JADWAL PELAKSANAAN

( TIME SCHEDULE )
LOKASI : Kecamatan Gemeh
NOMOR KONTRAK : 04/PPK-PJAB-DM/V/2016
TANGGAL KONTRAK : 31 Mei 2016
NILAI KONTRAK :
TAHUN ANGGARAN : 2016
KONSULTAN :
PENYEDIA JASA : CV. RISMA

BOBOT WAKTU PELAKSANAAN ( 150 Hari Kalender )


NO. MATA PEMB. URAIAN JENIS PEKERJAAN KET.
24-Jun 27-Jun 4-Jul 11-Jul 18-Jul 25-Jul 1-Aug 8-Aug 15-Aug 22-Aug 29-Aug 5-Sep 12-Sep 19-Sep 26-Sep 3-Oct 10-Oct 17-Oct 24-Oct 31-Oct 7-Nov 14-Nov
%
26-Jun 3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct 30-Oct 6-Nov 13-Nov 21-Nov
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
I Pekerjaan Persiapan 1.86 0.930 0.930

II Pekerjaan Broncap Tering I 6.45 6.450

III Pekerjaan Broncap Tering II 6.49 3.245 3.245

IV Pekerjaan Penampung 13.34 13.340

V Pekerjaan Reservoir 20.74 20.740


150
VI Pekerjaan Perpipaan 47.70 23.850 23.850 Hari Kalender

VII Pekerjaan Lain-Lain 3.41 3.410

100.0
Rencana Kemajuan Pekerjaan (%) 0.130 0.130 3.245 3.245 37.190 44.590 3.410 - - - - - - - - - - - - - - 0.930
Kumulatif Rencana Kemajuan Pekerjaan (%) 0.130 0.260 3.505 6.750 43.940 88.530 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 91.940 92.870
Realisasi Kemajuan Pekerjaan (%) 1.581 #REF! #REF! #REF! #REF! #REF! #REF!
Kumulatif Realisasi Kemajuan Pekerjaan (%)
Deviasi (%)

0.43 1.87 2.91 4.26 6.20 8.11 10.86 12.63 16.03 19.86 26.30 32.05 35.71 39.10 48.62 58.13 67.65 77.17 82.81 88.45 94.22

0 - KONSULTAN SUPERVISI DIBUAT OLEH :


0 0 PT. WESITAN KONSULTASI PEMBENGUNAN Konsultan Pengawas
CV. Piramida Abadi Consultant

0 0 SAIFUL B. MOKOGINTA, ST,M.MT 0


0 0 SUPERVISION ENGINEER Team Leader
Agustus 31 31
September 30 30
Oktober 31 31
Nopember 29 10

121 102 19

BULAN
1 2 3 4 5 6 7
TOTAL
Bobot Volume Bobot Volume Bobot Volume Bobot Volume Bobot Volume Bobot Volume Bobot Volume
1.860 0.00 3.00 0.930 0.50 - - - - - - 0.930 0.50 - - - -

6.450 0.00 3.00 6.450 3.60 - - - - - - - - - - - -

13.340 0.00 8.00 13.340 10.08 - - - - - - - - - - - -

0.000 0.00 3.00 - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0!

3.410 0.00 3.00 - - 3.410 17.20 - - - - - - - - - -


0.000 0.00 3.00 - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0! - #DIV/0!
25.060 -74.93
20.720 3.410 - - 0.930 - - 25.060
3.410
-
-
0.930
-
0 0

BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 BULAN 7 BULAN 8 BULAN 1 BULAN 2

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 1 2 3 4

- -

- -

#DIV/0! -

- -
#DIV/0! -

#REF! #REF!
BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 BULAN 7 BULAN 8

5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

0
0
LAPORAN KEMAJUAN PEKERJAAN BULANAN
PAKET : PEMBANGUNAN JARINGAN AIR BERSIH / AIR MINUM DESA RAE
PENYEDIA JASA : CV. RILLY
KONSULTAN PENGAWAS : CV. PIRAMIDA ABADI CONSULTANT MINGGU KE : 14 (Empat Belas)
NO./TGL. KONTRAK : 04/PPK-PJAB-DR/V/2016/2016, 27 MEI 2016 TANGGAL : 29 Agst s/d 4 Sept 2016
NILAI KONTRAK : Rp. 1,578,829,000.00

VOLUME SELESAI Nilai Bobot Nilai Bobot Tingkat


Mata VOLUME Tiap Bagian Penyelesaian Penyelesaian
URAIAN SAT.
Pembayaran KONTRAK S/D MINGGU Pekerjaan Tiap Pek. Tiap Bagian Thd
MINGGU INI (%) (%) Seluruh Pek (%)
INI

I PEKERJAAN PERSIAPAN

1 Fasilitas Penunjang Paket 1.00 0.76 0.76 1.864 76.00 1.416

II PEKERJAAN BRONCAPTERING

1 Pembersihan Daerah Broncap Ls 1.00 - - 0.348 - -


2 Galian Tanah Berbatu M3 7.28 - - 0.057 - -
3 Pas. Pondasi Batu Kali 1:3 M3 10.80 - - 2.049 - -
4 Cor Beton Bertulang Kedap Air (1:2:3) M3 12.48 - - 6.472 - -
5 Urugan Pasir Dibawah Lantai M3 3.64 - - 0.195 - -
6 Cor Beton 1:2:3 (Lantai Penangkap) M3 1.10 - - 0.243 - -
7 Plesteran sp 1:3 M2 20.30 - - 0.167 - -
8 Pipa Outlet
- Pipa GIP (Medium-A)dia 6" M' 40.00 - - 0.969 - -
- Gate valve dia 6" Unit 1.00 - - 0.181 - -
- Flange steel dia 6" Bh 7.00 - - 0.096 - -
- Baut mur dia. 17mm x 5 cm Bh 42.00 - - 0.022 - -
9 Pipa Penguras
- Pipa GIP (Medium-A)dia 4" M' 2.00 - - 0.042 - -
- Gate valve dia 4" Unit 1.00 - - 0.111 - -

III PEKERJAAN PENAMPUNG

1 Galian Tanah Berbatu M3 3.84 - - 0.030 - -


2 Timbunan Tanah Dipadatkan M3 6.40 - - 0.246 - -
3 Urugan Pasir M3 1.60 - - 0.086 - -
4 Pekerjaan Beton:
- Lantai kerja t. 10 cm beton tumbuk camp 1:3:5 M3 1.60 - - 0.310 - -
- Pelat lantai t. 20 cm beton bertulang 1:2:3 M3 3.20 - - 1.659 - -
- Dinding luar t. 20 cm beton bertulang 1:2:3 M3 6.40 - - 3.319 - -
- Pelat atap t. 15 cm beton bertulang 1:2:3 M3 2.40 - - 1.245 - -
5 Plesteran sp 1:3 M2 64.00 - - 0.527 - -
6 Acian M2 64.00 - - 0.253 - -
7 Pengecetan Dinding M2 80.00 - - 0.310 - -
8 Pipa Outlet Ke spl
- Pipa GIP (Medium-A)dia 4" M' 6.00 - - 0.126 - -
- Gate valve dia 4" Unit 1.00 - - 0.111 - -
- Flange steel dia 4" Unit 1.00 - - 0.011 - -
- Baut mur dia. 17mm x 5 cm Bh 16.00 - - 0.008 - -
9 Pipa Penguras
- Pipa GIP (Medium-A)dia 3" M' 2.00 - - 0.027 - -
- Gate valve dia 3" Unit 1.00 - - 0.091 - -
- Flange steel dia 3" Bh 6.00 - - 0.055 - -
- Baut mur dia. 17mm x 5 cm Bh 36.00 - - 0.019 - -
10 Pekerjaan Lain-Lain
- Cor Beton 1:3:5 M3 4.12 - - 0.799 - -
- Plesteran M2 41.20 - - 0.339 - -
- Manhole uk 50x50 cm Unit 1.00 - - 0.034 - -
- Box gate valve uk 40x40 cm Unit 1.00 - - 0.034 - -
- Kunci Gembok Bh 4.00 - - 0.005 - -

VI PEKERJAAN SARINGAN PASIR LAMBAT

1 Galian Tanah Biasa M3 39.89 28.73 28.73 0.229 72.02 0.165


2 Timbunan Tanah Dipadatkan M3 6.00 - - 0.230 - -
3 Urugan Pasir M3 2.80 - - 0.150 - -
4 Pekerjaan Beton:
- Lantai kerja t. 10 cm beton tumbuk camp 1:3:5 M3 4.00 - - 0.775 - -
- Pelat lantai t. 25 cm beton bertulang 1:2:3 M3 10.00 - - 5.186 - -
- Dinding luar t. 20 cm beton bertulang 1:2:3 M3 14.00 - - 7.260 - -
- Dinding sekat t. 20 cm beton bertulang 1:2:3 M3 4.00 2.074
- Pelat atap t. 15 cm beton bertulang 1:2:3 M3 6.00 - - 3.111 - -
5 Plesteran sp 1:3 M2 90.00 - - 0.741 - -
6 Acian M2 90.00 - - 0.356 - -
7 Pengecetan Dinding M2
71.60 - - 0.278 - -
8 Pipa Inlet
- Pipa GIP (Medium-A)dia 3" M' 6.00 - - 0.081 - -
- Gate valve dia 3" Unit 1.00 - - 0.091 - -
- Bend all flange 45 dia 3" Bh 2.00 0.028
- Flange steel dia 3" Bh 6.00 - - 0.055 - -
- Baut mur dia. 17mm x 5 cm Bh 1.00 - - 0.001 - -
9 Pipa Outlet
- Pipa GIP (Medium-A)dia 3" M' 6.00 - - 0.081 - -
- Gate valve dia 3" Unit 1.00 - - 0.091 - -
- Flange steel dia 3" Unit 1.00 - - 0.009 - -
- Baut mur dia. 17mm x 5 cm Bh 16.00 - - 0.008 - -
10 Pipa Penguras
- Pipa GIP (Medium-A)dia 3" M' 2.00 - - 0.027 - -
- Gate valve dia 3" Unit 1.00 - - 0.091 - -
- Flange steel dia 3" Bh 6.00 - - 0.055 - -
- Baut mur dia. 17mm x 5 cm Bh 2.00 - - 0.028 - -
11 Pekerjaan Saringan
- Cor beton 1:2:3 M3 3.99 - - 0.774 - -
- Nozel Bh 30.00 - - 0.025 - -
- Ijuk Kg 20.00 - - 0.063 - -
- Kerikil filter dia 5-10 mm M3 6.00 - - 0.505 - -
- Pasir Filter Unit 6.00 - - 0.457 - -
12 Pekerjaan Lain-lain -
- Manhole uk 50x50 cm Unit 1.00 - - 0.034 - -
- Box gate valve uk 40x40 cm Unit 1.00 - - 0.034 - -
- Tangga Monyet besi beton dia. 12 mm Unit 1.00 - - 0.033 - -

V PEKERJAAN PERPIPAAN

1 Pengadaan dan Pemasangan Pipa GIP (medium-B) dia. 6" M' 95.00 - - 2.300 - -
2 Pengadaan dan Pemasangan Pipa GIP (medium-B) dia. 4" M' 782.00 - - 16.359 - -
3 Pengadaan dan Pemasangan Pipa GIP (medium-B) dia. 3" M' 166.00 - - 2.245 - -
4 Pengadaan dan Pemasangan PipaPVC/RRJ (S-12.5) dia 4" M' 846.00 - - 9.006 - -
5 Pengadaan dan Pemasangan PipaPVC/RRJ (S-12.5) dia 3" M' 1,089.00 - - 10.044 - -
6 Pengadaan dan Pemasangan PipaPVC/RRJ (S-12.5) dia 2" M' 1,355.00 - - 10.049 - -
7 Pengadaan dan Pemasangan Accessories/Fitting
- Bend all flange (GI) 45 dia 4" Bh 4.00 - - 0.072 - -
- Bend all flange (GI) 22.5 dia 4" Bh 5.00 - - 0.091 - -
- Bend all flange (GI) 45 dia 3" Bh 4.00 - - 0.057 - -
- Flange steel dia 4" Bh 5.00 - - 0.056 - -
- Flange steel dia 3" Bh 8.00 - - 0.074 - -
- Bend 90 all socket (PVC/RRJ) dia 3" Bh 2.00 0.022
- Flange socket (PVC/RRJ) dia 4" Bh 8.00 - - 0.190 - -
- Flange socket (PVC/RRJ) dia 3" Bh 8.00 - - 0.156 - -
- Flange socket (PVC/RRJ) dia 2" Bh 8.00 - - 0.089 - -
- Flange spigot (PVC) dia 4" Bh 8.00 - - 0.183 - -
- Flange spigot (PVC) dia 3" Bh 8.00 - - 0.152 - -
- Flange spigot (PVC) dia 2" Bh 8.00 - - 0.085 - -
- Reducer all socket (PVC/RRJ) dia 4" x 3" Bh 1.00 - - 0.008
- Reducer all socket (PVC/RRJ) dia 3" x 2" Bh 1.00 - - 0.006
- Baut mur dia. 17mm x 5 cm Bh 48.00 - - 0.025 - -
- Packing Ls 1.00 - - 0.010 - -
9 Pengecetan Pipa Besi M2 139.41 - - 0.327 - -

VI PEKERJAAN LAIN-LAIN

1 Tiang Penyangga Pipa Beton Bertulang Bh 5.00 - - 0.670 - -


2 Perbaikan Jalan Pada Pelintasan Pipa Ls 1.00 - - 0.209 - -
3 Kran Umum dan Accesoriesnya Unit 15.00 - - 2.090 - -

TOTAL 100.00 1.581

KETERANGAN :
I. FISIK : II. WAKTU :
RENCANA KONTRAK : 55.881 % 180.00 HK = 100.00 %
REALISASI : 1.581 % 105.00 HK = 58.33 %
DEVIASI THDP KONTRAK : -54.300 % 75.00 HK = 41.67 %

DIBUAT OLEH :
Konsultan Pengawas
CV. Piramida Abadi Consultant