BACK UP DATA

PELEBARAN RUAS JALAN LANGORI BATU LAP

PEKERJAAN : PELEBARAN / CUTTINGAN RUAS JALAN LANGORI - BATU LAPPA

NO. KONTRAK : 8a/PU/PPK-PJDAU/APBD-P/SPK/XI/2017

PELAKSANA : CV. ARYA PERDANA

SUMBER DANA : DAU APBD-P T.A.2017

Rumus Sketsa

LA

Volume = Luas T
Trapesium x Jarak

LB L
LTOT

Jarak L Pelebaran
La Ltot Ltot Lb T
L La Lb
STA m (m) (m
rata2 rata2 rata2
(m) ) rata2 (m) (m)
x a b c d e f g=e-a h i
0 + 000 5.3 0.2 5.80 0.50 2.00
25 5.1 0.2 5.55 0.45
0 + 025 4.9 0.2 5.30 0.40 2.10
25 4.75 0.65 5.7 0.95
0 + 50 4.6 1.1 6.10 1.50 2.30
25 4.65 0.65 5.55 0.9
0 + 075 4.7 0.2 5.00 0.30 2.00
25 4.5 0.8 5.6 1.1
0 + 100 4.3 1.4 6.20 1.90 1.00
25 4.5 1.25 6.25 1.75
0 + 125 4.7 1.1 6.30 1.60 0.60
25 4.85 0.9 6.15 1.3
0 + 150 5 0.7 6.00 1.00 2.10
25 4.65 1.15 6.15 1.5
0 + 175 4.3 1.6 6.30 2.00 2.00
25 4.25 1.7 6.4 2.15
0 + 200 4.2 1.8 6.50 2.30 2.30
32 4.3 1.55 6.4 2.1
0 + 232 4.4 1.3 6.30 1.90 1.00
60 0 0 0 0
0 + 292 4 1.7 6.20 2.20 0.80
10 4.3 1.5 6.3 2
Rumus Sketsa

LA

Volume = Luas T
Trapesium x Jarak

LB L
LTOT

Jarak L Pelebaran
La Ltot Ltot Lb T
L La Lb
STA m (m) (m
rata2 rata2 rata2
(m) ) rata2 (m) (m)
x a b c d e f g=e-a h i
0 + 302 4.6 1.3 6.40 1.80 2.30
10 0 0 0 0
0 + 312 4.50 1.20 6.20 1.70 0.40
25 4.4 1.35 6.25 1.85
0 + 337 4.30 1.50 6.30 2.00 0.50
31 4.35 1.45 6.3 1.95
0 + 368 4.40 1.40 6.30 1.90 0.40
130 0 0 0 0
0 + 498 3.90 1.70 6.00 2.10 2.00
25 4.05 1.65 6.15 2.1
0 + 523 4.20 1.60 6.30 2.10 2.10
25 4.3 1.55 6.3 2
0 + 548 4.40 1.50 6.30 1.90 2.30
25 4.45 1.45 6.35 1.9
0 + 573 4.50 1.40 6.40 1.90 2.10
25 4.5 1.3 6.3 1.8
0 + 598 4.50 1.20 6.20 1.70 1.50
25 4.4 1.3 6.2 1.8
0 + 623 4.30 1.40 6.20 1.90 1.20
25 4.15 1.6 6.25 2.1
Rumus Sketsa

LA

Volume = Luas T
Trapesium x Jarak

LB L
LTOT

Jarak L Pelebaran
La Ltot Ltot Lb T
L La Lb
STA m (m) (m
rata2 rata2 rata2
(m) ) rata2 (m) (m)
x a b c d e f g=e-a h i
0 + 648 4.00 1.80 6.30 2.30 1.50
25 3.85 1.85 6.2 2.35
0 + 673 3.70 1.9 6.10 2.40 1.40
25 3.6 2.05 6.15 2.55
0 + 698 3.50 2.20 6.20 2.70 5.50
25 3.6 2.15 6.25 2.65
0 + 723 3.70 2.10 6.30 2.60 3.60
25 3.7 2.05 6.3 2.6
0 + 748 3.70 2.00 6.30 2.60 4.10
25 3.55 2.25 6.35 2.8
0 + 773 3.40 2.50 6.40 3.00 3.70
25 3.4 2.6 6.45 3.05
0 + 798 3.40 2.70 6.50 3.10 3.70
25 3.4 2.4 6.25 2.85
0 + 823 3.40 2.10 6.00 2.60 2.50
25 3.4 2.3 6.25 2.85
0 + 848 3.40 2.50 6.50 3.10 1.70
25 3.85 1.85 6.25 2.4
0 + 873 4.30 1.20 6.00 1.70 2.00
25 4.4 1.2 6.05 1.65
0 + 898 4.50 1.20 6.10 1.60 2.10
25 4.4 1.3 6.15 1.75
0 + 923 4.30 1.40 6.20 1.90 2.30
25 4.1 1.8 6.4 2.3
0 + 948 3.90 2.20 6.60 2.70 1.40
25 4.05 2 6.55 2.5
0 + 973 4.20 1.80 6.50 2.30 1.50
25 4.35 1.55 6.4 2.05
0 + 998 4.5 1.3 6.3 1.80 2
25 4.45 1.3 6.25 1.8
1 + 23 4.4 1.3 6.2 1.8 1.3
25 4.2 1.4 6.1 1.9
0 + 48 4 1.5 6 2.00 1.4
Rumus Sketsa

LA

Volume = Luas T
Trapesium x Jarak

LB L
LTOT

Jarak L Pelebaran
La Ltot Ltot Lb T
L La Lb
STA m (m) (m
rata2 rata2 rata2
(m) ) rata2 (m) (m)
x a b c d e f g=e-a h i
25 4.55 1.05 6.1 1.55
0 + 73 5.1 0.6 6.2 1.10 2
25 5.05 0.55 6.1 1.05
0 + 98 5 0.5 6 1.00 2.2
25 4.95 0.75 6.2 1.25
1 + 123 4.9 1 6.4 1.50 2.1
25 5.05 0.95 6.45 1.4
1 + 148 5.2 0.9 6.5 1.30 2
25 4.95 1.1 6.5 1.55
1 + 173 4.7 1.3 6.5 1.80 2.7
25 5 1 6.55 1.55
1 + 198 5.3 0.7 6.6 1.30 2.3
25 5.25 0.65 6.4 1.15
1 + 223 5.2 0.6 6.2 1.00 2.1
25 5 0.8 6.25 1.25
1 + 248 4.8 1 6.3 1.50 2.3
25 5.25 0.7 6.35 1.1
1 + 273 5.7 0.4 6.4 0.70 2
25 4.4 1 5.85 1.45
1 + 298 3.1 1.6 5.3 2.20 2.4
25 4.5 0.9 5.75 1.25
1 + 323 5.9 0.2 6.2 0.30 2.2
25 5.5 0.5 6.25 0.75
1 + 348 5.1 0.8 6.3 1.20 3.2
25 4.8 1.15 6.35 1.55
Rumus Sketsa

LA

Volume = Luas T
Trapesium x Jarak

LB L
LTOT

Jarak L Pelebaran
La Ltot Ltot Lb T
L La Lb
STA m (m) (m
rata2 rata2 rata2
(m) ) rata2 (m) (m)
x a b c d e f g=e-a h i
1 + 373 4.5 1.5 6.4 1.90 2
25 4.45 1.45 6.35 1.9
1 + 398 4.4 1.4 6.3 1.90 1.3
25 4.4 1.3 6.3 1.9
1 + 423 4.4 1.2 6.3 1.90 1.2
25 4.35 1.35 6.3 1.95
1 + 448 4.3 1.5 6.3 2.00 1.3
25 4.2 1.8 6.5 2.3
1 + 473 4.1 2.1 6.7 2.60 2
25 4.05 1.75 6.4 2.35
1 + 498 4 1.4 6.1 2.10 2.2
25 4.3 1.05 5.95 1.65
1 + 523 4.6 0.7 5.8 1.20 1.4
25 4.45 1.4 6.4 1.95
1 + 548 4.3 2.1 7 2.70 1.3
25 3.65 1.7 5.95 2.3
1 + 573 3 1.3 4.9 1.90 1.3
15 3.15 1.65 5.3 2.15
1 + 588 3.3 2 5.7 2.40 2
TOTAL

: Disetujui Oleh :Diperiksa Oleh


Pejabat Pembuat Komitmen ( PPK ) Konsultan Pengawas
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV. DUA PUTRA

.M.SYACHWAL M, S.T .HASRIANA, S.T


NIP. 19790824 200804 1 001 Site Engineer
BACK UP DATA
AS JALAN LANGORI BATU LAPPA

Sketsa

LA

LB L
LTOT

Pelebaran
Volume
T Luas
rata2 ( m2 ) Ket
( m3 )
j k=((d+h)/2)*j l=k.x
0.666 16.656 KANAN
2.05
1.760 44.000 KANAN
2.2
1.666 41.656 KANAN
2.15
1.425 35.625 KANAN
1.5
1.200 30.000 KANAN
0.8
1.485 37.125 KANAN
1.35
2.716 67.906 KANAN
2.05
4.139 103.469 KANAN
2.15
3.011 96.360 KANAN
1.65
Tidak ada
0.000 0.000
0 Cuttingan

2.713 27.125 KIRI


1.55
Sketsa

LA

LB L
LTOT

Pelebaran
Volume
T Luas
rata2 ( m2 ) Ket
( m3 )
j k=((d+h)/2)*j l=k.x
Tidak ada
0.000 0.000
0 Cuttingan

0.720 18.000 KIRI


0.45
0.765 23.715 KIRI
0.45
Tidak ada
0.000 0.000
0 Cuttingan

3.844 96.094 KANAN


2.05
3.905 97.625 KANAN
2.2
3.685 92.125 KANAN
2.2
2.790 69.750 KANAN
1.8
2.093 52.313 KANAN
1.35
2.498 62.438 KANAN
1.35
Sketsa

LA

LB L
LTOT

Pelebaran
Volume
T Luas
rata2 ( m2 ) Ket
( m3 )
j k=((d+h)/2)*j l=k.x
3.045 76.125 KANAN
1.45
7.935 198.375 KANAN
3.45
10.920 273.000 KANAN
4.55
8.951 223.781 KANAN
3.85
9.848 246.188 KANAN
3.9
10.453 261.313 KANAN
3.7
8.138 203.438 KANAN
3.1
5.408 135.188 KANAN
2.1
3.931 98.281 KANAN
1.85
2.921 73.031 KANAN
2.05
3.355 83.875 KANAN
2.2
3.793 94.813 KANAN
1.85
3.263 81.563 KANAN
1.45
3.150 78.750 KANAN
1.75
2.558 63.938 KANAN
1.65
2.228 55.688 KANAN
1.35
2.210 55.250 KANAN
Sketsa

LA

LB L
LTOT

Pelebaran
Volume
T Luas
rata2 ( m2 ) Ket
( m3 )
j k=((d+h)/2)*j l=k.x
2.210 55.250 KANAN
1.7
1.680 42.000 KANAN
2.1
2.150 53.750 KANAN
2.15
2.409 60.219 KANAN
2.05
3.114 77.844 KANAN
2.35
3.188 79.688 KANAN
2.5
1.980 49.500 KANAN
2.2
2.255 56.375 KANAN
2.2
1.935 48.375 KANAN
2.15
2.695 67.375 KANAN
2.2
2.473 61.813 KANAN
2.3
1.688 42.188 KANAN
2.7
3.510 87.750 KANAN
2.6
Sketsa

LA

LB L
LTOT

Pelebaran
Volume
T Luas
rata2 ( m2 ) Ket
( m3 )
j k=((d+h)/2)*j l=k.x
2.764 69.094 KANAN
1.65
2.000 50.000 KANAN
1.25
2.063 51.563 KANAN
1.25
3.383 84.563 KANAN
1.65
4.305 107.625 KANAN
2.1
2.430 60.750 KANAN
1.8
2.261 56.531 KANAN
1.35
2.600 65.000 KANAN
1.3

1.65 3.135 47.025 KANAN

4633.600 m3

:Diperiksa Oleh :Diajukan Oleh


Konsultan Pengawas Kontraktor Pelaksana
CV. DUA PUTRA CV. ARYA PERDANA

.HASRIANA, S.T VERAWATY KUDDUS, S.Si


Site Engineer Direktur