12 Bambu dia. 6-8 cm/ 6 m' Rp. 9,347.83 5,000.00 5,750.00 btg
16 Batu tempel kapur tekstur tidak rata Rp. 1,565.22 1,575.00 1,800.00 bh
17 Batu tempel palimanan 10 x 20 Rp. 782.61 1,100.00 1,275.00 bh
48 Closet jongkok porselen merk INA / KIA Rp. 86,086.96 95,000.00 109,250.00 bh
49 Closet duduk ( mono block ) porselen merk INA Rp. 717,391.30 850,000.00 977,500.00 bh
50 Closet duduk ( siram) porselen merk INA Rp. 334,782.61 375,000.00 431,250.00 bh
96 Kayu dolken dia 8 -10/4 m' Rp. 31,695.65 37,500.00 43,125.00 btg
97 Kayu dolken dia 12 -15/4 m' Rp. 44,543.48 40,000.00 46,000.00 btg
117 List kayu B.3 (lebar sisi 3 cm) Rp. 2,239.13 3,000.00 3,450.00 m'
118 List kayu B.4 (lebar sisi 4 cm) Rp. 2,456.52 3,250.00 3,725.00 m'
119 List keliling gypsum lebar 8 cm Rp. 4,108.70 4,500.00 5,175.00 m'
120 List keliling gypsum lebar 10 cm Rp. 5,413.04 6,000.00 6,900.00 m'
121 List keliling gypsum lebar 12 cm Rp. 6,456.52 6,500.00 7,475.00 m'
141 Pipa PVC 2" S-12,5 ( 8 - 10 bar ) Rp. 5,347.83 6,000.00 6,900.00 m1
142 Pipa PVC 3" S-12,5 ( 8 - 10 bar ) Rp. 9,086.96 9,000.00 10,350.00 m1
143 Pipa PVC 2" ( kelas rumah tangga ) Rp. 64,347.83 64,000.00 73,600.00 btng
144 Pipa PVC 3" ( kelas rumah tangga ) Rp. 84,152.17 84,000.00 96,600.00 btng
145 Pipa reducer PVC 3" - 4" Rp. 3,956.52 4,000.00 4,600.00 bh
155 Reng kayu borneo uk. 2/3 cm Rp. 4,195.65 7,000.00 8,050.00 bt
161 Seng gelombang 3" - 6" BJLS 30 Rp. 47,434.78 47,500.00 54,625.00 lbr
162 Sirlak Rp. 15,826.09 16,000.00 18,400.00 kg
186 Kusen Aluminium 3'' warna natural Rp. 45,000.00 51,750.00 m'
187 Kusen Aluminium 3'' warna coklat dop Rp. 50,000.00 57,500.00 m'
188 Kusen Aluminium 3'' warna coklat kilap Rp. 90,000.00 103,500.00 m'
189 Kusen Aluminium 4'' warna natural Rp. 70,000.00 80,500.00 m'
190 Kusen Aluminium 4'' warna coklat dop Rp. 80,000.00 92,000.00 m'
191 Kusen Aluminium 4'' warna coklat kilap Rp. 120,000.00 138,000.00 m'
194 Daun pintu aluminium lengkap warna coklat kilap Rp. 1,200,000.00 1,380,000.00 bh
KEPALA DINAS CIPTA KARYA DAN TATA RUANG KEPALA SEKSI BANGUNAN GEDUNG
KABUPATEN CIREBON DINAS CIPTA KARYA DAN TATA RUANG
KABUPATEN CIREBON
HARGA
JUMLAH
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp Rp
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Direksikeet dan Los Bahan SNI.100.12 m2 707,800.00 -
2 Bouwplank dan Propil SNI.100.05 m2 94,800.00 -
3 Steiger/alat-alat bantu dari bambu SNI.000.04 m2 44,700.00 -
4 Papan nama proyek SNI.100.03 bh 330,400.00 -
-
II PEKERJAAN BONGKARAN
1 Membongkar atap genteng/asbes SNI.990.07 m2 1,800.00 -
2 Membongkar genteng bubung - Ls - -
3 Membongkar rangka atap SNI.990.09 m2 5,600.00 -
4 Membongkar rangka kuda-kuda SNI.990.12 m3 67,200.00 -
5 Membongkar Plafond SNI.990.09 m2 5,600.00 -
6 Membongkar papan listplank - Ls - -
7 Mengupas plesteran lama SNI.990.06 m2 2,800.00 -
8 Membongkar dinding tembok SNI.990.04 m2 11,200.00 -
9 Membongkar kusen,pintu dan jendela - Ls - -
10 Membongkar lantai tegel/floor SNI.990.05 m2 6,000.00 -
11 Membongkar talang - Ls - -
-
IV PEKERJAAN PONDASI
1 Urugan pasir di bawah pondasi SNI.200.11 m3 227,200.00 -
2 Pasangan batu kosong SNI.250.14 m3 396,300.00 -
3 Pasangan batu belah ad. 1PC : 5PS SNI.250.07 m3 723,600.00 -
-
V PEKERJAAN BETON/PEMBESIAN
1 Pembesian untuk sloop,kolom &ringbalk SNI.300.32 kg 17,000.00 -
2 Bekisting untuk sloop,kolom &ringbalk SNI.300.36 m2 237,000.00 -
3 Bekisting untuk kolom struktur SNI.300.37 m2 462,600.00 -
4 Adukan beton untuk sloop,kolom dan
ringbalk ad. 1 PC : 2PS : 3Krl SNI.300.19 m3 812,500.00 -
-
-
VII PEKERJAAN KUSEN,PINTU DAN JENDELA
1 Kusen, pintu, jendela dari kayu meranti/lanan/ SNI.955.31 m3 9,930,000.00 -
kruing/balau/kamper SNI.955.30 m3 10,667,100.00 -
SNI.955.29 m3 11,649,900.00 -
SNI.955.28 m3 14,655,000.00 -
SNI.955.27 m3 12,900,000.00 -
1 2 3 4 5 6
2 Rangka pintu dan jendela dari kayu meranti/ SNI.960.41 m2 527,600.00 -
lanan/kruing/balau/kamper SNI.960.40 m2 549,100.00 -
SNI.960.39 m2 577,700.00 -
SNI.960.38 m2 665,400.00 -
SNI.960.37 m2 614,200.00 -
3 Triplek untuk melapis daun pintu 3 mm - lb 52,000.00 -
4 Triplek untuk melapis daun pintu 4 mm - lb 55,000.00 -
5 Teakwood untuk melapis daun pintu 4 mm - lb 80,000.00 -
6 Sketsel triplek rangkap rangka kayu kruing SNI.453.42 m2 345,300.00 -
7 Sketsel GRC rangkap rangka kayu meranti SNI.453.44 m2 218,900.00 -
8 Jalusi dari kayu meranti/kruing/kamper tebal 1,5 cm SNI.970.37 m2 240,600.00 -
SNI.970.35 m2 269,200.00 -
SNI.970.33 m2 290,100.00 -
9 Ram kawat harmonika untuk bovenlight SNI.900.13 m2 54,700.00 -
10 Kaca Polos tebal 3 mm SNI.850.16 m2 94,600.00 -
11 Kaca Polos tebal 5 mm SNI.850.17 m2 109,100.00 -
12 Kaca nako tebal 5 mm berikut teralis SNI.900.17 dn 38,000.00 -
-
IX PEKERJAAN LANTAI
1 Urugan pasir di bawah lantai SNI.200.11 m3 227,200.00 -
2 Lantai tegel abu-abu kepala basah 20 x 20 cm SNI.650.03 m2 112,400.00 -
3 Lantai tegel wafel SNI.650.04 m2 112,400.00 -
4 Lantai beton tumbuk tebal 5 cm ad. 1PC:3PS:6Krl SNI.300.08 m2 32,025.00 -
5 Pasang lantai keramik uk. 30 x 30 cm SNI.650.05 m2 104,400.00 -
6 Pasang lantai keramik uk. 40 x 40 cm SNI.650.20 m2 113,900.00
7 Pasang lantai keramik uk. 30 x 30 cm (menggunakan SNI.650.05.rob m2 108,900.00 -
zat addictive berikut pengecoran)
1 2 3 4 5 6
8 Pasang lantai keramik uk. 20 x 20 cm SNI.650.06 m2 183,300.00 -
9 Pasang lantai keramik uk. 10 x 20 cm SNI.650.07 m2 183,300.00 -
10 Pasang lantai mozaik uk.30 x 30 cm SNI.650.14 m2 119,353.00 -
11 Pasang lantai mozaik uk.20 x 20 cm SNI.650.15 m2 187,700.00 -
12 Pasang rabat keliling SNI.300.08 m2 32,025.00 -
13 Pembuatan Saluran gravel 1/2 dia 20 cm SNI.GRAVEL m' 161,400.00 -
14 Pasang paving block setara K.125 SNI. 999.01 m2 122,900.00 -
-
XI PEKERJAAN MENGECAT
1 Mengecat kayu kusen, pintu, jendela dan listplank SNI.950.07 m2 35,400.00 -
berikut plamir
2 Mengecat kayu lama SNI.950.08 m2 31,700.00 -
3 Mengecat tembok baru dan langit-langit dengan cat SNI.950.15 m2 21,600.00 -
tembok berikut plamir
4 Mengecat tembok lama dan langit-langit dengan cat SNI.950.17 m2 15,600.00 -
tembok berikut plamir
5 Mengeter kayu kuda-kuda & rangka atap SNI. 985.36 m2 14,200.00 -
6 Mengosok/dempul kayu yang akan diplistur SNI.950.06 m2 9,500.00 -
7 Mengerjalan plisturan sirlak SNI.985.34 m2 55,200.00 -
-
R E K A P I T U LA S I
I PEKERJAAN PERSIAPAN Rp -
II PEKERJAAN BONGKARAN Rp -
III PEKERJAAN GALIAN/URUGAN Rp -
IV PEKERJAAN PONDASI Rp -
V PEKERJAAN BETON/PEMBESIAN Rp -
VI PEKERJAAN PASANGAN DINDING BATA Rp -
VII PEKERJAAN KUSEN,PINTU DAN JENDELA Rp -
VIII PEKERJAAN KUDA-KUDA / ATAP Rp -
IX PEKERJAAN LANTAI Rp -
1 2 3 4 5 6
X PEKERJAAN BESI / LAIN-LAIN Rp -
XI PEKERJAAN MENGECAT Rp -
JUMLAH -
PPN 10 % Rp -
JUMLAH TOTAL Rp -
DIBULATKAN Rp -
TERBILANG : ( .. )
SUMBER, 2016
KEPALA SEKSI PERUMAHAN DAN PERMUKIMAN DINAS KEPALA SEKSI BANGUNAN GEDUNG
CIPTA KARYA DAN TATA RUANG KABUPATEN CIREBON DINAS CIPTA KARYA DAN TATA RUANG KABUPATEN
CIREBON
H. ABDUL KARIM, ST
NIP. 19620609 199101 1 001 YEDI ADHI PRIATNA, BAE.S.Sos
NIP. 19660815 199803 1 004
HARGA SATUAN
NO BAHAN
(Rp)
A. BAHAN PEKERJAAN BANGUNAN
1 Alumunium foil Rp. 30,000.00 m2
2 Alumunium pelapis pintu KM (tebal 0,4 cm) Rp. 70,000.00 lbr
3 Asbes gelombang 1500 x 1050 x 4 mm Rp. 42,500.00 lbr
4 Asbes gelombang 1800 x 920 x 4 mm Rp. 32,000.00 lbr
5 Asbes gelombang 2100 x 1050 x 4 mm Rp. 57,000.00 lbr
6 Asbes gelombang 2400 x 1050 x 4 mm Rp. 65,000.00 lbr
7 Asbes gelombang 2700 x 1050 x 4 mm Rp. 75,000.00 lbr
8 Asbes gelombang 3000 x 1050 x 4 mm Rp. 85,000.00 lbr
9 Atras (tanah urug) Rp. 125,000.00 m3
10 Bak mandi keramik volume 0.3 m3 Rp. 185,000.00 bh
11 Bak mandi fiber 120 L Rp. 220,000.00 bh
12 Bambu dia. 6-8 cm/ 6 m' Rp. 17,000.00 btg
13 Bata merah Rp. 800.00 bh
14 Bata berongga Rp. 2,400.00 bh
15 Batu apung Rp. 4,300.00 kg
16 Batu belah 10/15 cm Rp. 175,000.00 m3
17 Batu pecah 5/7 cm Rp. 175,000.00 m3
18 Batu tempel kapur tekstur tidak rata Rp. 2,050.00 bh
19 Batu tempel 10 x 20 Rp. 1,550.00 bh
20 Baut 3/4" Rp. 6,700.00 bh
21 Baut 5/8" Rp. 6,700.00 bh
22 Baut 1/2" Rp. 6,000.00 bh
23 Baut 1/2", panjang 30 cm Rp. 8,550.00 bh
24 Baut lawa-lawa Rp. 13,000.00 kg
25 Beading penurunan (PC) gypsum Rp. 10,000.00 m'
26 Beading horison gypsum Rp. 10,000.00 m'
27 Besi beton Rp. 13,000.00 kg
28 Besi strip Rp. 13,750.00 kg
29 Besi WF Rp. 13,750.00 kg
30 Besi galvanis dia. 0,5" Rp. 25,000.00 m'
31 Besi galvanis dia. 1" Rp. 27,000.00 m'
32 Besi galvanis dia. 1,5" Rp. 45,000.00 m'
33 Besi galvanis dia. 2" Rp. 57,000.00 m'
34 Besi galvanis dia. 2,5" Rp. 80,500.00 m'
35 Besi galvanis dia. 3" Rp. 84,000.00 m'
36 Besi stainless dia. 0,5" Rp. 38,000.00 m'
37 Besi stainless dia. 1" Rp. 60,000.00 m'
38 Besi stainless dia. 1,5" Rp. 75,000.00 m'
39 Besi stainless dia. 2" Rp. 80,000.00 m'
40 Besi stainless dia. 2,5" Rp. 125,000.00 m'
41 Besi stainless dia. 3" Rp. 152,000.00 m'
42 Besi biasa dia. 2" Rp. 250,000.00 btg
43 Besi biasa dia. 3" Rp. 310,000.00 btg
44 Cat dasar / menie Rp. 25,000.00 kg
45 Cat genteng Rp. 50,000.00 kg
46 Cat penutup kayu Rp. 49,000.00 kg
47 Cat penutup tembok Rp. 25,000.00 kg
48 Cat penutup besi Rp. 52,000.00 kg
49 Cat zincromate Rp. 90,000.00 kg
50 Closet jongkok porselen Rp. 140,000.00 bh
51 Closet duduk ( mono block ) porselen Rp. 1,237,000.00 bh
52 Closet duduk ( siram) porselen Rp. 545,000.00 bh
53 Dempul kayu Rp. 18,500.00 kg
54 Dinding keramik uk. 10 x 20 cm Rp. 1,000.00 bh
55 Dinding keramik uk. 20 x 20 cm Rp. 2,000.00 bh
56 Dinding keramik uk. 20 x 25 cm Rp. 2,200.00 bh
57 Dinding keramik uk. 30 x 30 cm Rp. 4,500.00 bh
58 Digital printing Rp. 25,000.00 m'
59 Dop besi dia 3" Rp. 60,000.00 bh
60 Engsel jendela Rp. 12,000.00 set
61 Elastomer 30 x 30 x 5 Rp. 632,500.00 bh
62 Engsel meubeler Rp. 3,800.00 bh
63 Engsel pintu Rp. 19,000.00 set
64 Eternit tebal 4 mm uk. 1 m x 1 m Rp. 6,900.00 lbr
65 Eternit tebal 4 mm uk. 1 m x 0.5 m Rp. 3,450.00 lbr
66 Flincote Rp. 22,000.00 ltr
67 Genteng glazuur turbo Rp. 3,500.00 bh
68 Genteng nok/bubung diglazuur turbo Rp. 4,000.00 bh
69 Genteng nok/bubung press mesin Rp. 2,500.00 bh
70 Genteng nok/bubung press tangan Rp. 2,000.00 bh
71 Genteng nok/ bubung morando diglazuur Rp. 4,500.00 bh
72 Genteng nok/ bubung morando Rp. 4,000.00 bh
73 Genteng press tangan diglazuur Rp. 2,500.00 bh
74 Genteng morando diglazuur Rp. 3,500.00 bh
75 Genteng morando Rp. 3,500.00 bh
76 Genteng press mesin Rp. 1,900.00 bh
77 Genteng press tangan Rp. 1,400.00 bh
78 Genteng Type Viktoria Rp. 9,000.00 bh
79 Genteng nok/bubung type Viktoria Rp. 12,500.00 bh
80 Genteng nok/bubung ujung type Viktoria Rp. 20,000.00 bh
81 Genteng nok/bubung ujung pertigaan type Viktoria Rp. 25,000.00 bh
82 Genteng beton Rp. 5,000.00 bh
83 Glass Block Rp. 17,500.00 bh
84 Gorong buis beton diameter 100 cm Rp. 150,000.00 bh
85 Gorong buis beton diameter 80 cm Rp. 130,000.00 bh
86 Gorong buis beton diameter 60 cm Rp. 140,000.00 bh
87 Gorong buis beton diameter 40 cm Rp. 100,000.00 bh
88 Gorong buis beton diameter 30 cm Rp. 80,000.00 bh
89 Gorong buis beton diameter 20 cm Rp. 60,000.00 bh
90 Gravel 60 cm Rp. 75,000.00 bh
91 Gravel 40 cm Rp. 45,000.00 bh
92 Gravel 20 cm Rp. 35,000.00 bh
93 Grendel pintu / jendela Rp. 5,500.00 bh
94 Gypsum board Rp. 52,500.00 lbr
95 GRC tebal 4 mm Rp. 52,500.00 lbr
96 Hampelas Rp. 3,000.00 lbr
97 Kaca nako tebal 5 mm berikut teralis Rp. 11,400.00 bh
98 Kaca polos tebal 3 mm Rp. 63,250.00 m2
99 Kaca polos tebal 5 mm Rp. 75,000.00 m2
100 Kait angin Rp. 7,500.00 bh
101 Kapur sirih Rp. 2,000.00 kg
102 Kawat beton Rp. 20,000.00 kg
103 Kawat duri Rp. 14,700.00 kg
104 Kayu bakar Rp. 150,000.00 m3
105 Kayu balau *) Rp. 9,500,000.00 m3
106 Kayu borneo Rp. 5,000,000.00 m3
107 Kayu meranti Rp. 6,000,000.00 m3
108 Kayu dolken dia 8 -10/4 m' Rp. 60,000.00 btg
109 Kayu dolken dia 12 -15/4 m' Rp. 68,000.00 btg
110 Kayu hutan Rp. 3,500,000.00 m3
111 Kayu kamper *) Rp. 8,200,000.00 m3
112 Kayu kaso 5/7 meranti Rp. 79,000.00 btng
113 Kayu kruing Rp. 7,274,000.00 m3
114 Kayu lanan Rp. 6,546,000.00 m3
115 Kayu jati Jabar Rp. 8,200,000.00 m3
116 Kerikil Rp. 65,000.00 m3
117 Kunci gembok Rp. 20,000.00 bh
118 Kunci pintu ukuran besar Rp. 125,000.00 bh
119 Langko-langko kuda-kuda *) Rp. 18,000.00 bh
120 Lantai granit 40 x 40 cm B Rp. 43,500.00 bh
121 Lantai granit 40 x 40 cm A Rp. 42,000.00 bh
122 Lantai granit 60 x 60 cm polos Rp. 84,600.00 bh
123 Lantai granit 60 x 60 cm corak Rp. 57,600.00 bh
124 Lantai keramik uk 10 x 20 cm Rp. 1,000.00 bh
125 Lantai keramik uk 20 x 20 cm Rp. 2,000.00 bh
126 Lantai keramik uk 30 x 30 cm Rp. 3,150.00 bh
127 Lantai keramik uk 40 x 40 cm (putih polos) Rp. 7,200.00 bh
128 Lantai terakota 20 x 5 cm Rp. 4,400.00 bh
129 Lem kayu Rp. 30,000.00 ltr
130 Zat addictive Rp. 15,000.00 kg
131 List kayu B.3 (lebar sisi 3 cm) Rp. 4,400.00 m'
132 List kayu B.4 (lebar sisi 4 cm) Rp. 4,800.00 m'
133 List keliling gypsum lebar 7-8 cm Rp. 14,000.00 m'
134 List keliling gypsum lebar 10 cm Rp. 16,000.00 m'
135 List keliling gypsum lebar 12 cm Rp. 18,000.00 m'
136 List drop Rp. 8,900.00 m'
137 Melamin / folywood Rp. 88,500.00 lbr
138 Mozaik uk 20 x 20 cm Rp. 1,900.00 bh
139 Multiplex tebal 15 mm Rp. 275,000.00 m2
140 Nok steel gelombang 1050 x 5 mm Rp. 29,000.00 m1
141 Nok steel gelombang 920 x 5 mm Rp. 22,500.00 m1
142 Nok/bubung genteng beton Rp. 6,000.00 bh
143 Paku biasa 1/2" - 1" Rp. 18,500.00 kg
144 Paku biasa 2" - 5" Rp. 16,000.00 kg
145 Paku pancing 60 x 230 Rp. 825.00 bh
146 Paku sekrup 3" - 5" Rp. 400.00 bh
147 Paku ulir Rp. 150.00 bh
148 Pasir beton Rp. 179,000.00 m3
149 Pasir pasang Rp. 162,000.00 m3
150 Pasir urug Rp. 150,000.00 m3
151 Paving block hexagon natural setara K.225 (uk. 17 x 17 x 6 cm) Rp. 1,650.00 bh
152 Paving block hexagon motif setara K.225 (uk. 17 x 17 x 6 cm) Rp. 1,800.00 bh
153 Paving block hexagon warna setara K.225 (uk. 17 x 17 x 6 cm) Rp. 2,000.00 bh
154 Paving block hexagon natural setara K.225 (uk. 20 x 18 x 7 cm) Rp. 2,450.00 bh
155 Paving block hexagon motif setara K.225 (uk. 20 x 18 x 7 cm) Rp. 2,650.00 bh
156 Paving block hexagon warna setara K.225 (uk. 20 x 18 x 7 cm) Rp. 2,850.00 bh
157 Paving block bolder natural setara K.225 (uk. 20 x 20 x 7 cm) Rp. 3,000.00 bh
158 Paving block bolder warna setara K.225 (uk. 20 x 20 x 7 cm) Rp. 3,200.00 bh
159 Paving block bata natural setara K.225 (uk. 10 x 20 x 7 cm) Rp. 1,400.00 bh
160 Paving block bata warna setara K.225 (uk. 10 x 20 x 7 cm) Rp. 1,500.00 bh
161 Pelumas bekisting Rp. 10,000.00 ltr
162 Plamir kayu / kualitas 1 Rp. 20,000.00 kg
163 Plamir tembok Rp. 23,000.00 kg
164 Plat baja tebal 5 mm - 20 mm Rp. 13,000.00 kg
165 Polycarbonate Rp. 115,000.00 m2
166 Portland cemen (PC) Rp. 70,000.00 zak
167 Rubber joint 25 x 10 x 5 Rp. 235,000.00 bh
168 Reng kayu borneo uk. 2/3 cm Rp. 54,000.00 bt
169 Roster / batu kerawang Rp. 4,000.00 bh
170 Ram kawat harmonika Rp. 25,000.00 m2
171 Semen Portland Rp. 1,400.00 kg
172 Semen warna Rp. 6,000.00 kg
173 Seng BJLS 30 Rp. 38,000.00 lbr
174 Seng gelombang 3" - 6" BJLS 30 Rp. 51,000.00 lbr
175 Sirlak Rp. 19,500.00 kg
176 Sirtu Rp. 145,000.00 m3
177 Spirtus Rp. 9,000.00 ltr
178 Split ( batu pecah mesin ) 2/3 Rp. 200,000.00 m3
179 Solar Rp. 5,950.00 ltr
180 Tali ijuk Rp. 9,000.00 kg
181 Teakwood 4 mm (1200 x 2400) Rp. 80,000.00 lbr
182 Teakwood 4 mm (900 x 2400) Rp. 65,000.00 lbr
183 Ter kayu Rp. 14,500.00 kg
185 Tiner/Minyak cat Rp. 11,500.00 ltr
186 Triplek 3 mm Rp. 52,000.00 lbr
187 Triplek 4 mm Rp. 55,000.00 lbr
188 Triplek 6 mm Rp. 83,000.00 lbr
189 Triplek 9 mm Rp. 102,500.00 lbr
190 Ubin abu-abu kepala basah 20 x 20 cm Rp. 2,000.00 bh
191 Ubin abu-abu kepala basah 30 x 30 cm Rp. 2,500.00 bh
192 Ubin wafel ukuran 20 x 20 cm Rp. 2,000.00 bh
193 Ubin warna 20 x 20 cm Rp. 2,300.00 bh
194 Ubin warna 30 x 30 cm Rp. 2,900.00 bh
195 Woodplank corak 4 m Rp. 60,000.00 bh
196 Woodplank polos 2 m Rp. 32,500.00 bh
197 Wasthafel Rp. 686,000.00 bh
198 Plester Mutiara Rp. 8,000.00 kg
199 TG 302 Rp. 43,600.00 ltr
200 Skim Coat Rp. 4,400.00 kg
201 zat addictive Just Do It Rp. 4,500.00 kg
202 zat addictive FS Nat Rp. 15,850.00 kg
203 Kusen Aluminium 3'' warna natural Rp. 60,000.00 m'
204 Kusen Aluminium 3'' warna coklat dop Rp. 65,000.00 m'
205 Kusen Aluminium 3'' warna coklat kilap Rp. 75,000.00 m'
206 Kusen Aluminium 4'' warna natural Rp. 65,000.00 m'
207 Kusen Aluminium 4'' warna coklat dop Rp. 75,000.00 m'
208 Kusen Aluminium 4'' warna coklat kilap Rp. 85,000.00 m'
209 Daun jendela aluminium lengkap warna natural/coklat dop Rp. 361,750.00 bh
210 Daun jendela aluminium lengkap warna coklat kilap Rp. 400,000.00 bh
211 Door closer Rp. 165,300.00 bh
212 Daun pintu aluminium lengkap warna natural/coklat dop Rp. 945,000.00 bh
213 Daun pintu aluminium lengkap warna coklat kilap Rp. 1,300,000.00 bh
214 Zincalume Rp. 75,000.00 m2
215 plywood Rp. 92,250.00 lbr
216 Holo 4/4 meni Rp. 12,100.00 btg
217 Holo 2/4 meni Rp. 11,000.00 btg
218 Kawat Bwg 12 Rp. 10,000.00 kg
219 Paku screw 2.5 cm Rp. 50.00 bh
220 Adhesive Rp. 6,000.00 kg
221 Kain kasa Rp. 400.00 m'
222 Paku beton Rp. 175.00 bh
223 Profil U 75 53 mm Zinc Alumunium G. 550 Rp. 18,450.00 m'
224 Profil U 60 53 mm Zinc Alumunium G. 550 Rp. 14,000.00 m'
225 Profil U 75 83 mm Zinc Alumunium G. 550 Rp. 22,300.00 m'
226 Reng U 39 0.43 mm Zinc Alumunium G. 550 Rp. 9,050.00 m'
227 Plat Tumpu Rp. 7,975.00 bh
228 Plat Diafragma 0.5 mm Rp. 1,500.00 bh
229 Dynabolt Rp. 950.00 bh
230 Baut Kuda - Kuda Rp. 250.00 bh
231 Baut Reng Rp. 150.00 bh
232 Profil 45 X 27 B50 Rp. 15,490.00 m'
233 Profil 65 X 26 C08 Rp. 22,260.00 m'
234 Profil 75 X 40 W08 Rp. 24,020.00 m'
235 Profil 95 X 33 Z08 Rp. 24,210.00 m'
236 - Multigrip Rp. 4,760.00 bh
237 - Bolt Rp. 2,100.00 bh
238 - Screw Rp. 675.00 bh
239 Profil Batu Alam Rp. 50,000.00 bh
240 Batu Alam Rp. 10,850.00 bh
241 coating Rp. 80,000.00 kg
242 Spanrel Rp. 400,000.00 m2
243 Kabel Listrik NYA 3 x 2,5 mm Rp. 6,500.00 m'
244 Stop Kontak Rp. 12,000.00 Bh
245 Lampu SL 18 watt + fitting Rp. 27,000.00 Bh
246 Sekring Kast Rp. 35,000.00 Bh
247 MCB BOX Rp. 85,000.00 Bh
248 Over Spaneng Rp. 9,000.00 m'
249 Saklar Ganda Rp. 16,000.00 Bh
250 Saklar Tunggal Rp. 12,000.00 Bh
251 Wiremesh Rp. 515,000.00 Lbr
HARGA SATUAN
NO UPAH KERJA
(Rp)
1 Mandor Rp. 100,000.00 hari
2 Kepala Tukang Rp. 95,000.00 hari
3 Tukang Rp. 90,000.00 hari
4 Pembantu tukang Rp. 70,000.00 hari
5 Pekerja Rp. 10,000.00 jam
6 Kepala Tukang Rp. 13,571.43 jam
7 Tukang Rp. 12,857.14 jam
8 Mandor Rp. 14,285.71 jam
HARGA SATUAN
NO PERALATAN
(Rp)
1 Asphalt Spayer Rp. 113,747.09 jam
2 Compresor Rp. 185,882.28 jam
3 Dump truck 3.5 ton Rp. 297,684.44 jam
4 Dump truck 5 ton Rp. 401,725.39 jam
5 Motor grader Rp. 499,769.35 jam
6 Wheel Loader Rp. 389,008.13 jam
7 Three Wheel Roller Rp. 207,652.93 jam
8 Tandem Roller Rp. 307,225.14 jam
9 Water Tanker Rp. 283,674.99 jam
10 Asphalt Distributor Rp. 375,875.18 jam
11 AMP Rp. 4,219,019.76 jam
12 Genset Rp. 494,672.17 jam
13 Tyre Roller Rp. 463,787.91 jam
14 Conc. Mixer Rp. 71,434.36 jam
15 Conc. Pan Mixer Rp. 361,536.03 jam
16 Truck Mixer Rp. 596,950.86 jam
SUMBER, 2016
H. ABDUL KARIM, ST
NIP. 19620609 199101 1 001 YEDI ADHI PRIATNA, BAE.S.Sos
NIP. 19660815 199803 1 004
KEPALA DINAS CIPTA KARYA DAN TATA RUANG
KEPALA BIDANG BANGUNAN, PERUMAHAN DAN
KABUPATEN CIREBON
PERMUKIMAN DINAS CIPTA KARYA DAN TATA RUANG
KABUPATEN CIREBON
66,747.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 99,932.00
OVERHEAD & PROFIT (12.5%) 12,491.50
Jumlah Total 112,423.50
Dibulatkan 112,400.00
SNI.650.04 1 M2 PASANG LANTAI UBIN WAFEL PC 20 X 20 CM
25 bh Ubin wafel 20 x 20 cm 2,000.00 50,000.00
10.4 Kg Semen Portland 1,400.00 14,560.00
0.0135 m3 Pasir pasang 162,000.00 2,187.00
66,747.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 99,932.00
OVERHEAD & PROFIT (12.5%) 12,491.50
Jumlah Total 112,423.50
Dibulatkan 112,400.00
SNI.650.05 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM
11 bh Keramik 30 x 30 cm 3,150.00 34,650.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
59,586.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.014 Mandor 100,000.00 1,400.00
33,235.00
Jumlah 92,821.00
OVERHEAD & PROFIT (12.5%) 11,602.63
Jumlah Total 104,423.63
Dibulatkan 104,400.00
SNI.650.06 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM
25 bh Keramik 20 x 20 cm 2,000.00 50,000.00
11.38 kg Semen portland 1,400.00 15,932.00
0.042 m3 Pasir pasang 162,000.00 6,804.00
1.5 kg Semen warna 6,000.00 9,000.00
81,736.00
0.62 Pembantu tukang 70,000.00 43,400.00
0.35 Tukang batu 90,000.00 31,500.00
0.035 Kepala tukang 95,000.00 3,325.00
0.03 Mandor 100,000.00 3,000.00
81,225.00
Jumlah 162,961.00
OVERHEAD & PROFIT (12.5%) 20,370.13
Jumlah Total 183,331.13
Dibulatkan 183,300.00
SNI.650.07 1 M2 PASANG LANTAI KERAMIK 20 X 10 CM
50 bh Keramik 20 x 10 cm 1,000.00 50,000.00
11.38 kg Semen portland 1,400.00 15,932.00
0.042 m3 Pasir pasang 162,000.00 6,804.00
1.5 kg Semen warna 6,000.00 9,000.00
81,736.00
0.62 Pembantu tukang 70,000.00 43,400.00
0.35 Tukang batu 90,000.00 31,500.00
0.035 Kepala tukang 95,000.00 3,325.00
0.03 Mandor 100,000.00 3,000.00
81,225.00
Jumlah 162,961.00
OVERHEAD & PROFIT (12.5%) 20,370.13
Jumlah Total 183,331.13
Dibulatkan 183,300.00
SNI.650.08 1 M2 PASANG DINDING KERAMIK 30 X 30 CM
11 bh Keramik 30 x 30 cm 4,500.00 49,500.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
74,436.00
0.6 Pembantu tukang 70,000.00 42,000.00
0.45 Tukang batu 90,000.00 40,500.00
0.045 Kepala tukang 95,000.00 4,275.00
0.03 Mandor 100,000.00 3,000.00
89,775.00
Jumlah 164,211.00
OVERHEAD & PROFIT (12.5%) 20,526.38
Jumlah Total 184,737.38
Dibulatkan 184,700.00
SNI.650.09 1 M2 PASANG DINDING KERAMIK 20 X 20 CM
25 bh Keramik 20 x 20 cm 2,000.00 50,000.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
74,936.00
0.6 Pembantu tukang 70,000.00 42,000.00
0.45 Tukang batu 90,000.00 40,500.00
0.045 Kepala tukang 95,000.00 4,275.00
0.03 Mandor 100,000.00 3,000.00
89,775.00
Jumlah 164,711.00
OVERHEAD & PROFIT (12.5%) 20,588.88
Jumlah Total 185,299.88
Dibulatkan 185,200.00
SNI.650.10 1 M2 PASANG DINDING KERAMIK 10 X 20 CM
50 bh Keramik 10 x 20 cm 1,000.00 50,000.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
74,936.00
0.6 Pembantu tukang 70,000.00 42,000.00
0.45 Tukang batu 90,000.00 40,500.00
0.045 Kepala tukang 95,000.00 4,275.00
0.03 Mandor 100,000.00 3,000.00
89,775.00
Jumlah 164,711.00
OVERHEAD & PROFIT (12.5%) 20,588.88
Jumlah Total 185,299.88
Dibulatkan 185,200.00
SNI.650.11 1 M2 PASANG DINDING KERAMIK 20 X 25 CM
20 bh Keramik 20 x 25 cm 2,200.00 44,000.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
68,936.00
0.6 Pembantu tukang 70,000.00 42,000.00
0.45 Tukang batu 90,000.00 40,500.00
0.045 Kepala tukang 95,000.00 4,275.00
0.03 Mandor 100,000.00 3,000.00
89,775.00
Jumlah 158,711.00
OVERHEAD & PROFIT (12.5%) 19,838.88
Jumlah Total 178,549.88
Dibulatkan 178,500.00
SNI.650.12 1 M2 PASANG BATU TEMPEL KAPUR TEKSTUR TIDAK RATA 10 X 20 CM
50 bh Batu tempel 10 x 20 cm 2,050.00 102,500.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
127,436.00
0.6 Pembantu tukang 70,000.00 42,000.00
0.45 Tukang batu 90,000.00 40,500.00
0.045 Kepala tukang 95,000.00 4,275.00
0.03 Mandor 100,000.00 3,000.00
89,775.00
Jumlah 217,211.00
OVERHEAD & PROFIT (12.5%) 27,151.38
Jumlah Total 244,362.38
Dibulatkan 244,300.00
SNI.650.13 1 M2 PASANG BATU TEMPEL PALIMANAN TIDAK RATA 10 X 20 CM
50 bh Batu tempel Palimanan 1,550.00 77,500.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
102,436.00
0.6 Pembantu tukang 70,000.00 42,000.00
0.45 Tukang batu 90,000.00 40,500.00
0.045 Kepala tukang 95,000.00 4,275.00
0.03 Mandor 100,000.00 3,000.00
89,775.00
Jumlah 192,211.00
OVERHEAD & PROFIT (12.5%) 24,026.38
Jumlah Total 216,237.38
Dibulatkan 216,200.00
SNI.650.15 1 M2 PASANG LANTAI MOZAIK 20 X 20 CM
25 bh Mozaik 20 x 20 cm 1,900.00 47,500.00
14.15 kg Semen portland 1,400.00 19,810.00
0.039 m3 Pasir pasang 162,000.00 6,318.00
2 kg Semen warna 6,000.00 12,000.00
85,628.00
0.62 Pembantu tukang 70,000.00 43,400.00
0.35 Tukang batu 90,000.00 31,500.00
0.035 Kepala tukang 95,000.00 3,325.00
0.03 Mandor 100,000.00 3,000.00
81,225.00
Jumlah 166,853.00
OVERHEAD & PROFIT (12.5%) 20,856.63
Jumlah Total 187,709.63
Dibulatkan 187,700.00
SNI. 650.17 1 M2 PASANG LANTAI GRANIT 40 X 40 CM B
6.4 bh Granit 40 x 40 cm B 43,500.00 278,400.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
303,336.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 336,521.00
OVERHEAD & PROFIT (12.5%) 42,065.13
Jumlah Total 378,586.13
Dibulatkan 378,500.00
SNI. 650.18 1 M2 PASANG LANTAI GRANIT 40 X 40 CM A
6.4 bh Granit 40 x 40 cm A 42,000.00 268,800.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
293,736.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 326,921.00
OVERHEAD & PROFIT (12.5%) 40,865.13
Jumlah Total 367,786.13
Dibulatkan 367,700.00
SNI. 650.19 1 M2 PASANG LANTAI TERAKOTA 20 X 5 CM
100 bh Terakota 20 x 5 cm 4,400.00 440,000.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
464,936.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 498,121.00
OVERHEAD & PROFIT (12.5%) 62,265.13
Jumlah Total 560,386.13
Dibulatkan 560,300.00
SNI. 650.20 1 M2 PASANG LANTAI KERAMIK 40 X 40 CM
6 bh keramik 40 x 40 cm (putih polos) 7,200.00 43,200.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
68,136.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 101,321.00
OVERHEAD & PROFIT (12.5%) 12,665.13
Jumlah Total 113,986.13
Dibulatkan 113,900.00
SNI. 650.21 1 M2 PASANG LANTAI GRANIT 60 X 60 POLOS
3 bh Granit 60 x 60 cm 84,600.00 253,800.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
278,736.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 311,921.00
OVERHEAD & PROFIT (12.5%) 38,990.13
Jumlah Total 350,911.13
Dibulatkan 350,900.00
SNI. 650.22 1 M2 PASANG LANTAI GRANIT 60 X 60 CORAK
3 bh Granit 60 x 60 cm 57,600.00 172,800.00
9.3 kg Semen portland 1,400.00 13,020.00
0.018 m3 Pasir pasang 162,000.00 2,916.00
1.5 kg Semen warna 6,000.00 9,000.00
197,736.00
0.27 Pembantu tukang 70,000.00 18,900.00
0.13 Tukang batu 90,000.00 11,700.00
0.013 Kepala tukang 95,000.00 1,235.00
0.0135 Mandor 100,000.00 1,350.00
33,185.00
Jumlah 230,921.00
OVERHEAD & PROFIT (12.5%) 28,865.13
Jumlah Total 259,786.13
Dibulatkan 259,700.00
SNI. 950.17 1 M2 PENGECATAN TEMBOK LAMA (1 LPS CAT DASAR + 2 LPS CAT PENUTUP )
SNI. 960.36 1 M2 MENGERJAKAN RGK DAUN PINTU & JENDELA DARI KAYU JATI JABAR
0.035 m3 Kayu Jati jabar 8,200,000.00 287,000.00
287,000.00
0.8 Pembantu tukang 70,000.00 56,000.00
2 Tukang kayu 90,000.00 180,000.00
0.2 Kepala tukang 95,000.00 19,000.00
0.04 Mandor 100,000.00 4,000.00
259,000.00
Jumlah 546,000.00
OVERHEAD & PROFIT (12.5%) 68,250.00
Jumlah Total 614,250.00
Dibulatkan 614,200.00
SNI. 960.37 1 M2 MENGERJAKAN RANGKA DAUN PINTU & JENDELA DARI KAYU KAMPER
SNI. 960.45 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU JATI JABAR
0.064 m3 Kayu jati jabar 8,200,000.00 524,800.00
524,800.00
1 Pembantu tukang 70,000.00 70,000.00
3 Tukang kayu 90,000.00 270,000.00
0.3 Kepala tukang 95,000.00 28,500.00
0.3 Mandor 100,000.00 30,000.00
398,500.00
Jumlah 923,300.00
OVERHEAD & PROFIT (12.5%) 115,412.50
Jumlah Total 1,038,712.50
Dibulatkan 1,038,700.00
SNI. 960.47 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU JATI JABAR
0.0196 m3 Kayu jati jabar 8,200,000.00 160,720.00
0.03 kg Paku biasa 1/2" - 1" 18,500.00 555.00
0.3 ltr Lem kayu 30,000.00 9,000.00
1 lbr Plywood 4' x 3' x 4 mm 92,250.00 92,250.00
262,525.00
0.6 Pembantu tukang 70,000.00 42,000.00
2 Tukang kayu 90,000.00 180,000.00
0.2 Kepala tukang 95,000.00 19,000.00
0.03 Mandor 100,000.00 3,000.00
244,000.00
Jumlah 506,525.00
OVERHEAD & PROFIT (12.5%) 63,315.63
Jumlah Total 569,840.63
Dibulatkan 569,800.00
SNI. 960.48 1 M2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU KAMPER
0.0196 m3 Kayu kamper 8,200,000.00 160,720.00
0.03 kg Paku biasa 1/2" - 1" 18,500.00 555.00
0.3 ltr Lem kayu 30,000.00 9,000.00
1 lbr Plywood 4' x 3' x 4 mm 92,250.00 92,250.00
262,525.00
0.6 Pembantu tukang 70,000.00 42,000.00
2 Tukang kayu 90,000.00 180,000.00
0.2 Kepala tukang 95,000.00 19,000.00
0.03 Mandor 100,000.00 3,000.00
244,000.00
Jumlah 506,525.00
OVERHEAD & PROFIT (12.5%) 63,315.63
Jumlah Total 569,840.63
Dibulatkan 569,800.00
SNI. 960.50 1 M2 PASANG PINTU PLYWOOD DAN FORMIKA RANGKA KAYU JATI JABAR
0.0196 m3 Kayu jati jabar 8,200,000.00 160,720.00
0.3 kg Paku biasa 1/2" - 1" 18,500.00 5,550.00
0.8 ltr Lem kayu 30,000.00 24,000.00
1 lbr Plywood 4' x 8' x 4 mm 92,250.00 92,250.00
0.5 lbr formika 92,250.00 46,125.00
328,645.00
0.8 Pembantu tukang 70,000.00 56,000.00
2.5 Tukang kayu 90,000.00 225,000.00
0.25 Kepala tukang 95,000.00 23,750.00
0.04 Mandor 100,000.00 4,000.00
308,750.00
Jumlah 637,395.00
OVERHEAD & PROFIT (12.5%) 79,674.38
Jumlah Total 717,069.38
Dibulatkan 717,000.00
SNI. 960.51 1 M2 PASANG PINTU PLYWOOD DAN FORMIKA RANGKA KAYU KAMPER
0.0196 m3 Kayu kamper 8,200,000.00 160,720.00
0.3 kg Paku biasa 1/2" - 1" 18,500.00 5,550.00
0.8 ltr Lem kayu 30,000.00 24,000.00
1 lbr Plywood 4' x 8' x 4 mm 92,250.00 92,250.00
0.5 lbr formika 92,250.00 46,125.00
328,645.00
0.8 Pembantu tukang 70,000.00 56,000.00
2.5 Tukang kayu 90,000.00 225,000.00
0.25 Kepala tukang 95,000.00 23,750.00
0.04 Mandor 100,000.00 4,000.00
308,750.00
Jumlah 637,395.00
OVERHEAD & PROFIT (12.5%) 79,674.38
Jumlah Total 717,069.38
Dibulatkan 717,000.00
SNI. 960.52 1 M2 PASANG PINTU FORMIKA DOUBLE RANGKA KAYU JATI
0.0196 m3 Kayu Jati 8,200,000.00 160,720.00
0.300 kg Paku biasa 1/2" - 1" 18,500.00 5,550.00
1.200 ltr Lem kayu 30,000.00 36,000.00
1.000 lbr Plywood 4' x 8' x 4 mm 92,250.00 92,250.00
1.000 lbr formika 92,250.00 92,250.00
386,770.00
1.000 Oh Pembantu tukang 70,000.00 70,000.00
2.600 Oh Tukang kayu 90,000.00 234,000.00
0.260 Oh Kepala tukang 95,000.00 24,700.00
1.000 Oh Mandor 100,000.00 100,000.00
428,700.00
Jumlah 815,470.00
OVERHEAD & PROFIT (12.5%) 101,933.75
Jumlah Total 917,403.75
Dibulatkan 917,400.00
SNI. 970.32 1 M2 PASANGAN JALUSI MATI DARI KAYU JATI JABAR
0.02 m3 Kayu jati jabar 8,200,000.00 164,000.00
0.075 kg Paku biasa 1/2" - 1" 18,500.00 1,387.50
165,387.50
0.025 Pembantu tukang 70,000.00 1,750.00
0.9 Tukang kayu 90,000.00 81,000.00
0.09 Kepala tukang 95,000.00 8,550.00
0.012 Mandor 100,000.00 1,200.00
Upah kerja 92,500.00
Jumlah 257,887.50
OVERHEAD & PROFIT (12.5%) 32,235.94
Jumlah Total 290,123.44
Dibulatkan 290,100.00
SNI. 970.33 1 M2 PASANGAN JALUSI DARI KAYU KAMPER
0.02 m3 Kayu kamper 8,200,000.00 164,000.00
0.075 kg Paku biasa 1/2" - 1" 18,500.00 1,387.50
165,387.50
0.025 Pembantu tukang 70,000.00 1,750.00
0.9 Tukang kayu 90,000.00 81,000.00
0.09 Kepala tukang 95,000.00 8,550.00
0.012 Mandor 100,000.00 1,200.00
Upah kerja 92,500.00
Jumlah 257,887.50
OVERHEAD & PROFIT (12.5%) 32,235.94
Jumlah Total 290,123.44
Dibulatkan 290,100.00
SNI. 970.34 1 M2 PASANGAN JALUSI DARI KAYU BALAU
0.02 m3 Kayu balau 9,500,000.00 190,000.00
0.075 kg Paku biasa 1/2" - 1" 18,500.00 1,387.50
191,387.50
0.025 Pembantu tukang 70,000.00 1,750.00
0.9 Tukang kayu 90,000.00 81,000.00
0.09 Kepala tukang 95,000.00 8,550.00
0.012 Mandor 100,000.00 1,200.00
Upah kerja 92,500.00
Jumlah 283,887.50
OVERHEAD & PROFIT (12.5%) 35,485.94
Jumlah Total 319,373.44
Dibulatkan 319,300.00
SNI. 970.35 1 M2 PASANGAN JALUSI DARI KAYU KRUING
0.02 m3 Kayu kruing 7,274,000.00 145,480.00
0.075 kg Paku biasa 1/2" - 1" 18,500.00 1,387.50
146,867.50
0.025 Pembantu tukang 70,000.00 1,750.00
0.9 Tukang kayu 90,000.00 81,000.00
0.09 Kepala tukang 95,000.00 8,550.00
0.012 Mandor 100,000.00 1,200.00
Upah kerja 92,500.00
Jumlah 239,367.50
OVERHEAD & PROFIT (12.5%) 29,920.94
Jumlah Total 269,288.44
Dibulatkan 269,200.00
SNI. 970.36 1 M2 PASANGAN JALUSI DARI KAYU LANAN
0.02 m3 Kayu lanan 6,546,000.00 130,920.00
0.075 Paku biasa 1/2" - 1" 18,500.00 1,387.50
132,307.50
0.025 Pembantu tukang 70,000.00 1,750.00
0.9 Tukang kayu 90,000.00 81,000.00
0.09 Kepala tukang 95,000.00 8,550.00
0.012 Mandor 100,000.00 1,200.00
92,500.00
Jumlah 224,807.50
OVERHEAD & PROFIT (12.5%) 28,100.94
Jumlah Total 252,908.44
Dibulatkan 252,900.00
SNI. 970.37 1 M2 PASANGAN JALUSI DARI KAYU MERANTI
0.02 m3 Kayu meranti 6,000,000.00 120,000.00
0.075 Paku biasa 1/2" - 1" 18,500.00 1,387.50
121,387.50
0.025 Pembantu tukang 70,000.00 1,750.00
0.9 Tukang kayu 90,000.00 81,000.00
0.09 Kepala tukang 95,000.00 8,550.00
0.012 Mandor 100,000.00 1,200.00
Upah kerja 92,500.00
Jumlah 213,887.50
OVERHEAD & PROFIT (12.5%) 26,735.94
Jumlah Total 240,623.44
Dibulatkan 240,600.00
SNI. 975.22 1 M3 MENGERJAKAN RANGKA KUDA-KUDA DARI JATI JABAR
1.1 m3 Kayu jati jabar 8,200,000.00 9,020,000.00
15 kg Besi strip 13,750.00 206,250.00
0.8 kg Paku biasa 2" - 5" 16,000.00 12,800.00
9,239,050.00
4 Pembantu tukang 70,000.00 280,000.00
12 Tukang kayu 90,000.00 1,080,000.00
1.2 Kepala tukang 95,000.00 114,000.00
0.2 Mandor 100,000.00 20,000.00
1,494,000.00
Jumlah 10,733,050.00
OVERHEAD & PROFIT (12.5%) 1,341,631.25
Jumlah Total 12,074,681.25
Dibulatkan 12,074,600.00
SNI. 975.23 1 M3 MENGERJAKAN RANGKA KUDA-KUDA DARI KAYU KAMPER
1.1 m3 Kayu Kamper 8,200,000.00 9,020,000.00
15 kg Besi strip 13,750.00 206,250.00
0.8 kg Paku biasa 2" - 5" 16,000.00 12,800.00
9,239,050.00
4 Pembantu tukang 70,000.00 280,000.00
12 Tukang kayu 90,000.00 1,080,000.00
1.2 Kepala tukang 95,000.00 114,000.00
0.2 Mandor 100,000.00 20,000.00
1,494,000.00
Jumlah 10,733,050.00
OVERHEAD & PROFIT (12.5%) 1,341,631.25
Jumlah Total 12,074,681.25
Dibulatkan 12,074,600.00
SNI. 975.24 1 M3 MENGERJAKAN RANGKA KUDA-KUDA DARI KAYU BALAU
1.1 m3 Kayu balau 9,500,000.00 10,450,000.00
15 kg Besi strip 13,750.00 206,250.00
0.8 kg Paku biasa 2" - 5" 16,000.00 12,800.00
10,669,050.00
4 Pembantu tukang 70,000.00 280,000.00
12 Tukang kayu 90,000.00 1,080,000.00
1.2 Kepala tukang 95,000.00 114,000.00
0.2 Mandor 100,000.00 20,000.00
1,494,000.00
Jumlah 12,163,050.00
OVERHEAD & PROFIT (12.5%) 1,520,381.25
Jumlah Total 13,683,431.25
Dibulatkan 13,683,400.00
SNI. 975.25 1 M3 MENGERJAKAN RANGKA KUDA-KUDA DARI KRUING
1.1 m3 Kayu kruing 7,274,000.00 8,001,400.00
15 kg Besi strip 13,750.00 206,250.00
0.8 kg Paku biasa 2" - 5" 16,000.00 12,800.00
8,220,450.00
4 Pembantu tukang 70,000.00 280,000.00
12 Tukang kayu 90,000.00 1,080,000.00
1.2 Kepala tukang 95,000.00 114,000.00
0.2 Mandor 100,000.00 20,000.00
1,494,000.00
Jumlah 9,714,450.00
OVERHEAD & PROFIT (12.5%) 1,214,306.25
Jumlah Total 10,928,756.25
Dibulatkan 10,928,700.00
SNI. 975.26 1 M3 MENGERJAKAN RANGKA KUDA-KUDA DARI KAYU LANAN
1.1 m3 Kayu lanan 6,546,000.00 7,200,600.00
15 kg Besi strip 13,750.00 206,250.00
0.8 kg Paku biasa 2" - 5" 16,000.00 12,800.00
7,419,650.00
4 Pembantu tukang 70,000.00 280,000.00
12 Tukang kayu 90,000.00 1,080,000.00
1.2 Kepala tukang 95,000.00 114,000.00
0.2 Mandor 100,000.00 20,000.00
1,494,000.00
Jumlah 8,913,650.00
OVERHEAD & PROFIT (12.5%) 1,114,206.25
Jumlah Total 10,027,856.25
Dibulatkan 10,027,800.00
SNI. 975.27 1 M3 MENGERJAKAN RANGKA KUDA-KUDA DARI MERANTI
1.1 m3 Kayu meranti 6,000,000.00 6,600,000.00
15 kg Besi strip 13,750.00 206,250.00
0.8 kg Paku biasa 2" - 5" 16,000.00 12,800.00
6,819,050.00
4 Pembantu tukang 70,000.00 280,000.00
12 Tukang kayu 90,000.00 1,080,000.00
1.2 Kepala tukang 95,000.00 114,000.00
0.2 Mandor 100,000.00 20,000.00
1,494,000.00
Jumlah 8,313,050.00
OVERHEAD & PROFIT (12.5%) 1,039,131.25
Jumlah Total 9,352,181.25
Dibulatkan 9,352,100.00
SNI. 975.28 1 M3 MENGERJAKAN RANGKA KUDA-KUDA DARI BORNEO
1.1 m3 Kayu borneo 5,000,000.00 5,500,000.00
15 kg Besi strip 13,750.00 206,250.00
0.8 kg Paku biasa 2" - 5" 16,000.00 12,800.00
5,719,050.00
4 Pembantu tukang 70,000.00 280,000.00
12 Tukang kayu 90,000.00 1,080,000.00
1.2 Kepala tukang 95,000.00 114,000.00
0.2 Mandor 100,000.00 20,000.00
1,494,000.00
Jumlah 7,213,050.00
OVERHEAD & PROFIT (12.5%) 901,631.25
Jumlah Total 8,114,681.25
Dibulatkan 8,114,600.00
SNI. 975.29 1 M3 MENGERJAKAN RANGKA LANGIT-LANGIT (1,00 X 1,00)M, KAYU JATI JABAR
0.012 m3 Kayu jati jabar 8,200,000.00 98,400.00
0.1 kg Paku biasa 2" - 5" 16,000.00 1,600.00
100,000.00
0.15 Pembantu tukang 70,000.00 10,500.00
0.25 Tukang kayu 90,000.00 22,500.00
0.025 Kepala tukang 95,000.00 2,375.00
0.075 Mandor 100,000.00 7,500.00
42,875.00
Jumlah 142,875.00
OVERHEAD & PROFIT (12.5%) 17,859.38
Jumlah Total 160,734.38
Dibulatkan 160,700.00
SNI. 999.01 1 M2 PASANG PAVING BLOCK HEXAGON NATURAL SETARA K.225 TEBAL 6 CM
36 bh Paving block hexagon natural (uk. 17 x 17 x 6 cm) 1,650.00 59,400.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
75,600.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 109,287.50
OVERHEAD & PROFIT (12.5%) 13,660.94
Jumlah Total 122,948.44
Dibulatkan 122,900.00
SNI. 999.02 1 M2 PASANG PAVING BLOCK HEXAGON MOTIF SETARA K.225 TEBAL 6 CM
36 bh Paving block hexagon motif (uk. 17 x 17 x 6 cm) 1,800.00 64,800.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
81,000.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 114,687.50
OVERHEAD & PROFIT (12.5%) 14,335.94
Jumlah Total 129,023.44
Dibulatkan 129,000.00
SNI. 999.03 1 M2 PASANG PAVING BLOCK HEXAGON WARNA SETARA K.225 TEBAL 6 CM
36 bh Paving block hexagon warna (uk. 17 x 17 x 6 cm) 2,000.00 72,000.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
88,200.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 121,887.50
OVERHEAD & PROFIT (12.5%) 15,235.94
Jumlah Total 137,123.44
Dibulatkan 137,100.00
SNI. 999.04 1 M2 PASANG PAVING BLOCK HEXAGON NATURAL SETARA K.225 TEBAL 7 CM
27 bh Paving block hexagon natural (uk. 20 x 18 x 7 cm) 2,450.00 66,150.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
82,350.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 116,037.50
OVERHEAD & PROFIT (12.5%) 14,504.69
Jumlah Total 130,542.19
Dibulatkan 130,500.00
SNI. 999.05 1 M2 PASANG PAVING BLOCK HEXAGON MOTIF SETARA K.225 TEBAL 7 CM
27 bh Paving block hexagon motif (uk. 20 x 18 x 7 cm) 2,650.00 71,550.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
87,750.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 121,437.50
OVERHEAD & PROFIT (12.5%) 15,179.69
Jumlah Total 136,617.19
Dibulatkan 136,600.00
SNI. 999.06 1 M2 PASANG PAVING BLOCK HEXAGON WARNA SETARA K.225 TEBAL 7 CM
27 bh Paving block hexagon warna (uk. 20 x 18 x 7 cm) 2,850.00 76,950.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
93,150.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 126,837.50
OVERHEAD & PROFIT (12.5%) 15,854.69
Jumlah Total 142,692.19
Dibulatkan 142,600.00
SNI. 999.07 1 M2 PASANG PAVING BLOCK BOLDER NATURAL SETARA K.225 TEBAL 7 CM
25 bh Paving block bolder natural (uk. 20 x 20 x 7 cm) 3,000.00 75,000.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
91,200.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 124,887.50
OVERHEAD & PROFIT (12.5%) 15,610.94
Jumlah Total 140,498.44
Dibulatkan 140,400.00
SNI. 999.08 1 M2 PASANG PAVING BLOCK BOLDER WARNA SETARA K.225 TEBAL 7 CM
25 bh Paving block bolder warna (uk. 20 x 20 x 7 cm) 3,200.00 80,000.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
96,200.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 129,887.50
OVERHEAD & PROFIT (12.5%) 16,235.94
Jumlah Total 146,123.44
Dibulatkan 146,100.00
SNI. 999.09 1 M2 PASANG PAVING BLOCK BATA NATURAL SETARA K.225 TEBAL 7 CM
49 bh Paving block bata natural (uk. 10 x 20 x 7 cm) 1,400.00 68,600.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
84,800.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 118,487.50
OVERHEAD & PROFIT (12.5%) 14,810.94
Jumlah Total 133,298.44
Dibulatkan 133,200.00
SNI. 999.10 1 M2 PASANG PAVING BLOCK BATA WARNA SETARA K.225 TEBAL 7 CM
49 bh Paving block bata warna (uk. 10 x 20 x 7 cm) 1,500.00 73,500.00
0.1 m3 Pasir pasang 162,000.00 16,200.00
89,700.00
0.125 Pembantu tukang 70,000.00 8,750.00
0.25 Tukang batu 90,000.00 22,500.00
0.0125 Kepala tukang 95,000.00 1,187.50
0.0125 Mandor 100,000.00 1,250.00
33,687.50
Jumlah 123,387.50
OVERHEAD & PROFIT (12.5%) 15,423.44
Jumlah Total 138,810.94
Dibulatkan 138,800.00
SNI. BJR.02.b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG < 9 m
1.12 m' Profil U 75 53 mm Zinc Alumunium G. 550 18,450.00 20,664.00
0.945 m' Profil U 60 53 mm Zinc Alumunium G. 550 14,000.00 13,230.00
1.12 m' Profil U 75 83 mm Zinc Alumunium G. 550 22,300.00 24,976.00
6.09 m' Reng U 39 0.43 mm Zinc Alumunium G. 550 9,050.00 55,114.50
0.47 bh Plat Tumpu 7,975.00 3,748.25
2.12 bh Plat Diafragma 0.5 mm 1,500.00 3,180.00
0.80 bh Dynabolt 950.00 760.00
19.48 bh Baut Kuda - Kuda 250.00 4,870.00
20.50 bh Baut Reng 150.00 3,075.00
129,617.75
SNI. BJR.02.c 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG 9-12 m
1.31 m' Profil U 75 53 mm Zinc Alumunium G. 550 18,450.00 24,169.50
0.96 m' Profil U 60 53 mm Zinc Alumunium G. 550 14,000.00 13,440.00
1.31 m' Profil U 75 83 mm Zinc Alumunium G. 550 22,300.00 29,213.00
6.06 m' Reng U 39 0.43 mm Zinc Alumunium G. 550 9,050.00 54,843.00
0.45 bh Plat Tumpu 7,975.00 3,588.75
2.12 bh Plat Diafragma 0.5 mm 1,500.00 3,180.00
0.73 bh Dynabolt 950.00 693.50
21.00 bh Baut Kuda - Kuda 250.00 5,250.00
22.53 bh Baut Reng 150.00 3,379.50
137,757.25
SNI. BJR.02.d 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG 9-12 m
1.31 m' Profil U 75 53 mm Zinc Alumunium G. 550 18,450.00 24,169.50
0.99 m' Profil U 60 53 mm Zinc Alumunium G. 550 14,000.00 13,860.00
1.31 m' Profil U 75 83 mm Zinc Alumunium G. 550 22,300.00 29,213.00
6.09 m' Reng U 39 0.43 mm Zinc Alumunium G. 550 9,050.00 55,114.50
0.45 bh Plat Tumpu 7,975.00 3,588.75
2.12 bh Plat Diafragma 0.5 mm 1,500.00 3,180.00
0.75 bh Dynabolt 950.00 712.50
21.03 bh Baut Kuda - Kuda 250.00 5,257.50
22.55 bh Baut Reng 150.00 3,382.50
138,478.25
SNI. BJR.02.f 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG 12-15 m
1.48 m' Profil U 75 53 mm Zinc Alumunium G. 550 18,450.00 27,306.00
1.01 m' Profil U 60 53 mm Zinc Alumunium G. 550 14,000.00 14,140.00
1.48 m' Profil U 75 83 mm Zinc Alumunium G. 550 22,300.00 33,004.00
6.32 m' Reng U 39 0.43 mm Zinc Alumunium G. 550 9,050.00 57,196.00
0.668 bh Plat Tumpu 7,975.00 5,327.30
2.12 bh Plat Diafragma 0.5 mm 1,500.00 3,180.00
0.84 bh Dynabolt 950.00 798.00
22.5 bh Baut Kuda - Kuda 250.00 5,625.00
24.25 bh Baut Reng 150.00 3,637.50
150,213.80
SNI. BJR.03.a 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL Z GALVANISED COATING G.550
BENTUK ATAP PELANA BENTANG < 10 m
5.18 m' Profil 45 X 27 B50 15,490.00 80,238.20
0.42 m' Profil 65 X 26 C08 22,260.00 9,349.20
0.92 m' Profil 75 X 40 W08 24,020.00 22,098.40
1.57 m' Profil 95 X 33 Z08 24,210.00 38,009.70
1.78 bh - Multigrip 4,760.00 8,472.80
0.17 bh - Bolt 2,100.00 357.00
29 bh - Screw 675.00 19,575.00
178,100.30
SNI. BJR.03.b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL Z GALVANISED COATING G.550
BENTUK ATAP PERISAI BENTANG < 10 m
5.190 m' Profil 45 X 27 B50 15,490.00 80,393.10
0.425 m' Profil 65 X 26 C08 22,260.00 9,460.50
0.925 m' Profil 75 X 40 W08 24,020.00 22,218.50
1.575 m' Profil 95 X 33 Z08 24,210.00 38,130.75
1.785 bh - Multigrip 4,760.00 8,496.60
0.175 bh - Bolt 2,100.00 367.50
29.25 bh - Screw 675.00 19,743.75
178,810.70
SNI.All.7 1 UNIT PEMASANGAN DAUN PINTU ALLUMUNIUM lengkap warna natural/coklat dop 0,9 x 2,1 m
1.000 bh Daun Pintu Allumunium 945,000.00 945,000.00
0.900 m2 Kaca Polos 5 mm 75,000.00 67,500.00
0.630 m2 Spanrel 400,000.00 252,000.00
1.000 Alat Bantu 200,000.00 200,000.00
SNI.All.8 1 UNIT PEMASANGAN Daun pintu aluminium lengkap warna coklat kilap 0,9 x 2,1 m
1.000 bh Daun Pintu Allumunium 1,300,000.00 1,300,000.00
0.900 m2 Kaca Polos 5 mm 75,000.00 67,500.00
0.630 m2 Spanrel 400,000.00 252,000.00
1.000 Alat Bantu 200,000.00 200,000.00
SNI.All.9 1 UNIT PEMASANGAN Daun jendela aluminium lengkap warna natural/coklat dop 0,60 x 1m
1.000 bh Daun Jendela 361,750.00 361,750.00
0.900 m2 Kaca Polos 5 mm 75,000.00 67,500.00
1.000 Alat Bantu 100,000.00 100,000.00
SNI.All.10 1 UNIT PEMASANGAN Daun jendela aluminium lengkap warna coklat kilap 0,60 x 1m
1.000 bh Daun Jendela 400,000.00 400,000.00
0.900 m2 Kaca Polos 5 mm 75,000.00 67,500.00
1.000 Alat Bantu 100,000.00 100,000.00
4,910.68
OVERHEAD & PROFIT (12.5%) 596.65
HARGA SATUAN PEKERJAAN 5,507.33
ANB.2 1 m' Pemasangan pipa PVC dia. 315 (12 Inch) mm melalui galian tanah berbatu / bongkar jalan
0.825 m Galian tanah berbatu / bongkar jalan 123,700.00 102,052.50
0.225 m Urugan pasir 227,200.00 51,120.00
0.563 m Urugan tanah kembali 17,200.00 9,675.00
0.038 m Buang tanah sisa galian 27,100.00 1,016.25
1 m' Pemasangan pipa PVC dia. 315 mm 4,500.00 4,500.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 169,863.75
Dibulatkan 169,800.00
ANB.3 1 m' Pemasangan pipa PVC dia. 250 mm (10 Ich ) melalui galian tanah berbatu / bongkar jalan
0.715 m Galian tanah berbatu / bongkar jalan 123,700.00 88,445.50
0.195 m Urugan pasir 227,200.00 44,304.00
0.488 m Urugan tanah kembali 17,200.00 8,385.00
0.033 m Buang tanah sisa galian 27,100.00 880.75
1 m' Pemasangan pipa PVC dia. 250 mm 4,000.00 4,000.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 147,515.25
Dibulatkan 147,500.00
ANB.4 1 m' Pemasangan pipa PVC dia. 200 mm ( 8 Inch) melalui galian tanah berbatu / bongkar jalan
0.600 m Galian tanah berbatu / bongkar jalan 123,700.00 74,220.00
0.120 m Urugan pasir 227,200.00 27,264.00
0.450 m Urugan tanah kembali 17,200.00 7,740.00
0.030 m Buang tanah sisa galian 27,100.00 813.00
1 m' Pemasangan pipa PVC dia. 200 mm 3,500.00 3,500.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 115,037.00
Dibulatkan 115,000.00
ANB.5 1 m' Pemasangan pipa PVC dia. 160 mm ( 6 Inch) melalui galian tanah berbatu / bongkar jalan
0.450 m Galian tanah berbatu / bongkar jalan 123,700.00 55,665.00
0.100 m Urugan pasir 227,200.00 22,720.00
0.325 m Urugan tanah kembali 17,200.00 5,590.00
0.025 m Buang tanah sisa galian 27,100.00 677.50
1 m' Pemasangan pipa PVC dia. 160 mm 3,000.00 3,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 88,852.50
Dibulatkan 88,800.00
ANB.6 1 m' Pemasangan pipa PVC dia. 110 mm ( 4 Inch) melalui galian tanah berbatu / bongkar jalan
0.360 m Galian tanah berbatu / bongkar jalan 123,700.00 44,532.00
0.080 m Urugan pasir 227,200.00 18,176.00
0.260 m Urugan tanah kembali 17,200.00 4,472.00
0.020 m Buang tanah sisa galian 27,100.00 542.00
1 m' Pemasangan pipa PVC dia. 110 mm 2,500.00 2,500.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 71,422.00
Dibulatkan 71,400.00
ANB.7 1 m' Pemasangan pipa PVC dia. 90 mm ( 3 Inch) melalui galian tanah berbatu / bongkar jalan
0.320 m Galian tanah berbatu / bongkar jalan 82,400.00 26,368.00
0.080 m Urugan pasir 227,200.00 18,176.00
0.220 m Urugan tanah kembali 17,200.00 3,784.00
0.020 m Buang tanah sisa galian 27,100.00 542.00
1 m' Pemasangan pipa PVC dia. 90 mm 2,000.00 2,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 52,070.00
Dibulatkan 52,000.00
ANB.8 1 m' Pemasangan pipa PVC dia. 63 mm ( 2 Inch) melalui galian tanah berbatu / bongkar jalan
0.180 m Galian tanah berbatu / bongkar jalan 82,400.00 14,832.00
0.060 m Urugan pasir 227,200.00 13,632.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 63 mm 1,500.00 1,500.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 33,376.50
Dibulatkan 33,300.00
ANB.9 1 m' Pemasangan pipa PVC dia. 50 mm ( 1 1/2 Inch)melalui galian tanah berbatu / bongkar jalan
0.180 m Galian tanah berbatu / bongkar jalan 82,400.00 14,832.00
0.060 m Urugan pasir 227,200.00 13,632.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 50 mm 1,000.00 1,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 32,876.50
Dibulatkan 32,800.00
ANB.10 1 m' Pemasangan pipa PVC dia. 25 mm ( 3/4 Inch) melalui galian tanah berbatu / bongkar jalan
0.120 m Galian tanah berbatu / bongkar jalan 82,400.00 9,888.00
0.105 m Urugan tanah kembali 227,200.00 23,856.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 25 mm 500.00 500.00
1 ls Perapihan 1,000.00 1,000.00
Jumlah 35,650.50
Dibulatkan 35,600.00
ANK.2 1 m' Pemasangan pipa PVC dia. 315 mm ( 12 Inch)melalui galian tanah keras / berbatu
0.825 m Galian tanah keras / berbatu 82,400.00 67,980.00
0.225 m Urugan pasir 227,200.00 51,120.00
0.563 m Urugan tanah kembali 17,200.00 9,675.00
0.038 m Buang tanah sisa galian 27,100.00 1,016.25
1 m' Pemasangan pipa PVC dia. 315 mm 4,500.00 4,500.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 135,791.25
Dibulatkan 135,700.00
ANK.3 1 m' Pemasangan pipa PVC dia. 250 mm ( 10 Inch )melalui galian tanah keras / berbatu
0.715 m Galian tanah keras / berbatu 82,400.00 58,916.00
0.195 m Urugan pasir 227,200.00 44,304.00
0.488 m Urugan tanah kembali 17,200.00 8,385.00
0.033 m Buang tanah sisa galian 27,100.00 880.75
1 m' Pemasangan pipa PVC dia. 250 mm 4,000.00 4,000.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 117,985.75
Dibulatkan 117,900.00
ANK.4 1 m' Pemasangan pipa PVC dia. 200 mm (8 Inch) melalui galian tanah keras / berbatu
0.600 m Galian tanah keras / berbatu 82,400.00 49,440.00
0.120 m Urugan pasir 227,200.00 27,264.00
0.450 m Urugan tanah kembali 17,200.00 7,740.00
0.030 m Buang tanah sisa galian 27,100.00 813.00
1 m' Pemasangan pipa PVC dia. 200 mm 3,500.00 3,500.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 90,257.00
Dibulatkan 90,200.00
ANK.5 1 m' Pemasangan pipa PVC dia. 160 mm ( 6 Inch ) melalui galian tanah keras / berbatu
0.450 m Galian tanah keras / berbatu 82,400.00 37,080.00
0.100 m Urugan pasir 227,200.00 22,720.00
0.325 m Urugan tanah kembali 17,200.00 5,590.00
0.025 m Buang tanah sisa galian 27,100.00 677.50
1 m' Pemasangan pipa PVC dia. 160 mm 3,000.00 3,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 70,267.50
Dibulatkan 70,200.00
ANK.6 1 m' Pemasangan pipa PVC dia. 110 mm ( 4 Inch ) melalui galian tanah keras / berbatu
0.360 m Galian tanah keras / berbatu 82,400.00 29,664.00
0.080 m Urugan pasir 227,200.00 18,176.00
0.260 m Urugan tanah kembali 17,200.00 4,472.00
0.020 m Buang tanah sisa galian 27,100.00 542.00
1 m' Pemasangan pipa PVC dia. 110 mm 2,500.00 2,500.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 56,554.00
Dibulatkan 56,500.00
ANK.7 1 m' Pemasangan pipa PVC dia. 90 mm ( 3 Inch) melalui galian tanah keras / berbatu
0.320 m Galian tanah keras / berbatu 82,400.00 26,368.00
0.080 m Urugan pasir 227,200.00 18,176.00
0.220 m Urugan tanah kembali 17,200.00 3,784.00
0.020 m Buang tanah sisa galian 27,100.00 542.00
1 m' Pemasangan pipa PVC dia. 90 mm 2,000.00 2,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 52,070.00
Dibulatkan 52,000.00
ANK.8 1 m' Pemasangan pipa PVC dia. 63 mm ( 2 Inch) melalui galian tanah keras / berbatu
0.180 m Galian tanah keras / berbatu 82,400.00 14,832.00
0.060 m Urugan pasir 227,200.00 13,632.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 63 mm 1,500.00 1,500.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 33,376.50
Dibulatkan 33,300.00
ANK.9 1 m' Pemasangan pipa PVC dia. 50 mm 1 1/2 Inch) melalui galian tanah keras / berbatu
0.180 m Galian tanah keras / berbatu 82,400.00 14,832.00
0.060 m Urugan pasir 227,200.00 13,632.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 50 mm 1,000.00 1,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 32,876.50
Dibulatkan 32,800.00
ANK.10 1 m' Pemasangan pipa PVC dia. 25 mm (3/4 Inch ) melalui galian tanah keras / berbatu
0.120 m Galian tanah keras / berbatu 82,400.00 9,888.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 25 mm 500.00 500.00
1 ls Perapihan 1,000.00 1,000.00
Jumlah 13,600.50
Dibulatkan 13,600.00
ANBS.2 1 m' Pemasangan pipa PVC dia. 315 mm ( 12 Inch) melalui galian tanah biasa
0.825 m Galian tanah biasa 36,000.00 29,700.00
0.225 m Urugan pasir 227,200.00 51,120.00
0.563 m Urugan tanah kembali 17,200.00 9,675.00
0.038 m Buang tanah sisa galian 27,100.00 1,016.25
1 m' Pemasangan pipa PVC dia. 315 mm 4,500.00 4,500.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 97,511.25
Dibulatkan 97,500.00
ANBS.3 1 m' Pemasangan pipa PVC dia. 250 mm ( 10 Inch) melalui galian tanah biasa
0.715 m Galian tanah biasa 36,000.00 25,740.00
0.195 m Urugan pasir 227,200.00 44,304.00
0.488 m Urugan tanah kembali 17,200.00 8,385.00
0.033 m Buang tanah sisa galian 27,100.00 880.75
1 m' Pemasangan pipa PVC dia. 250 mm 4,000.00 4,000.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 84,809.75
Dibulatkan 84,800.00
ANBS.4 1 m' Pemasangan pipa PVC dia. 200 mm ( 8 Inch ) melalui galian tanah biasa
0.600 m Galian tanah biasa 36,000.00 21,600.00
0.120 m Urugan pasir 227,200.00 27,264.00
0.450 m Urugan tanah kembali 17,200.00 7,740.00
0.030 m Buang tanah sisa galian 27,100.00 813.00
1 m' Pemasangan pipa PVC dia. 200 mm 3,500.00 3,500.00
1 ls Perapihan 1,500.00 1,500.00
Jumlah 62,417.00
Dibulatkan 62,400.00
ANBS.5 1 m' Pemasangan pipa PVC dia. 160 mm ( 6 Inch ) melalui galian tanah biasa
0.450 m Galian tanah biasa 36,000.00 16,200.00
0.100 m Urugan pasir 227,200.00 22,720.00
0.325 m Urugan tanah kembali 17,200.00 5,590.00
0.025 m Buang tanah sisa galian 27,100.00 677.50
1 m' Pemasangan pipa PVC dia. 160 mm 3,000.00 3,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 49,387.50
Dibulatkan 49,300.00
ANBS.6 1 m' Pemasangan pipa PVC dia. 110 mm ( 4 Inch ) melalui galian tanah biasa
0.360 m Galian tanah biasa 36,000.00 12,960.00
0.080 m Urugan pasir 227,200.00 18,176.00
0.260 m Urugan tanah kembali 17,200.00 4,472.00
0.020 m Buang tanah sisa galian 27,100.00 542.00
1 m' Pemasangan pipa PVC dia. 110 mm 2,500.00 2,500.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 39,850.00
Dibulatkan 39,800.00
ANBS.7 1 m' Pemasangan pipa PVC dia. 90 mm ( 3 Inch) melalui galian tanah biasa
0.320 m Galian tanah biasa 36,000.00 11,520.00
0.080 m Urugan pasir 227,200.00 18,176.00
0.220 m Urugan tanah kembali 17,200.00 3,784.00
0.020 m Buang tanah sisa galian 27,100.00 542.00
1 m' Pemasangan pipa PVC dia. 90 mm 2,000.00 2,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 37,222.00
Dibulatkan 37,200.00
ANBS.8 1 m' Pemasangan pipa PVC dia. 63 mm ( 2 Inch) melalui galian tanah biasa
0.180 m Galian tanah biasa 36,000.00 6,480.00
0.060 m Urugan pasir 227,200.00 13,632.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 63 mm 1,500.00 1,500.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 25,024.50
Dibulatkan 25,000.00
ANBS.9 1 m' Pemasangan pipa PVC dia. 50 mm ( 1 1/2 Inch) melalui galian tanah biasa
0.180 m Galian tanah biasa 36,000.00 6,480.00
0.060 m Urugan pasir 227,200.00 13,632.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 50 mm 1,000.00 1,000.00
1 ls Perapihan 1,200.00 1,200.00
Jumlah 24,524.50
Dibulatkan 24,500.00
ANBS.10 1 m' Pemasangan pipa PVC dia. 25 mm ( 3/4 Inch) melalui galian tanah biasa
0.120 m Galian tanah biasa 36,000.00 4,320.00
0.105 m Urugan tanah kembali 17,200.00 1,806.00
0.015 m Buang tanah sisa galian 27,100.00 406.50
1 m' Pemasangan pipa PVC dia. 25 mm 500.00 500.00
1 ls Perapihan 1,000.00 1,000.00
Jumlah 8,032.50
Dibulatkan 8,000.00
SUMBER, 2016
HARGA SATUAN
NO KODE SATUAN PEKERJAAN
Rp
SUMBER, 2016
H. ABDUL KARIM, ST
NIP. 19620609 199101 1 001 YEDI ADHI PRIATNA, BAE.S.Sos
NIP. 19660815 199803 1 004
H. ABDUL KARIM, ST
NIP. 19620609 199101 1 001 YEDI ADHI PRIATNA, BAE.S.Sos
NIP. 19660815 199803 1 004