BAB I
PERHITUNGAN PANJANG BENGKOKAN DAN BENTUK TULANGAN
K6-T-01
2.2 Kolom K7
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
a. K7-T-02
Hitungan :
D = db+dp = 72.5+22 ` = 94,5 mm
x = (0,5dp+ db) = (0,5x72.5 + 22) = 58,25 mm
6d = 6x22 = 132 mm
A =D = 94,5 = 74,220 mm
B = tinggi lantai 9+tinggi balok+1/4tinggi lantai 8-selimut beton-x
= 3000+600+750-50-58,25
= 4241,750 mm
Panjang Total = 12d+A+B = 132+74,220+4241,750 = 4447,97 mm = 4,5 m
Banyaknya kebutuhan batang=20, untuk 2 kolom membutuhkan 20x2= 40
batang
a. Tulangan Atas
9B1-7-01
Diketahui :
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) =( 62.5+25) = 56,25 mm
12d = 12x25 = 300 mm
A =D = 87,5 = 68,722 mm
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
B = 12000-12d-A-x
= 12000-300-68,722-56,25
= 11575,028 mm
Panjang Total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang :
1. Untuk As A = 2 batang
2. Untuk As C = 2 batang
Total 4 batang
9B1-A-2
Diketahui :
db = 25 mm
Panjang total = 12000 mm
Banyaknya Kebutuhan Batang :
1. Untuk As A = 2 batang
2. Untuk As C = 2 batang
Total 4 batang
9B1-A-3
Diketahui :
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton (sb) = 50 mm
Panjang total tulangan atas = 24500 mm
Hitungan :
D = db+dp = 62.5+25 = 87,5 mm
x = (0,5dp+ db) = ( 62.5+25) = 56,25 mm
12d = 12x25 = 300 mm
A =D = 87,5 = 68,722 mm
B = 24500 - 2sb - 2x (panjang B tulangan 9B1-A-1) ((panjang
tulangan 9B1-A-2)-40d) +40d
= 24500 100 112,5 11575,028 10000 + 1000
= 3712,472 mm
Panjang Total = 12d+A+B = 300+68,722+3712,472 = 4081,194mm = 4,1 m
Banyaknya Kebutuhan Batang :
1. Untuk As A = 2 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
2. Untuk As C = 2 batang
Total 4 batang
9B1-A-4
Diketahui :
Dipasang untuk tumpuan lapis pertama
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton (sb) = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) = ( 62.5+25) = 56,25 mm
12d = 12x25 = 300 mm
A =D = 87,5 = 68,722 mm
B = ( lebar balok-sb)+( 4000 )+15db
= (250-50)+(1000)+(375)
= 1575 mm
Panjang Total = 12d+A+B = 300+68,722+1575 = 1943,722 mm = 1,9 m
Banyaknya Kebutuhan Batang
1. Untuk As A = 4 batang tumpuan paling kiri dan 4 batang tumpuan paling
kanan
2. Untuk As C = 4 batang tumpuan paling kiri dan 4 batang tumpuan paling
kanan
Total = 16 batang
9B1-A-5
Diketahui :
db = 25 mm
Dipasang untuk lapangan lapisa pertama, tumpuan lapis pertama, tumpuan
lapis kedua
Hitungan :
A= ( 4000)+2(15d) = 2000+2(375) = 2750 mm = 2,8 m
Banyaknya Kebutuhan Batang
1. As A :
- Untuk lapangan lapis pertama = 6 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
Dipasang untuk tumpuan lapis kedua
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton (sb) = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) = ( 62.5+25) = 56,25 mm
12d = 12x25 = 300 mm
A =D = 87,5 = 68,722 mm
B = ( lebar balok-sb-diameter tul)+( 4000 )+15db
= (250-50-25)+(1000)+(375)
= 1550 mm
Panjang Total = 12d+A+B = 300+76,576+1550 = 1926,876 mm =1,9 m
Banyaknya Kebutuhan Batang
1. Untuk As A = 2 batang tumpuan paling kiri dan 2 batang tumpuan paling
kanan
2. Untuk As C = 2 batang tumpuan paling kiri dan 2 batang tumpuan paling
kanan
Total = 8 batang
b. Tulangan Badan
9B1-BD-1
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
db = 16 mm
dp = 2,5db mm = 40 mm
Hitungan :
D = db+dp = 40+16 = 56 mm
x = (0,5dp+ db) = ( 40+16) = 36 mm
12d = 12x16 = 192 mm
A =D = 56 = 43,982 mm
B = 12000-12d-A-x
= 12000-192-43,982-36
= 11728,018 mm
Panjang Total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang = 4 batang untuk As A dan 4 batang untuk As C
Total = 8 batang
9B1-BD-2
Diketahui :
db = 25 mm
Panjang total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang = 4 batang untuk As A dan 4 batang untuk As C
Total = 8 batang
9B1-BD-3
Diketahui :
db = 16 mm
dp = 2,5db mm = 40 mm
Hitungan :
D = db+dp = 40+16 = 56 mm
x = (0,5dp+ db) = ( 40+16) = 36 mm
12d = 12x16 = 192 mm
A =D = 56 = 43,982 mm
B = panjang total-2x-(panjangB 9B1-BD-1)-((A 9B1-BD-2)-40db)+40db
= 24300-72-11728,018-11360+640
= 1779,92 mm
Panjang Total = 12d+A+B = 192+43,982+1779,92 = 2015,902 mm = 2 m
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 62.5+25 = 87,5 mm
x = (0,5dp+ db) = ( 62.5+25) = 56,25 mm
A =D = 87,5 = 68,722 mm
12d = 12x25 = 300 mm
B = 12000-12d-A-x
= 12000-300-68,722 -56,25
= 11575,028 mm
Panjang Total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang : 5 batang untuk As A dan 5 batang untuk As C
Total = 10 batang
9B1-B-2
Diketahui :
db = 25 mm
Panjang total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang : 5 batang untuk As A dan 5 batang untuk As C
Total = 10 batang
9B1-B-3
Diketahui :
db = 25 mm
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
dp = 2,5db mm = 62.5 mm
selimut beton (sb) = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) = ( 62.5+25) = 56,25 mm
A =D = 87,5 = 68,722 mm
12d = 12x25 = 300 mm
B = 24500 - 2sb - 2x (panjang B tulangan 9B1-B-1) ((panjang
tulangan 9B1-B-2)-40d) +40d
= 24500 100 112,5 11575,028 10000 + 1000
= 3712,472 mm
Panjang Total = 12d+A+B = 300+68,722 +3712,472 = 4081,194 mm = 4,1 m
Banyaknya Kebutuhan Batang : 5 batang untuk As A dan 5 batang untuk As C
Total = 10 batang
a. Tulangan Atas
9B2-B-01
Diketahui :
db = 29 mm
dp = 2,5db mm = 72.5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 72.5+29 = 101,5 mm
x = (0,5dp+ db) = ( 72.5+29) = 65,25 mm
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
db = 29 mm
Panjang total = 12000 mm = 12 m
Banyaknya kebutuhan batang = 3
9B2-A-3
Diketahui :
db = 29 mm
dp = 2,5db mm = 72.5 mm
selimut beton (sb) = 50 mm
Hitungan :
A =D = 101,5 = 79,718 mm
D = db+dp = 72.5+29 ` = 101,5 mm
x = (0,5dp+ db) = ( 72.5+29) = 65,25 mm
12d = 12x29 = 348 mm
B = 24500 - 2sb - 2x (panjang B tulangan 9B2-A-1) ((panjang
tulangan 9B2-A-2)-2(40d)) +40d
= 24500 100 130,5 11507,032 9680 + 1000
= 4082,468 mm
Panjang Total = 12d+A+B = 348+79,718 +4082,468 = 4510,186 mm = 4,5 m
Banyaknya kebutuhan batang = 3
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B2-A-4
Diketahui :
Dipasang untuk tumpuan lapis pertama dan tupuan lapis kedua
db = 29 mm
dp = 2,5db mm = 72.5 mm
selimut beton (sb) = 50 mm
Hitungan :
A =D = 101,5 = 79,718 mm
D = db+dp = 72.5+29 ` = 101,5 mm
x = (0,5dp+ db) = ( 72.5+29) = 65,25 mm
12d = 12x29 = 348 mm
B = ( lebar balok-sb)+( 4000 )+15db
= (250-50)+(1000)+(435)
= 1635 mm
Panjang total = 348+79,718+1635 = 2062,718 mm = 2,1 m
Banyaknya kebutuhan batang : 4 batang tumpuan paling kiri dan 4 batang
tumpuan paling kanan
Total = 8 batang
9B1-A-5
Diketahui :
db = 29 mm
dp = 2,5db mm = 72.5 mm
selimut beton (sb) = 50 mm
Hitungan :
A =D = 101,5 = 79,718 mm
D = db+dp = 72.5+29 ` = 101,5 mm
x = (0,5dp+ db) = ( 72.5+29) = 65,25 mm
12d = 12x29 = 348 mm
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
db = 29 mm
A= ( 4000)+2(15d) = 2000+2(435) = 2870 mm = 2,9 m
Banyaknya Kebutuhan Batang
- Untuk lapangan lapis pertama = 2x6 segmen = 12 batang
- Untuk tumpuan lapis pertama = 4x5 = 20 batang
- Untuk tumpuan lapis kedua = 3x5 = 15 batang
Total = 47 batang
b. Tulangan Badan
9B2-BD-1
Diketahui :
db = 29 mm
dp = 2,5db mm = 72,5 mm
Hitungan :
A =D = 101,5 = 79,718 mm
D = db+dp = 72.5+29 ` = 101,5 mm
x = (0,5dp+ db) = ( 72.5+29) = 65,25 mm
12d = 12x29 = 348 mm
B = 12000-12d-A-x
= 12000-348-79,718-65,25
= 11510,032 mm
Panjang Total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang = 6 batang
9B1-BD-2
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
db = 29 mm
Panjang total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang = 6 batang
9B1-BD-3
Diketahui :
db = 29 mm
dp = 2,5db mm = 72,5 mm
Hitungan :
A =D = 101,5 = 79,718 mm
D = db+dp = 72.5+29 ` = 101,5 mm
x = (0,5dp+ db) = ( 72.5+29) = 65,25 mm
12d = 12x29 = 348 mm
B = panjang total-2x-(panjangB 9B2-BD-1)-((A 9B2-BD-2)
2(40db))+40db
= 24300-130,5-11510,032 -9680+1160
= 4139,468 mm
Panjang Total = 12d+A+B = 348+79,718 +4139,468 = 4567,186 mm = 4,7 m
Banyaknya Kebutuhan Batang = 6 batang
c. Tulangan Bawah
9B2-B-01
Diketahui :
db = 29mm
dp = 2,5db mm = 72.5 mm
selimut beton = 50 mm
Hitungan :
A =D = 101,5 = 79,718 mm
D = db+dp = 72.5+29 ` = 101,5 mm
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
db = 29 mm
Panjang total = 12000 mm = 12 m
Banyaknya Kebutuhan Batang = 7 batang
9B2-B-3
Diketahui :
db = 29 mm
dp = 2,5db mm = 72.5 mm
selimut beton (sb) = 50 mm
Hitungan :
A =D = 101,5 = 79,718 mm
D = db+dp = 72.5+29 ` = 101,5 mm
x = (0,5dp+ db) = ( 72.5+29) = 65,25 mm
12d = 12x29 = 348 mm
B = 24500 - 2sb - 2x (panjang B tulangan 9B2-B-1) ((panjang
tulangan 9B2-B-2)-2(40d)) +40d
= 24500 100 130,5 11507,032 9680 + 1160
= 4242,468 mm
Panjang Total = 12d+A+B = 348+79,718 +4242,468 = 4670,186 mm= 4,7 m
Banyaknya Kebutuhan Batang = 7 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
a. Tulangan Atas
9B1-07-01
Diketahui :
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) =( 62.5+25) = 56,25 x 2 = 112.5 mm
12d = 12x25 = 300 x 2 = 600 mm
A =D = 87,5 = 68,722 x 2 = 137.444 mm
B = 5900-A-x
= 5900-137.444-112.5
= 5650.1 mm
Panjang Total = 6500 mm = 6.5 m
Banyaknya Kebutuhan Batang :
Untuk As 7 = 2 batang
Total = 2 x 2 = 4 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-07-02
Diketahui :
db = 25 mm
15 D = 15 x 25 = 375 mm
Panjang total = . 5950 + 375 = 1862.5 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 8 batang
Total = 8x2= 16 batang
9B1-07-03
Diketahui :
db = 25 mm
15 D = 15 x 25 = 375 x 2 = 750 mm
Panjang total = . 5900 + 750 = 3700 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 1 batang
Total 1x2 = 2 batang
b. Tulangan Badan
9B1-07-04 (Tulangan Susut)
Diketahui :
db = 16 mm
Panjang total = 5900 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 4 batang
Total =4x2 = 8 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
c. Tulangan Bawah
9B1-07-05
Diketahui :
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) =( 62.5+25) = 56,25 x 2 = 112.5 mm
12d = 12x25 = 300 x 2 = 600 mm
A =D = 87,5 = 68,722 x 2 = 137.444 mm
B = 5900-A-x
= 5900-137.444-112.5
= 5650.1 mm
Panjang Total = 6500 mm = 6.5 m
Banyaknya Kebutuhan Batang :
Untuk As 7 = 2 batang
Total 2x2 = 4 batang
9B1-07-06
Diketahui :
db = 25 mm
Panjang total = 5900 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 3 batang
Total 3x2= 6 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
a. Tulangan Atas
9B1-08-01
Diketahui :
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) =( 62.5+25) = 56,25 x 2 = 112.5 mm
12d = 12x25 = 300 x 2 = 600 mm
A =D = 87,5 = 68,722 x 2 = 137.444 mm
B = 10800-A-x
= 10800-137.444-112.5
= 10550.056 mm
Panjang Total = 11400 mm = 11.4 m
Banyaknya Kebutuhan Batang :
Untuk As 8= 2 batang
Total =2x5 = 10 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-08-2
Diketahui :
db = 25 mm
15 D = 15 x 25 = 375 mm
Panjang total = . 10850 + 375 = 11275 mm
Banyaknya Kebutuhan Batang :
Untuk As 8 = 6 batang
Total = 6x5= 30 batang
9B1-08-3
Diketahui :
db = 25 mm
15 D = 15 x 25 = 375 x 2 = 750 mm
Panjang total = . 10800 + 750 = 6150 mm
Banyaknya Kebutuhan Batang :
Untuk As 8 = 1 batang
Total =1x5= 5 batang
b. Tulangan Badan
9B1-08-4 (Tulangan Susut)
Diketahui :
db = 16 mm
Panjang total = 10800 mm
Banyaknya Kebutuhan Batang :
Untuk As 8 = 4 batang
Total =4x5 = 20 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
c. Tulangan Bawah
9B1-08-05
Diketahui :
db = 25 mm
dp = 2,5db mm = 62.5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 62.5+25 ` = 87,5 mm
x = (0,5dp+ db) =( 62.5+25) = 56,25 x 2 = 112.5 mm
12d = 12x25 = 300 x 2 = 600 mm
A =D = 87,5 = 68,722 x 2 = 137.444 mm
B = 10800-A-x
= 10800-137.444-112.5
= 10550.056 mm
Panjang Total = 11400 mm = 11.4 m
Banyaknya Kebutuhan Batang :
Untuk As 8 = 2 batang
Total =2x5 = 10 batang
9B1-08-06
Diketahui :
db = 25 mm
Panjang total = 10800 mm
Banyaknya Kebutuhan Batang :
Untuk As 8 = 3 batang
Total =3x5= 15 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
d. Tulangan Atas
9B2-07-01
Diketahui :
db = 29 mm
dp = 2,5db mm = 72,5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 72,5+29 ` = 101.5 mm
x = (0,5dp+ db) =( 72,5+29) = 65,25 x 2 = 130,5 mm
12d = 12x29 = 348 x 2 = 696 mm
A =D = 101.5 = 79,718 x 2 = 159,436 mm
B = 4800-A-x
= 4800-159,436-130,5
= 4510,064 mm
Panjang Total = 5496 mm = 5,496 m
Banyaknya Kebutuhan Batang :
Untuk As 7 = 2 batang
Total =2x2= 4 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B2-07-2
Diketahui :
db = 29 mm
15 D = 15 x 29 = 435 mm
Panjang total = . 4850+ 435 = 1647.5 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 10 batang
Total =10x2 = 10 batang
9B2-07-3
Diketahui :
db = 29 mm
15 D = 15 x 29 = 435 x 2 = 870 mm
Panjang total = . 4800 + 870 = 3270 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 3 batang
Total =3x2= 6 batang
d. Tulangan Badan
9B2-07-4 (Tulangan Susut)
Diketahui :
db = 29 mm
Panjang total = 4800 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 6 batang
Total =6x2= 12 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
e. Tulangan Bawah
9B2-07-05
Diketahui :
db = 29 mm
dp = 2,5db mm = 72,5 mm
selimut beton = 50 mm
Hitungan :
D = db+dp = 72,5+29 ` = 101.5 mm
x = (0,5dp+ db) =( 72,5+29) = 65,25 x 2 = 130,5 mm
12d = 12x29 = 348 x 2 = 696 mm
A =D = 101.5 = 79,718 x 2 = 159,436 mm
B = 4800-A-x
= 4800-159,436-130,5
= 4510,064 mm
Panjang Total = 5496 mm = 5,496 m
Banyaknya Kebutuhan Batang :
Untuk As 7 = 2 batang
Total =2x2 = 4 batang
9B2-07-06
Diketahui :
db = 25 mm
Panjang total = 4800 mm
Banyaknya Kebutuhan Batang :
Untuk As 7 = 5 batang
Total =5x2 = 10 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
D10-200
dp = 10
L = 6000 mm
1
= 1500 mm
4
Hitungan :
D = dp+db = 10+10 = 20
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4x10 = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
c = 1500-x = 1500-15 = 1485 mm
Panjang Total = a+b+c = 1548,56 mm = 1,6 m
Bayak Kebutuhan Tulangan = ((8000x3)/200)+1= 41 batang
Kode 3
Diketahui :
D10-200
dp = 10
L = 6000 mm dan 4900 mm
L yang dipakai = ( 6000)+( 49000) = 2725
Hitungan
D = dp+db = 10+10 = 20
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4(10) = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
c = 2725-2x = 2725-15 = 2710 mm
Panjang Total = 2a+2b+c = 2837,12 mm = 2,8 m
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
D10-200
Dp = 10
L = 4900 mm
1
= 1225 mm
4
Hitungan :
D = dp+db = 10+10 = 20
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4x10 = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
c = 1225-x = 1225-15 = 1210 mm
Panjang Total = a+b+c = 1273,56 mm = 1,3 m
Bayak Kebutuhan Tulangan = ((8000x3)/200)+1= 41 batang
Tulangan Atas Lapis Kedua
Kode 2
Diketahui :
D10-150
Dp = 10
L = 4000 mm
1
4 = 1000 mm
Hitungan :
D = dp+db = 10+10 = 20
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4x10 = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
D10-150
dp = 10
L = 8000
1
= 2000 mm
4
Hitungan
D = dp+db = 10+10 = 20
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4(10) = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
c = 2000-2x = 2000-15 = 1970 mm
Panjang Total = 2a+2b+c = 2097,12 mm = 2,1 m
Bayak Kebutuhan Tulangan = ((6000+4900)/150)+1= 74 batang
Total yang dibutuhkan = 74x 5 baris = 370 batang
3.2 Tulangan Bawah
Tulangan Bawah Lapis Pertama
Kode 9
Diketahui :
D10-200
dp = 10
L = 10900
Selimut beton = 30 mm
Hitungan
L = 10900- (2 x 30)= 10840 mm
D = dp+db = 10+10 = 20
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4(10) = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
c = 10840-2x = 10840-30 = 10810 mm
Panjang Total = 2a+2b+c = 10937,12 mm = 11 m
Bayak Kebutuhan Tulangan = (24000/200)+1= 121 batang
Kode 6 dan 7
Diketahui :
D10-150
dp = 10
Hitungan
D = dp+db = 10+10 = 20
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4(10) = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
c = 12000-2a-2b = 11872,88 mm
Panjang Total = 12 m
Bayak Kebutuhan Tulangan = ((6000+4900)/150)+1= 74 batang
Total = 74 x 2 = 148 batang
Kode 8
Diketahui :
D10-150
dp = 10
Ltotal = 24000- (2 x 30)= 23940 mm
Hitungan
D = dp+db = 10+10 = 20
1 1
x = 2dp+db= 210+10= 15 mm
a = 4D = 4(10) = 40 mm
3 3
b = 8 D = 8 20= 23,56 mm
c = 23940-c kode 6- c kode 7 2x = 164,24 mm
Panjang Total = 2a+2b+c = 291,36 mm = 0,3 m
Bayak Kebutuhan Tulangan = ((6000+4900)/150)+1= 74 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
Diketahui :
D13-100 untuk tumpuan dan D13-300 untuk lapangan
db = 13 mm
dp = 29 mm
selimut beton = 50 mm
Banyak kolom K6 dilantai 9 = 4 kolom
tinggi lantai 9 = 3000 mm ; tinggi lantai 8 = 750 mm
Hitungan :
D = db+dp = 13+29 = 42 mm
x = (0,5dp+ db) = (0,5x29 + 13) = 27,5 mm
6d = 6(13) = 78 mm
A = 600-100 = 500 mm
A = A-2X = 5002(27.5) = 445 mm
3 342
B = = = 49,480 mm
8 8
C = D = 42 = 32,987 mm
Panjang Total = 2(6d)+2B+4A+3C
= 2(78)+2(49,480)+4(445)+3(32,987)
= 2133,921 mm
= 2,1 m
Kebutuhan batang untuk satu kolom :
1. Tumpuan : 3((750/100)+1) = 24 batang
2. Lapangan : 1500/300 = 5 btg
Kebutuhan batang untuk empat kolom :
1. Tumpuan : 24x4 = 96 btg
2. Lapangan : 5x4 = 20 btg
Total = 116 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
K7-S-02
Diketahui :
D13-100 untuk tumpuan dan D13-300 untuk lapangan
db = 13 mm
dp = 22 mm
selimut beton = 50 mm
Banyak kolom K7 dilantai 9 = 2 kolom
tinggi lantai 9 = 3000 mm ; tinggi lantai 8 = 750 mm
Hitungan :
D = db+dp = 13+22 = 35 mm
x = (0,5dp+ db) = (0,5x22 + 13) = 24 mm
6d = 6(13) = 78 mm
A = 500-100 = 400 mm
A = A-2X= 4002(24) = 352 mm
3 335
B = = = 41,233 mm
8 8
C = D = 35 = 27,489 mm
Panjang Total = 2(6d)+2B+4A+3C
= 2(78)+2(41,233)+4(352)+3(27,489)
= 1728,933 mm
= 1,7 m
Kebutuhan batang untuk satu kolom :
3. Tumpuan : 3((750/100)+1) = 24 batang
4. Lapangan : 1500/300 = 5 btg
Kebutuhan batang untuk dua kolom :
3. Tumpuan : 24x2 = 28 btg
4. Lapangan : 5x2 = 10 btg
Total = 38 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
b. Sengkang Balok
Balok 9B1
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-S-1
Diketahui :
db = 13 mm
dp = 25 mm
D = 13+25= 38 mm
x = (0,5 dp+ db) = (0,5x25 + 13) = 25,5 mm
selimut beton = 50 mm
Hitungan :
A = 500-100 = 400 mm
A = A-2x = 400-(2x25,5) = 349 mm
D = 600-100 = 500 mm
D = D-2x = 500-(2x25,5) = 449 mm
6db = 6db = 6x13 = 78 mm
C = D = (38) = 29,845 mm
B = 3/8D =3/8(38) = 44,768 mm
Panjang total = 2(6db)+2A + 2D + 3C+2B
= 2(78)+2(349)+2(449)+3(29,845)+2(44,768)
= 1931,071 mm
=2m
9B1-S-2
Diketahui :
db = 13 mm
dp = 25 mm
D = 13+25= 38 mm
x = (0,5 dp+ db) = (0,5x25 + 13) = 25,5 mm
Hitungan :
A = 3(75) = 225 mm
D = 600-100 = 500 mm
D = D-2x = 500-(2x25,5) = 449 mm
6db = 6db = 6x13 = 78 mm
C = D = (38) = 29,845 mm
B = 3/8D =3/8(38) = 44,768 mm
Panjang total = 2(6db)+2A+2D+3C+2B
= 2(78)+2(225)+2(449)+3(29,845)+2(44,768)
= 1683,071 mm = 1,7 m
9B1-S-3
Diketahui :
db = 13 mm
dp = 25 mm
D = 13+25= 38 mm
x = (0,5 dp+ db) = (0,5x25 + 13) = 25,5 mm
Hitungan :
A = 500-100= 400 mm
A = A-2x = 400-(2x25,5) = 349 mm
6db = 6db = 6x13 = 78 mm
C = D = (38) = 29,845 mm
Panjang total = 2(6db)+A+2C = 2(78)+349+2(29,845)
= 564,63 mm = 0,56 m
Balok 9B2
9B2-S-1
Diketahui :
db = 16 mm
dp = 29 mm
D = 16+29= 45 mm
x = (0,5 dp+ db) = (0,5x29 + 16) = 30,5 mm
selimut beton = 50 mm
Hitungan :
A = 800-100 = 700 mm
A = A-2x = 700-(2x30,5) = 639 mm
D = 600-100 = 500 mm
D = D-2x = 500-(2x30,5) = 439 mm
6db = 6db = 6x16 = 96 mm
C = D = (45) = 35,34 mm
B = 3/8D =3/8(45) = 53,01 mm
Panjang total = 2(6db)+2A + 2D + 3C+2B
= 2(96)+2(639)+2(439)+3(35,34)+2(53,01)
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
= 2560,04 mm
= 2,56004 m
9B2-S-2
Diketahui :
db = 16 mm
dp = 29 mm
D = 16+29= 45 mm
x = (0,5 dp+ db) = (0,5x29 + 16) = 30,5 mm
selimut beton = 50 mm
Hitungan :
A = 111+2x = 111+2(30,5) = 172 mm
D = 600-100 = 500 mm
D = D-2x = 500-(2x30,5) = 439 mm
6db = 6db = 6x16 = 96 mm
C = D = (45) = 35,34 mm
B = 3/8D =3/8(45) = 53,01 mm
Panjang total = 2(6db)+2A + 2D + 3C+2B
= 2(96)+2(172)+2(439)+3(35,34)+2(53,01)
= 1626,04 mm
=1,62604 m
9B2-S-3
Diketahui :
db = 16 mm
dp = 29 mm
D = 16+29= 45 mm
x = (0,5 dp+ db) = (0,5x29 + 16) = 30,5 mm
selimut beton = 50 mm
Hitungan :
A = 333+2x = 333+2(30,5) = 394 mm
D = 600-100 = 500 mm
D = D-2x = 500-(2x30,5) = 439 mm
6db = 6db = 6x16 = 96 mm
C = D = (45) = 35,34 mm
B = 3/8D =3/8(45) = 53,01 mm
Panjang total = 2(6db)+2A + 2D + 3C+2B
= 2(96)+2(394)+2(439)+3(35,34)+2(53,01)
= 2070,04 mm
=2,07004 m
9B2-S-4
Diketahui :
db = 16 mm
dp = 29 mm
D = 16+29= 45 mm
x = (0,5 dp+ db) = (0,5x29 + 16) = 30,5 mm
selimut beton = 50 mm
Hitungan :
A = 800-100= 700 mm
A = A-2x = 700-(2x30,5) = 639 mm
6db = 6db = 6x16 = 96 mm
C = D = (45) = 35,343 mm
Panjang total = 2(6db)+A+2C = 2(96)+700+2(35,343)
= 1598,69 mm = 1,5987 m
BAB II
PERHITUNGAN KEBUTUHAN BATANG TULANGAN
Diketahui 1 lente = 12 m
2.1 Kolom
K6-T-01
Diameter 29
Panjang perbatang = 4,7 m
Total kebutuhan : 96 batang
Banyaknya kebutuhan perlente = 12 m / 4,7 m = 2,5 batang
1 lente bisa untuk 2 batang, maka untuk 96 batang = 96/2 = 48 lente.
Sisa = 12m-(2x4,7) = 2,6 m setiap lente
K7-T-02
Diameter 22
Panjang perbatang = 4,5 m
Total kebutuhan : 40 batang
Banyaknya kebutuhan = 12 m / 4,5 m = 2,7 btg
1 lente bisa untuk 2 batang, maka untuk 40 batang = 40/2 = 20 lente
Sisa = 12m-(2x4,5) = 3 m setiap lente
2.2 Balok
9B1-A-01
Diameter 25
Panjang perbatang = 12 m
Total kebutuhan : 4 batang
Banyaknya kebutuhan perlente = 12 m/12 m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 12 batang = 12/1 = 12 lente
Sisa = 0 setiap lente
9B1-A-02
Diameter 25
Panjang perbatang = 12 m
Total kebutuhan : 4 batang
Banyaknya kebutuhan perlente = 12 m/12 m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 12 batang = 12/1 = 12 lente
Sisa = 0 setiap lente
9B1-A-03
Diameter 25
Panjang perbatang = 4,1 m
Total kebutuhan : 4 batang
Banyaknya kebutuhan perlente = 12 m/4,1 m = 2,9 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-BD-3
Diameter 16
Panjang perbatang = 2 m
Total kebutuhan : 8 batang
Banyaknya kebutuhan perlente = 12 m/2 m = 6 batang
1 lente bisa untuk 6 batang, maka untuk 8 batang = 8/6 = 1,3 lente = 2 lente
Sisa = 12m-(2x2) = 8 m untuk satu lente
9B1-B-1
Diameter 25
Panjang perbatang = 12 m
Total kebutuhan : 10 batang
Banyaknya kebutuhan perlente = 12 m/12 m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 10 batang = 10/1 = 10 lente
Sisa = 0
9B1-B-2
Diameter 25
Panjang perbatang = 12 m
Total kebutuhan : 10 batang
Banyaknya kebutuhan perlente = 12 m/12 m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 10 batang = 10/1 = 10 lente
Sisa = 0
9B1-B-3
Diameter 25
Panjang perbatang = 4,1 m
Total kebutuhan : 10 batang
Banyaknya kebutuhan perlente = 12 m/4,1m = 2,9 batang
1 lente bisa untuk 2 batang, maka untuk 10 batang = 10/2 = 5 lente
Sisa = 12m-(2x4,1) = 3,8 m untuk satu lente
9B2-B-01
Diameter 29
Panjang perbatang = 12 m
Total kebutuhan : 3 batang
Banyaknya kebutuhan perlente = 12 m/12m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 3 batang = 3/1 = 3 lente
Sisa = 0
9B2-A-2
Diameter 29
Panjang perbatang = 12 m
Total kebutuhan : 3 batang
Banyaknya kebutuhan perlente = 12 m/12m = 1 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-BD-2
Diameter 29
Panjang perbatang = 12 m
Total kebutuhan : 6 batang
Banyaknya kebutuhan perlente = 12 m/12m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 6 batang = 6/1 = 6 lente
Sisa = 0
9B1-BD-3
Diameter 29
Panjang perbatang = 4,7 m
Total kebutuhan : 6 batang
Banyaknya kebutuhan perlente = 12 m/4,7m = 2,6 batang
1 lente bisa untuk 2 batang, maka untuk 6 batang = 6/2 = 3 lente
Sisa = 12m-(2x4,7) = 2,6 m untuk satu lente
9B2-B-01
Diameter 29
Panjang perbatang = 12 m
Total kebutuhan : 7 batang
Banyaknya kebutuhan perlente = 12 m/12m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 7 batang = 7/1 = 7 lente
Sisa = 0
9B2-B-2
Diameter 29
Panjang perbatang = 12 m
Total kebutuhan : 7 batang
Banyaknya kebutuhan perlente = 12 m/12m = 1 batang
1 lente bisa untuk 1 batang, maka untuk 7 batang = 7/1 = 7 lente
Sisa = 0
9B2-B-3
Diameter 29
Panjang perbatang = 4,7 m
Total kebutuhan : 7 batang
Banyaknya kebutuhan perlente = 12 m/4,7m = 2,6 batang
1 lente bisa untuk 2 batang, maka untuk 7 batang = 7/2 = 3,5 lente
Sisa = 12m-(2x4,7) = 2,6 m untuk masing masing 3 lente
Sisa = 12m-(1x4,7) = 7,3 m untuk satu lente
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-07-01
Diameter 25
Panjang perbatang = 6,5 m
Total kebutuhan : 4 batang
Banyaknya kebutuhan perlente = 12 m/6,5 m = 1,85 batang
1 lente bisa untuk 1 batang, maka untuk 4 batang = 4/1 = 4 lente
Sisa = 12m-(1x6,5) = 5,5 m untuk masing masing 4 lente
9B1-07-02
Diameter 25
Panjang perbatang = 1,863 m
Total kebutuhan : 16 batang
Banyaknya kebutuhan perlente = 12 m/1,863 m = 6,44 batang
1 lente bisa untuk 6 batang, maka untuk 16 batang = 16/6 = 2,67 lente = 3 lente
Sisa = 12m-(6x1,863) = 0,82 m untuk masing masing 2 lente
Sisa = 12m-(4x1,863) = 4,54 m untuk satu lente
9B1-07-03
Diameter 25
Panjang perbatang = 3,7 m
Total kebutuhan : 2 batang
Banyaknya kebutuhan perlente = 12 m/3,7 m = 3,24 batang
1 lente bisa untuk 3 batang, maka untuk 2 batang = 2/3 = 0,667 lente = 1 lente
Sisa = 12m-(2x3,7) = 4,6 m untuk satu lente
9B1-07-04
Diameter 16
Panjang perbatang = 5,9 m
Total kebutuhan : 8 batang
Banyaknya kebutuhan perlente = 12 m/5,9 m = 2,03 batang
1 lente bisa untuk 2 batang, maka untuk 8 batang = 8/2 = 4 lente
Sisa = 12m-(2x5,9) = 0,2 m untuk masing masing 4 lente
9B1-07-05
Diameter 25
Panjang perbatang = 6,5 m
Total kebutuhan : 4 batang
Banyaknya kebutuhan perlente = 12 m/6,5 m = 1,85 batang
1 lente bisa untuk 1 batang, maka untuk 4 batang = 4/1 = 4 lente
Sisa = 12m-(1x6,5) 5,5 m untuk masing masing 4 lente
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-07-06
Diameter 25
Panjang perbatang = 5,9 m
Total kebutuhan : 6 batang
Banyaknya kebutuhan perlente = 12 m/5,9 m = 2,03 batang
1 lente bisa untuk 2 batang, maka untuk 6 batang = 6/2 = 3 lente
Sisa = 12m-(2x5,9) = 0,2 m untuk masing masing 3 lente
9B1-08-01
Diameter 25
Panjang perbatang = 11,4 m
Total kebutuhan : 10 batang
Banyaknya kebutuhan perlente = 12 m/11,4 m = 1,05 batang
1 lente bisa untuk 1 batang, maka untuk 10 batang = 10/1 = 10 lente
Sisa = 12m-(1x11,4) = 0,6 m untuk masing masing 10 lente
9B1-08-02
Diameter 25
Panjang perbatang = 11,28 m
Total kebutuhan : 30 batang
Banyaknya kebutuhan perlente = 12 m/11,28 m = 1,06 batang
1 lente bisa untuk 1 batang, maka untuk 30 batang = 30/1 = 30 lente
Sisa = 12m-(1x11,28) = 0,72 m untuk masing masing 30 lente
9B1-08-03
Diameter 25
Panjang perbatang = 6,15 m
Total kebutuhan : 5 batang
Banyaknya kebutuhan perlente = 12 m/6,15 m = 1,95 batang
1 lente bisa untuk 1 batang, maka untuk 5 batang = 5/1 = 5 lente
Sisa = 12m-(1x6,15) = 5,85 m untuk masing masing 5 lente
9B1-08-04
Diameter 16
Panjang perbatang = 10,8 m
Total kebutuhan : 20 batang
Banyaknya kebutuhan perlente = 12 m/10,8 m = 1,1 batang
1 lente bisa untuk 1 batang, maka untuk 20 batang = 20/1 = 20 lente
Sisa = 12m-(1x10,8) = 1,2 m untuk masing masing 20 lente
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-08-05
Diameter 25
Panjang perbatang = 11,4 m
Total kebutuhan : 10 batang
Banyaknya kebutuhan perlente = 12 m/11,4 m = 1,05 batang
1 lente bisa untuk 1 batang, maka untuk 10 batang = 10/1 = 10 lente
Sisa = 12m-(1x11,4) = 0,6 m untuk masing masing 10 lente
9B1-08-06
Diameter 25
Panjang perbatang = 10,8 m
Total kebutuhan : 15 batang
Banyaknya kebutuhan perlente = 12 m/10,8 m = 1,1 batang
1 lente bisa untuk 1 batang, maka untuk 15 batang = 15/1 = 15 lente
Sisa = 12m-(1x10,8) = 1,2 m untuk masing masing 15 lente
9B2-07-01
Diameter 29
Panjang perbatang = 5,5 m
Total kebutuhan : 4 batang
Banyaknya kebutuhan perlente = 12 m/5,5 m = 2,18 batang
1 lente bisa untuk 2 batang, maka untuk 4 batang = 4/2 = 2 lente
Sisa = 12m-(2x5,5) = 1 m untuk masing masing 2 lente
9B2-07-02
Diameter 29
Panjang perbatang = 1,65 m
Total kebutuhan : 10 batang
Banyaknya kebutuhan perlente = 12 m/1,65 m = 7,27 batang
1 lente bisa untuk 7 batang, maka untuk 10 batang = 10/7 = 1.43 lente = 2 lente
Sisa = 12m-(7x1,65) = 0,45 m untuk 1 lente
Sisa = 12m-(3x1,65) = 7,05 m untuk 1 lente berikutnya
9B2-07-03
Diameter 29
Panjang perbatang = 3,27 m
Total kebutuhan : 6 batang
Banyaknya kebutuhan perlente = 12 m/3,27 m = 3,67 batang
1 lente bisa untuk 3 batang, maka untuk 6 batang = 6/3 = 2 lente
Sisa = 12m-(3x3,27) = 2,19 m untuk 2 lente
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B2-07-04
Diameter 29
Panjang perbatang = 4,8 m
Total kebutuhan : 12 batang
Banyaknya kebutuhan perlente = 12 m/4,8 m = 2,5 batang
1 lente bisa untuk 2 batang, maka untuk 12 batang = 12/2 = 6 lente
Sisa = 12m-(2x4,8) = 2,4 m untuk masing-masing 6 lente
9B2-07-05
Diameter 29
Panjang perbatang = 5,5 m
Total kebutuhan : 4 batang
Banyaknya kebutuhan perlente = 12 m/5,5 m = 2,18 batang
1 lente bisa untuk 2 batang, maka untuk 4 batang = 4/2 = 2 lente
Sisa = 12m-(2x5,5) = 1 m untuk masing-masing 2 lente
9B2-07-06
Diameter 25
Panjang perbatang = 4,8 m
Total kebutuhan : 10 batang
Banyaknya kebutuhan perlente = 12 m/4,8 m = 2,5 batang
1 lente bisa untuk 2 batang, maka untuk 10 batang = 10/2 = 5 lente
Sisa = 12m-(2x4,8) = 2,4 m untuk masing-masing 5 lente
Diameter 10
Panjang perbatang = 0,3 m
Total kebutuhan : 74 batang
Banyaknya kebutuhan perlente = 12 m/0,3 m = 40 batang
1 lente bisa untuk 40 batang, maka untuk 74 batang = 74/40 = 1,85 lente = 2 lente
Sisa = 12m-(37x0,3) = 0,9 m untuk masing masing satu lente
2.4 Sengkang
Sengkang Kolom
K6-S-01
Diameter 13-100
Panjang perbatang = 2,1 m
Total kebutuhan : 116 batang
Banyaknya kebutuhan perlente = 12 m/2,1 m = 5,71 batang
1 lente bisa untuk 5 batang, maka untuk 116 batang = 116/5 = 23,2 lente = 24 lente
Sisa = 12m-(5x2,1) = 1,5 m untuk 23 lente
Sisa = 12m-(1x2,1)= 9,9 m untuk satu lente
K6-S-02
Diameter 13-100
Panjang perbatang = 1,7 m
Total kebutuhan : 38 batang
Banyaknya kebutuhan perlente = 12 m/1,7 m = 7,06 batang
1 lente bisa untuk 7 batang, maka untuk 38 batang = 38/7 = 5,43 lente = 6 lente
Sisa = 12m-(7x1,7) = 0,1 m untuk 5 lente
Sisa = 12m-(3x1,7) = 6,9 m untuk satu lente
Sengkang Balok
9B1-S-1
Diameter 13-100
Panjang perbatang = 2 m
Total kebutuhan : 1080 batang
Banyaknya kebutuhan perlente = 12 m/2m = 6 batang
1 lente bisa untuk 6 batang, maka untuk 1080 batang = 1080/6 = 180 lente
Sisa = 12m-(6x2) = 0 m untuk 180 lente
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-S-2
Diameter 13-100
Panjang perbatang = 1,7 m
Total kebutuhan : 1080 batang
Banyaknya kebutuhan perlente = 12 m/1,7m = 7,06 batang
1 lente bisa untuk 7 batang, maka untuk 1080 batang = 1080/7 = 154,3lente =155 lente
Sisa = 12m-(7x1,7) = 0.1 m untuk 154 lente
Sisa = 12m-(2x1,7) = 8.6 m untuk satu lente
9B1-S-3
Diameter 13-100
Panjang perbatang = 0,56 m
Total kebutuhan : 510 batang
Banyaknya kebutuhan perlente = 12 m/0,56 m = 21,43 batang
1 lente bisa untuk 21 batang, maka untuk 510 batang =510/21= 24,3 lente =25 lente
Sisa = 12m-(21x0,56) = 0,24 m untuk 24 lente
Sisa = 12m-(6x0,56) = 8,64 m untuk satu lente
9B2-S-1
Diameter 16-125
Panjang perbatang = 2,6 m
Total kebutuhan : 255 batang
Banyaknya kebutuhan perlente = 12 m/2,6 m = 4,62 batang
1 lente bisa untuk 4 batang, maka untuk 255 batang =255/4= 63,75 lente = 64 lente
Sisa = 12m-(4x2,6) = 1,6 m untuk 63 lente
Sisa = 12m-(3x2,6) = 4,2 m untuk satu lente
9B2-S-2
Diameter 16-125
Panjang perbatang = 1,63 m
Total kebutuhan : 255 batang
Banyaknya kebutuhan perlente = 12 m/1,63 m = 7,36 batang
1 lente bisa untuk 7 batang, maka untuk 255 batang =255/7= 36,43 lente = 37 lente
Sisa = 12m-(7x1,63) = 0,59 m untuk 36 lente
Sisa = 12m-(3x1,63) = 7,11 m untuk satu lente
9B2-S-3
Diameter 16-125
Panjang perbatang = 2,1 m
Total kebutuhan : 255 batang
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B2-S-4
Diameter 16-125
Panjang perbatang = 1,6 m
Total kebutuhan : 102 batang
Banyaknya kebutuhan perlente = 12 m/1,6 m = 7,5 batang
1 lente bisa untuk 7 batang, maka untuk 102 batang =102/7 = 14,57 lente = 15 lente
Sisa = 12m-(7x1,6) = 0,8 m untuk 14 lente
Sisa = 12m-(4x1,6) = 5,6 m untuk satu lente
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
BAB III
PERHITUNGAN SISA TULANGAN
K6-S- 0,1 5
02 38 1,7 6 7,4
6,9 1
9B1-S-
1080 2 180 0 0 0
1
9B2-S- 16 0,59 36
9B2-S-1
2 255 1,63 37 5,2 1 23,15
7,11 1
9B2-S-
255 2,1 51 1,5 51 76,5
3
4
5,6 1
9B1-
08-04 20 10,8 20 1,2 20 24
9B1-
07-04 8 5,9 4 0,2 4 0,96
9B1-
BD-1 8 12 8 0 0 0
9B1-
BD-2 8 12 8 0 0 0
9B1-
BD-3 8 2 2 8 1 8
K6-T-
02 22 40 2,8 20 3 20 60
9B1-
9B1-07-02
07-01 4 6,5 4 5,5 4 7,6 2 14,4
25 Dikurangi 1
9B1- lente karena
0,82 2
07-02 16 1,9 3 1,64 mendapat
tambahan dari
9B1-07-01
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-
07-03 2 3,7 1 4,6 1 4,6
9B1-
07-05 4 6,5 4 5,5 4 22
9B1-
07-06 6 5,9 4 0,2 3 0,6
9B1-
08-01 10 11,4 10 0,6 10 6
9B1-
08-02 30 11,28 30 0,72 30 21,6
9B1-
08-03 5 6,15 5 5,85 5 29,25
9B1-
08-05 10 11,4 10 0,6 10 6
9B1-
08-06 15 10,8 15 1,2 15 18
9B1-B- 10 12 10 0 0 0
1
9B1-B- 10 12 10 0 0 0
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B1-A-
01 4 12 12 0 0 0
9B1-A-
02 4 12 12 0 0 0
9B1-A-
03 4 4,1 2 3,8 2 7,6
9B1-A- 0,6 2
04 16 1,9 3 5,6
4,4 1
9B1-A-
05 32 2,8 8 0,8 8 6,4
9B1-A- 0,6 1
06 8 1,9 2 8,8
8,2 1
9B2-
29 4 5,5 2 1 2 2
07-01
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B2- 0,45 1
9B2-07-01
07-02 10 1,65 2 5,5 1 2,5
7,05 1
9B2-
07-03 6 3,27 2 2,19 2 4,38
9B2-
07-04 12 4,8 6 2,4 6 14,4
9B2-
4 5,5 2 1 2 2
07-05
9B2-
07-06 10 4,8 5 2,4 5 12
9B2-
BD-1 6 12 6 0 0 0
9B2-
BD-2 6 12 6 0 0 0
9B2-
BD-3 6 4,7 3 2,6 1 2,6
9B2-B-
01 7 12 7 0 0 0
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B2-B-
02 7 12 7 0 0 0
9B2-B- 2,6 3
9B2-07-01
03 7 4,7 4 5,5 1 9,6
7,3 1
Hanya membeli 1
lente karena
mendapat
9B2-
4 5,5 2 1 2 6,5 tambahan dari
07-01
9B2-07-02, 9B2-
B-03, dan 9B2-A-
4
0,45 1 Tidak membeli
tulangan karena
9B2- mendapat
29
07-02 10 1,7 2 tambahan dari
7,05 1
9B2-07-03, 9B2-
07-04, dan 9B2-
07-06
9B2- 9B2-
07-03 6 3,3 2 2,19 2 07-02 1,7 2 0,98
9B2- 9B2-
07-04 12 4,8 6 2,4 6 07-02 1,7 6 4,2
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
9B2-
4 5,5 2 1 2 2
07-05
9B2- 9B2-
07-06 10 4,8 5 2,4 5 07-02 1,7 5 3,5
9B2-
BD-1 6 12 6 0 0 0
9B2-
BD-2 6 12 6 0 0 0
Dikurangi 1 lente
9B2- karena mendapat
BD-3 6 4,7 3 2,6 1 0 tambahan dari
9B2-B-03
Dan 9B2-A-3
9B2-B-
01 7 12 7 0 0 0
9B2-B-
02 7 12 7 0 0 0
01
9B2-B-
02 3 12 3 0 0 0
9B2-A- 3 1 9B2-
3 3 4,5 2 BD-3 4,7 1 5,8
7,5 1
9B2-A- 1,5 1 9B2-
4 8 5,7 2 07-01 5,5 1 2,2
5,7 1
9B2-A-
6 2 6 0 0 0
5
9B2-A- 0,4 11
47 2,9 12 7,7
6 3,3 1
K6-T- 96 4,7 48 2,6 48
124,8
01
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
BAB IV
KESIMPULAN
1. Diameter 10
Kebutuhan = 382 lente = 4584 m
Sisa = 198,5 m
198,5
100% = 4,3% < 10%
4584
2. Diameter 13
Kebutuhan = 390 lente = 4680 m
Sisa = 90,2 m
90,2
100% = 1,9 % < 10%
4680
3. Diameter 16
Kebutuhan = 208 lente = 2496 m
Sisa = 247,61 m
2508
100% = 9,9% < 10%
259,61
4. Diameter 22
Kebutuhan = 20 lente = 240 m
Sisa = 60 m
60
100% = 25% < 10%
240
Diameter ini tidak ekonomis dikarenakan sisa dari batang tersebut tidak dapat dipakai
untuk bentuk lain.
5. Diameter 25
Kebutuhan = 149 lente = 1788 m
Sisa = 156,29 m
156,29
100% = 8,7 % < 10%
1788
6. Diameter 29
Kebutuhan = 179 lente = 2148 m
Sisa = 217,56 m
217,56
100% = 10,1% < 10%
2148
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
2 10 41 2,8 114,8
3 10 41 1,3 53,3
6 10 121 11 1331
7 10 148 12 1776
8 10 74 0.3 22,2
10 13 38 1,7 64,6
11 13 1080 2 2160
14 16 255 2 510
18 22 40 4,3 172
19 24 96 4,2 403,2
20 25 4 12 48
21 25 4 12 48
22 25 4 4,1 16,4
23 25 16 1,9 30,4
24 25 32 2,8 89,6
25 25 8 1,6 12,8
26 16 8 12 96
27 16 8 12 96
28 16 8 1,8 14,4
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
29 25 10 12 120
30 25 10 12 120
31 25 10 4,1 41
32 29 3 12 36
33 29 3 12 36
34 29 3 4,5 13,5
35 29 8 2,1 16,8
36 29 6 2 12
37 29 47 2,9 136,3
38 29 12 6 72
39 29 12 6 72
40 29 6 4,7 28,2
41 29 12 7 84
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
42 29 12 7 84
43 29 7 4,7 32,9
44 25 4 6,5 26
45 25 16 1,9 30,4
46 25 2 3,7 7,4
47 25 8 5,9 47,2
48 25 4 6,5 26
49 25 6 5,9 35,4
50 25 10 11,4 114
51 25 30 11,2 336
52 25 5 6,1 30,5
53 16 20 10,8 216
54 25 10 11,4 114
55 25 15 10,8 162
56 29 4 5,5 22
57 29 10 1,6 16
58 29 6 3,3 19,8
LAPORAN LABORATORIUM KONSTRUKSI BETON
JURUSAN TEKNIK SIPIL
POLITEKNIK NEGERI BANDUNG
Jl. Gegerkalong Hilir Ds. Ciwaruga Kotak Pos 6468 BDCD Tlp. (022) 2013789, Ext.266 Bandung
59 29 12 4,8 57,6
60 29 4 5,5 22
61 25 10 4,8 48