PEKERJAAN PERSIAPAN

PEMBANGUNAN TOL RUAS PEMATANG PANGGANG - KAYU AGUNG


SUMATERA SELATAN
ID AKTIFITAS WAKTU MULAI SELESAI 2017 2018
Half 2, 2016 Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018
M J J A S O N D J F M A M J J A S O N D J F M A M J J
0 PEKERJAAN PERSIAPAN PEMBANGUNAN JALAN TOL RUAS 489 days Mon 7/25/16 Thu 6/7/18 7/25 6/7
PEMATANG PANGGANG - KAYU AGUNG, SUMATERA
SELATAN (STA 108+600 s/d STA 186+595,22)
1 1 STA 138+900 sd STA 163+900 489 days Mon 7/25/16 Thu 6/7/18 7/25 6/7
2 1.1 PPK & BPN 100 days Mon 7/25/16 Fri 12/9/16 7/25 12/9
3 1.1.1 LAHAN MILIK PERUSAHAAN (17 KM) 85 days Mon 7/25/16 Fri 11/18/16 7/25 11/18
4 1.1.1.1 Pematokan Trase 30 days Mon 7/25/16 Fri 9/2/16 7/25 9/2
5 1.1.1.2 Pengukuran Bidang Tanah 42 days Mon 8/8/16 Tue 10/4/16 8/8 10/4
6 1.1.1.3 Klarifikasi Kepemilikan 30 days Wed 8/24/16 Tue 10/4/16 8/24 10/4
7 1.1.1.4 Inventarisasi Pohon 5 days Fri 9/2/16 Thu 9/8/16 9/2 9/8
8 1.1.1.5 Berita Acara Kesepakatan 3 days Wed 10/5/16 Fri 10/7/16 10/5 10/7
9 1.1.1.6 Pembayaran Ganti Rugi 30 days Mon 10/10/16 Fri 11/18/16 10/10 11/18
10 1.1.2 LAHAN MILIK WARGA (8 KM) 100 days Mon 7/25/16 Fri 12/9/16 7/25 12/9
11 1.1.2.1 Pematokan Trase 50 days Mon 7/25/16 Fri 9/30/16 7/25 9/30
12 1.1.2.2 Pengukuran Bidang Tanah 42 days Mon 8/8/16 Tue 10/4/16 8/8 10/4
13 1.1.2.3 Klarifikasi Kepemilikan 30 days Wed 8/24/16 Tue 10/4/16 8/24 10/4
14 1.1.2.4 Inventarisasi Pohon 10 days Fri 9/2/16 Thu 9/15/16 9/2 9/15
15 1.1.2.5 Berita Acara Kesepakatan 3 days Wed 10/5/16 Fri 10/7/16 10/5 10/7
16 1.1.2.6 Pembayaran Ganti Rugi 45 days Mon 10/10/16 Fri 12/9/16 10/10 12/9
17 1.2 EGIS 142 days Tue 7/26/16 Wed 2/8/17 7/26 2/8
18 1.2.1 Tracking trase untuk kepastian koordinat 14 days Tue 7/26/16 Fri 8/12/16 7/26 8/12
19 1.2.2 Inventarisasi bangunan crossing (sungai, jalan, saluran, SUTT & 14 days Tue 7/26/16 Fri 8/12/16 7/26 8/12
AMDAL)
20 1.2.3 Pemasangan BM 14 days Mon 8/1/16 Thu 8/18/16 8/1 8/18
21 1.2.4 Penyelidikan Tanah 21 days Mon 8/1/16 Mon 8/29/16 8/1 8/29
22 1.2.5 Draft ROW Plan & Asistensi 14 days Wed 8/10/16 Mon 8/29/16 8/10 8/29
23 1.2.6 Preliminaries Desain 14 days Mon 8/15/16 Thu 9/1/16 8/15 9/1
24 1.2.7 Final Report Basic Design 14 days Fri 8/19/16 Wed 9/7/16 8/19 9/7
25 1.2.8 Detail Engineering Design 120 days Thu 8/25/16 Wed 2/8/17 8/25 2/8
26 1.3 WASKITA 408 days Thu 9/8/16 Mon 4/2/18 9/8 4/2
27 1.3.1 Site Clearing 120 days Mon 10/10/16 Fri 3/24/17 10/10 3/24
28 1.3.2 Pembuatan akses jalan 160 days Thu 10/13/16 Wed 5/24/17 10/13 5/24
29 1.3.3 Leveling (Galian/Timbunan) 180 days Thu 10/20/16 Wed 6/28/17 10/20 6/28
30 1.3.4 Konstruksi 408 days Thu 9/8/16 Mon 4/2/18 9/8 4/2
31 1.3.4.1 Perbaikan Tanah 180 days Thu 9/8/16 Wed 5/17/17 9/8 5/17
32 1.3.4.2 Subgrade 180 days Mon 12/19/16 Fri 8/25/17 12/19 8/25
33 1.3.4.3 Lapisan Pondasi 180 days Wed 3/29/17 Tue 12/5/17 3/29 12/5
34 1.3.4.4 Pavement 180 days Fri 7/7/17 Thu 3/15/18 7/7 3/15
35 1.3.4.5 Pekerjaan Pendukung & Marka Jalan 120 days Tue 10/17/17 Mon 4/2/18 10/17 4/2
36 1.4 Testing & Commissioning 90 days Fri 2/2/18 Thu 6/7/18 2/2 6/7
37 1.5 Serah Terima Pekerjaan 0 days Thu 6/7/18 Thu 6/7/18 6/7