI
1 Site Engineer 1.00 7.00 1,879,875.00 13,159,125.00
2 Quality Control 1.00 7.00 1,810,250.00 12,671,750.00

25,830,875.00
B. TENAGA PENUNJANG
3 Pengawas Lapangan 1.00 7.00 1,740,625.00 12,184,375.00

Sub Total 12,184,375.00


C. TENAGA PENDUKUNG
4 Operator/Admin 1.00 7.00 1,671,000.00 11,697,000.00

Sub Total 11,697,000.00


JUMLAH 49,712,250.00
II. BIAYA LANGSUNG NON PERSONIL
A. BIAYA TRANSPORTASI, MOBILISASI DAN DEMOBILISASI
HARGA
NO URAIAN VOLUME SATUAN JUMLAH (Rp)
SATUAN (Rp)
A. BIAYA PERJALANAN, UANG HARIAN
1 Site Engineer
Uang Jalan Kantor-Lokasi Proyek 21.00 OH 60,000.00 1,260,000.00
Uang Harian 21.00 OH 50,000.00 1,050,000.00
2 Quality Control
Uang Jalan Kantor-Lokasi Proyek 14.00 OH 55,000.00 770,000.00
Uang Harian 14.00 OH 50,000.00 700,000.00
3 Pengawas Lapangan
Uang Jalan Kantor-Lokasi Proyek 210.00 OH 50,000.00 10,500,000.00
Uang Harian 210.00 OH 50,000.00 10,500,000.00

JUMLAH 24,780,000.00
B SEWA KENDARAAN DAN OPERASIONAL
1 Sewa Kendaraan Roda 2 1.00 Unit 500,000.00 500,000.00

JUMLAH 500,000.00
C BIAYA SEWA KANTOR PROYEK
1 Sewa Kantor Proyek 7.00 Bulan 150,000.00 1,050,000.00

JUMLAH 1,050,000.00
D PERALATAN
1 Komputer Desk Top 1.00 Unit 500,000.00 500,000.00
2 Laptop 1.00 Unit 600,000.00 600,000.00
3 Printer A4 1.00 Unit 350,000.00 350,000.00
4 Digital Camera 1.00 Unit 200,000.00 200,000.00
5 Meter Roll 1.00 Unit 50,000.00 50,000.00
6 Pengukur Suhu Aspalt 1.00 Unit 200,000.00 200,000.00
JUMLAH 1,900,000.00
E BIAYA ATK
1 Kertas HVS A4 7.00 Rim 55,000.00 385,000.00
2 Bahan Computer dan Printer 1.00 Ls 700,000.00 700,000.00
3 Penggandaan/Foto Copy 1.00 Ls 1,050,000.00 1,050,000.00
4 Alat Tulis 1.00 Ls 116,000.00 116,000.00
JUMLAH 2,251,000.00
E BIAYA FASILITAS KANTOR
1 Meja dan Kursi Kerja 1.00 Set 350,000.00 350,000.00
2 White Board 1.00 Bh 150,000.00 150,000.00

JUMLAH 500,000.00
H BIAYA KOMUNIKASI
1 Biaya Telepon 1.00 Ls 250,000.00 250,000.00

JUMLAH 250,000.00
C. BIAYA PELAPORAN
1 Laporan Mingguan, Bulanan 5.00 Buku 75,000.00 375,000.00
2 Buku Laporan Akhir 5.00 Buku 100,000.00 500,000.00

JUMLAH 875,000.00
RINCIAN BEBAN BIAYA PERSONAL

Gaji Dasar Per Beban Biaya Beban Biaya Tunjangan Total Biaya langsung
Pengalam Sub Jumlah Rp Imbalan jasa
Bulan (GD) Umum Sosial Proyek Per Bulan Personil Rp.
No Nama Posisi an Thn
Min
(GD) (0.5 - 1.3) GD (0.3 - 0.4) GD (0.1 - 0.3) GD (1.2 - 3.1)GD
1 0.5 0.3 (1+2+3) 0.1 x [4] 0,1
1 2 3 4 5 6 7 = 4+5+6

A Tenaga Ahli

1 S1 Teknik Sipil Site Engineer 5 675,000.00 675,000.00 236,250.00 1,586,250.00 158,625.00 135,000.00 1,879,875.00
2 S1 Teknik Sipil Quality Control 5 650,000.00 650,000.00 227,500.00 1,527,500.00 152,750.00 130,000.00 1,810,250.00

B Tenaga Penunjang

1 D3 Sipil/SMK (Bangunan) Pengawas lapangan 4 625,000.00 625,000.00 218,750.00 1,468,750.00 146,875.00 125,000.00 1,740,625.00

C Tenaga Pendukung

1 SMA/Sederajat Operator/Admin 3 600,000.00 600,000.00 210,000.00 1,410,000.00 141,000.00 120,000.00 1,671,000.00