III PEK. POER PLAT DAN KOLOM PEDESTAL 125,916,683.56 7.039 4.657 2.258 6.915
A. POER PLAT
1 Type P-1
a Pek. Galian Tanah Biasa 74.56 M3 116,985.00 8,722,401.60 0.488 74.560 0.488 - - 74.560 0.488 100.000
b Pek. Urugan Pasir Bawah Pondasi 1.73 M3 350,317.00 606,048.41 0.034 1.730 0.034 - - 1.730 0.034 100.000
c Pak. Cor Lantai Kerja Tbl. 10 cm sp. 1:3:5 3.47 M3 1,326,729.71 4,603,752.10 0.257 3.470 0.257 - - 3.470 0.257 100.000
d Pas. Batako 21.60 M2 205,937.40 4,448,247.76 0.249 21.600 0.249 - - 21.600 0.249 100.000
e Cor Poer Plat Beton K-250 8.10 M3 2,015,962.95 16,329,299.88 0.913 - - 8.100 0.913 8.100 0.913 100.000
f Pembesian Dengan Besi Ulir 1,370.58 Kg 29,460.08 40,377,395.08 2.257 1,370.580 2.257 - - 1,370.580 2.257 100.000
g Urugan Kembali 26.10 M3 84,700.00 2,210,331.20 0.124 - - - - - - -
B. KOLOM PEDESTAL
1 PD-1
a Cor Kolom Pedestal Beton K-250 3.53 M3 2,015,962.95 7,116,349.21 0.398 - - 3.530 0.398 3.530 0.398 100.000
b Pembesian Dengan Besi Ulir 658.80 Kg 29,460.08 19,408,300.05 1.085 658.800 1.085 - - 658.800 1.085 100.000
c Pembesian Dengan Besi Polos 192.25 Kg 26,794.34 5,151,211.67 0.288 192.250 0.288 - - 192.250 0.288 100.000
d Bekisting Kolom Pedestal 40.32 M2 375,396.89 15,136,002.60 0.846 - - 40.320 0.846 40.320 0.846 100.000
e Bongkaran Bekisting 40.32 M2 44,825.00 1,807,344.00 0.101 - - 40.320 0.101 40.320 0.101 100.000
IV PEK. SLOOF, KOLOM, BALOK, PLAT LANTAI dan TANGGA 469,071,012.69 26.221 - 2.209 2.209
A. PEKERJAAN SLOOF BETON
1 Pek. Sloof Beton S-1
a Bekisting Sloof 7.04 M2 250,436.56 1,763,073.38 0.099 - - 7.040 0.099 7.040 0.099 100.000
b Bongkaran Bekisting 7.04 M2 44,825.00 315,568.00 0.018 - - - - - - -
c Cor Beton K-250 0.88 M3 2,015,962.95 1,774,047.39 0.099 - - - - - - -
d Pembesian Dengan Besi Ulir 89.11 Kg 29,460.08 2,625,187.64 0.147 - - 89.110 0.147 89.110 0.147 100.000
e Pembesian Dengan Besi Polos 46.27 Kg 26,794.34 1,239,774.07 0.069 - - 46.270 0.069 46.270 0.069 100.000
-
2 Pek. Sloof Beton S-2 -
a Bekisting Sloof 43.64 M2 250,436.56 10,929,051.48 0.611 - - 43.640 0.611 43.640 0.611 100.000
b Bongkaran Bekisting 43.64 M2 44,825.00 1,956,163.00 0.109 - - - - - - -
c Cor Beton K-250 4.36 M3 2,015,962.95 8,789,598.45 0.491 - - - - - - -
d Pembesian Dengan Besi Ulir 518.17 Kg 29,460.08 15,265,329.14 0.853 - - 518.170 0.853 518.170 0.853 100.000
e Pembesian Dengan Besi Polos 286.99 Kg 26,794.34 7,689,707.35 0.430 - - 286.990 0.430 286.990 0.430 100.000
-
B. PEKERJAAN KOLOM LANTAI - 1 -
1 Kolom K-1 -
a Cor Beton K-250 5.88 M3 2,015,962.95 11,853,862.13 0.663 - - - - - - -
b Pembesian Dengan Besi Ulir 737.86 Kg 29,460.08 21,737,413.89 1.215 - - - - - - -
c Pembesian Dengan Besi Polos 270.34 Kg 26,794.34 7,243,581.61 0.405 - - - - - - -
d Bekisting Kolom 67.20 M2 375,396.89 25,226,671.01 1.410 - - - - - - -
e Bongkaran Bekisting 67.20 M2 44,825.00 3,012,240.00 0.168 - - - - - - -
-
2 Kolom K-3 -
a Cor Beton K-250 0.16 M3 2,015,962.95 322,554.07 0.018 - - - - - - -
b Pembesian Dengan Besi Ulir 15.55 Kg 29,460.08 458,104.23 0.026 - - - - - - -
c Pembesian Dengan Besi Polos 9.56 Kg 26,794.34 256,153.88 0.014 - - - - - - -
d Bekisting Kolom 4.00 M2 375,396.89 1,501,587.56 0.084 - - - - - - -
e Bongkaran Bekisting 4.00 M2 44,825.00 179,300.00 0.010 - - - - - - -
-
3 Kolom Praktis 107.30 M' 155,798.55 16,717,184.48 0.934 - - - - - - -
-
C. PEKERJAAN KOLOM LANTAI - 2 -
1 Kolom K-1 -
KEMAJUAN PEKERJAAN BOBOT
HARGA SATUAN JUMLAH BOBOT THDP
NO. URAIAN VOLUME SAT MINGGU LALU MINGGU INI S/D MINGGU INI MASING -
MASING
( Rp. ) ( Rp. ) (%) Volume Bobot Volume Bobot Volume Bobot
PEKERJAAN
1 2 3 4 5 6 5 6 7=(6/4)X5 8 9=(8/4)X5 10=6+8 11=7+9 12=(10/4)X100