PERHITUNGAN KONTRUKSI
1. Panel A
1 1
Lny = ( 5750 2 x 300 - 2 x 300) = 5450 mm
1 1
Lnx = ( 3000 2 x 250 - 2 x 250) = 2750 mm
A 5450
= = 2750 = 1,9
diasumsikan m > 2, maka ketebalan minimum
300
(0,8+( ) 5450 (0,8+( )
1500 1500
Hmin = = = 102,63 mm
36+9 36+9(1,9)
41
42
2. Panel B
1 1
Lny = ( 3000 2 x 250 - 2 x 250) = 2750 mm
1 1
Lnx = ( 1250 2 x 300 - 2 x 300) = 950 mm
B 2750
= = 950 = 2,8
diasumsikan m > 2, maka ketebalan minimum
(0,8+(
) 2750 (0,8+(
300
)
1500 1500
Hmin = = = 44,93 mm
36+9 36+9(2,8)
3. Panel C
1 1
Lny = ( 4000 2 x 300 - 2 x 300 ) = 3700 mm
1 1
Lnx = ( 3000 2 x 250 - 2 x 250 ) = 2750 mm
C 3700
= = 2750 = 1,3
diasumsikan m > 2, maka ketebalan minimum
(0,8+(
1500
) 3750 (0,8+(
300
1500
)
Hmin = = = 78,61 mm
36+9 36+9(1,3)
4. Panel D
5.
1 1
Lny = ( 3000 2 x 250 - 2 x 250) = 2750 mm
1 1
Lnx = ( 3000 2 x 300 - 2 x 300) = 2700 mm
Hmin =
2750
= = 2700 = 1,0
diasumsikan m > 2, maka ketebalan minimum
(0,8+(
1500
36+9
)
=
2750 (0,8+(
300
1500
36+9(1,0)
)
= 61,11
43
5. Panel E
6.
1 1
Lny = ( 4000 2 x 250 - 2 x 250) = 3750 mm
1 1
E
Lnx = ( 3500 2 x 300 - 2 x 300) = 3200 mm
3750
= = 3200 = 1,1
diasumsikan m > 2, maka ketebalan minimum
300
(0,8+( ) 3750 (0,8+( )
1500 1500
Hmin = = = 81,69 mm
36+9 36+9(1,1)
6. Panel F
7.
1 1
Lny = ( 4000 2 x 250 - 2 x 250) = 3750 mm
1 1
Lnx = ( 4000 2 x 300 - 2 x 300) = 3700 mm
F 3750
= = 3700 = 1,0
diasumsikan m > 2, maka ketebalan minimum
300
(0,8+( ) 3750 (0,8+( )
1500 1500
Hmin = = = 83,33 mm
36+9 36+9(1,0)
7. Panel G
8.
1 1
Lny = ( 4000 2 x 250 - 2 x 250) = 3750 mm
1 1
Lnx = ( 3000 2 x 300 - 2 x 300) = 2700 mm
G 3750
= = 2700 = 1,3
diasumsikan m > 2, maka ketebalan minimum
300
(0,8+( ) 3750 (0,8+( )
1500 1500
Hmin = = = 78,61 mm
36+9 36+9(1,3)
44
Menghitung m
2 (30x60)
A
3 (25x40)
1 (25x40)
4 (30x60)
1. 1
beff = bw + hw bw + 4hf
300 + 497,37 300 + 4(102,63)
797,37 mm 710,52 mm
maka diambil nilai beff terkecil= 710,52 mm
b= 710,52mm
hf=102,63 mm
h=600
y1=548,685 hw=497,37 mm
y2=248,685
bw=300
45
1
= 710,52 102,633 + 72.920,66 201,5252
12
1
+ 300 497,373 + 149.211 98,4752
12
= 6102876576 mm4
1 1 1
Ipelat1 = . hf3 ( Lkanan + Lkiri)
12 2 2
1 1 1
= 12 x 102,633 ( 2 x 5750 + 2 x 0 )
= 258987968,9 mm4
1 6102876576 mm4
Maka nilai 1 = 1 = = 23,56
258987968,9 mm4
2. 2
beff = bw + hw bw + 4hf
250 + 297,37 250 + 4(102,63)
574,37 660,52
maka diambil nilai beff = 574,37 mm
46
b= 574,37mm
hf=102,63 mm
h=400
y1=348,685 hw=297,37 mm
y2=148,685
bw=250
1
+ 250 297,373 + 74.342,5 104,3652
12
= 1948456667 mm4
1 1 1
Ipelat2 = 12 . hf3 ( 2 Lkanan + Lkiri)
2
1 1 1
= 12 x 102,633 ( 2 x 3000 + 2 x 0 )
= 135124157,7 mm4
2 1948456667 mm4
Maka nilai 2 = 2 = = 14,41
135124157,7 mm4
47
3. 3
beff = bw + 2hw bw + 8hf
300 + 2(497,63) 300 + 8(102,63)
1295,26 1121,04
maka diambil nilai beff = 1121,04 mm
b=1121,04
hf=102,63
h=600
y1=548,945 hw=497,63
y2=248,815
bw=300
1
+ 300 497,633 + 149.289 130,6252
12
= 9034738291 mm4
48
1 1 1
Ipelat3 = 12 . hf3 ( 2 Lkanan + Lkiri)
2
1 1 1
= 12 x 102,633 ( 2 x 5750 + 2 x 5750)
= 517975937,8 mm4
3 9034738291 mm4
Maka nilai 3 = 3 = = 17,44
517975937,8 mm4
4. 4
beff = bw + 2 hw bw + 8hf
250 + 2(297,63) 250 + 8(102,63)
845,26 mm 1071,04 mm
maka diambil nilai beff = 845,26 mm
b=845,26
hf=102,63
h=400
y1=348,945 hw=297,63
y2=148,815
bw=250
1 1
Ibalok4 = 12 . 3 + 1. 12 + 12 . 3 + 2. 22
1
= 12 845,26 102,633 + 86.749,03 92,4052
1
+ 250 297,633 + 74.407,5 107,7252
12
= 2229614611 mm4
1 1 1
Ipelat4 = . hf3 ( Lkanan + Lkiri)
12 2 2
1 1 1
= 12 x 102,633 ( 2 x 3000 + 2 x 3000)
= 270248315,4 mm4
4 2229614611 mm4
Maka nilai 4 = 4 = 270248315,4 = 8,25
mm4
+ + + ,+ ,+ ,+ ,
Maka nilai m = = = 15,915
Tebal pelat minimum untuk pelat dengan m > 2 dengan tebal pelat
minimum 8,25 mm. Sehingga tebal pelat 100 mm dapat dipergunakan.
c. Pembebanan Pelat
Arah x,
D eff = h P x
= 100 40 x 10 = 55 mm
Arah y,
D eff = h P - - x
= 100 40 10 x 10 = 45 mm
51
3000
5750
Ly = 5750 mm, WU = 4,781 KN/m
Lx = 3000 mm,
5750
= 3000= 1,91 = 1,9 < 2 (Pelat 2 arah)
2 3000 1250 2,4 4,781 Mulx = 0,001xWuxLx2x koef = 0,44 0,181 0,0047 258,5 10-300
Muly = 0,001xWuxLx2x koef = 0,12 0,074 0,0047 211,5 10-370
2
B Mutx = -0,001xWuxLx x koef = 0,62 0,256 0,0047 258,5 10-300
Muty = -0,001xWuxLx2x koef = 0,38 0,234 0,0047 211,5 10-370
Mutiy = 1/2 Mulx = 1/2 x 0,83 = 0,22 0,135 0,0047 211,5 10-370
47
48
3 4000 3000 1,3 4,781 Mulx = 0,001xWuxLx2x koef = 1,63 0,673 0,0047 258,5 10-300
Muly = 0,001xWuxLx2x koef = 0,86 0,530 0,0047 211,5 10-370
C Mutx = -0,001xWuxLx2x koef = 2,90 1,198 0,0047 258,5 10-300
Muty = -0,001xWuxLx2x koef = 2,34 1,444 0,0049 220,5 10-350
4 3000 3000 1,0 4,781 Mulx = 0,001xWuxLx2x koef = 1,07 0,442 0,0047 258,5 10-300
2
Mulx = 0,001xWuxLx x koef = 1,07 0,660 0,0047 211,5 10-370
D Mutx = -0,001xWuxLx2x koef = 2,19 0,904 0,0047 258,5 10-300
Muty = -0,001xWuxLx2x koef = 2,19 1,351 0,0047 211,5 10-370
5 4000 3500 1,1 4,781 Mulx = 0,001xWuxLx2x koef = 1,78 0,735 0,0047 258,5 10-300
Muly = 0,001xWuxLx2x koef = 1,61 0,993 0,0047 211,5 10-370
2
E Mutx = -0,001xWuxLx x koef = 3,68 1,520 0,0052 286 10-275
Muty = -0,001xWuxLx2x koef = 3,77 2,327 0,0081 364,5 10-215
Mutix = 1/2 Mulx = 1/2 x 0,83 =0,89 0,367 0,0047 258,5 10-300
49
6 4000 4000 1,0 4,781 Mulx = 0,001xWuxLx2x koef = 2,25 0,929 0,0047 258,5 10-300
Muly = 0,001xWuxLx2x koef = 1,79 1,104 0,0047 211,5 10-370
Mutx = -0,001xWuxLx2x koef = 4,36 1,801 0,0062 341 10-230
F Muty = -0,001xWuxLx2x koef = 4,01 2,475 0,0087 391,5 10-200
7 4000 3000 1,3 4,781 Mulx = 0,001xWuxLx2x koef = 1,63 0,673 0,0047 258,5 10-300
2
Muly = 0,001xWuxLx x koef = 0,86 0,530 0,0047 211,5 10-370
10-200
10-200
10-250
10-250
50
51