LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : XI (SEBELAS)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 05 Sept. - 11 Sept. 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 37.15
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 13.41
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 50.56

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 27.52 100.00 0.06 - - - 27.52 100.00 0.06
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 3.01 100.00 0.03 - - - 3.01 100.00 0.03
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 12.04 100.00 0.29 - - - 12.04 100.00 0.29
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 34.40 100.00 1.47 - - - 34.40 100.00 1.47
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - 78.40 100.00 0.43 78.40 100.00 0.43
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 48.99 100.00 0.13 - - - 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 9.94 100.00 0.03 - - - 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - 7.56 100.00 0.02 7.56 100.00 0.02
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - 5.94 100.00 0.01 5.94 100.00 0.01
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - 6.10 100.00 0.01 6.10 100.00 0.01
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - 1.78 100.00 0.00 1.78 100.00 0.00
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 3.02 100.00 0.03 - - - 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 0.86 100.00 0.01 - - - 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 1.51 100.00 0.06 - - - 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 0.43 100.00 0.02 - - - 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 10.80 100.00 0.87 - - - 10.80 100.00 0.87
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 3.00 100.00 0.24 - - - 3.00 100.00 0.24
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 7.76 100.00 0.62 - - - 7.76 100.00 0.62
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 4.38 100.00 0.35 - - - 4.38 100.00 0.35
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 6.46 100.00 0.52 - - - 6.46 100.00 0.52
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 1,542.13 100.00 1.74 - - - 1,542.13 100.00 1.74
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 457.32 100.00 0.52 - - - 457.32 100.00 0.52
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 973.73 100.00 1.10 - - - 973.73 100.00 1.10
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 594.77 100.00 0.67 - - - 594.77 100.00 0.67
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 439.86 100.00 0.50 - - - 439.86 100.00 0.50
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 39.60 100.00 0.19 - - - 39.60 100.00 0.19
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 12.00 100.00 0.06 - - - 12.00 100.00 0.06
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 77.60 100.00 0.39 - - - 77.60 100.00 0.39
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 58.46 100.00 0.30 - - - 58.46 100.00 0.30
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 61.45 100.00 0.31 - - - 61.45 100.00 0.31
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 15.12 100.00 0.01 - - - 15.12 100.00 0.01
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 4.32 100.00 0.00 - - - 4.32 100.00 0.00
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 100.72 100.00 0.69 - - - 100.72 100.00 0.69
SUB JUMLAH II 393,195,123.97 15.83 11.20 0.48 11.68
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 2.68 100.00 0.22 - - - 2.68 100.00 0.22
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 0.33 100.00 0.03 - - - 0.33 100.00 0.03
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 675.41 100.00 0.76 - - - 675.41 100.00 0.76
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 46.95 100.00 0.05 - - - 46.95 100.00 0.05
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 36.72 100.00 0.41 - - - 36.72 100.00 0.41
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 7.34 100.00 0.08 - - - 7.34 100.00 0.08
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 4,201.42 100.00 8.93 - - - 4,201.42 100.00 8.93
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 2,730.48 100.00 5.80 - - - 2,730.48 100.00 5.80
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 319.95 100.00 0.68 - - - 319.95 100.00 0.68
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 1,871.71 100.00 3.98 - - - 1,871.71 100.00 3.98
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - 2,056.60 100.00 4.37 2,056.60 100.00 4.37
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 95.98 100.00 0.20 - - - 95.98 100.00 0.20
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 4.37 100.00 0.01 - - - 4.37 100.00 0.01
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 30.72 100.00 0.07 - - - 30.72 100.00 0.07
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 32.40 100.00 0.07 - - - 32.40 100.00 0.07
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 190.84 100.00 0.41 - - - 190.84 100.00 0.41
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 2.10 100.00 0.00 - - - 2.10 100.00 0.00
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 173.95 100.00 0.37 - - - 173.95 100.00 0.37
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 175.80 100.00 0.37 - - - 175.80 100.00 0.37
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 72.91 100.00 0.15 - - - 72.91 100.00 0.15
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 217.04 100.00 0.46 - - - 217.04 100.00 0.46
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 12.56 100.00 0.03 - - - 12.56 100.00 0.03
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 96.00 100.00 0.11 - - - 96.00 100.00 0.11
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 288.00 100.00 0.17 - - - 288.00 100.00 0.17
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 112.00 100.00 0.05 - - - 112.00 100.00 0.05
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 141.86 100.00 0.13 - - - 141.86 100.00 0.13
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 99.11 100.00 0.09 - - - 99.11 100.00 0.09
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 44.16 100.00 0.09 - - - 44.16 100.00 0.09
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 23.72 4.37 28.09
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - 418.38 100.00 5.61 418.38 100.00 5.61
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - 897.65 100.00 0.85 897.65 100.00 0.85
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - 40.00 100.00 0.75 40.00 100.00 0.75
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - 6.00 100.00 0.07 6.00 100.00 0.07
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - 7.29 7.29
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - 180.13 50.00 1.27 180.13 50.00 1.27
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - 1.27 1.27
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 37.15 13.41 50.56

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : X (SEPULUH)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 29 Agust. - 04 Sept. 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 24.79
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 12.36
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 37.15

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 27.52 100.00 0.06 - - - 27.52 100.00 0.06
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 3.01 100.00 0.03 - - - 3.01 100.00 0.03
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 12.04 100.00 0.29 - - - 12.04 100.00 0.29
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 34.40 100.00 1.47 - - - 34.40 100.00 1.47
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 48.99 100.00 0.13 - - - 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 9.94 100.00 0.03 - - - 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 3.02 100.00 0.03 - - - 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 0.86 100.00 0.01 - - - 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 1.51 100.00 0.06 - - - 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 0.43 100.00 0.02 - - - 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 10.80 100.00 0.87 - - - 10.80 100.00 0.87
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 3.00 100.00 0.24 - - - 3.00 100.00 0.24
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 7.76 100.00 0.62 - - - 7.76 100.00 0.62
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 4.38 100.00 0.35 - - - 4.38 100.00 0.35
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 6.46 100.00 0.52 - - - 6.46 100.00 0.52
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 1,542.13 100.00 1.74 - - - 1,542.13 100.00 1.74
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 457.32 100.00 0.52 - - - 457.32 100.00 0.52
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 973.73 100.00 1.10 - - - 973.73 100.00 1.10
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 594.77 100.00 0.67 - - - 594.77 100.00 0.67
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 439.86 100.00 0.50 - - - 439.86 100.00 0.50
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 39.60 100.00 0.19 - - - 39.60 100.00 0.19
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 12.00 100.00 0.06 - - - 12.00 100.00 0.06
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 77.60 100.00 0.39 - - - 77.60 100.00 0.39
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 58.46 100.00 0.30 - - - 58.46 100.00 0.30
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 61.45 100.00 0.31 - - - 61.45 100.00 0.31
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 15.12 100.00 0.01 - - - 15.12 100.00 0.01
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 4.32 100.00 0.00 - - - 4.32 100.00 0.00
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 100.72 100.00 0.69 - - - 100.72 100.00 0.69
SUB JUMLAH II 393,195,123.97 15.83 11.20 - 11.20
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 2.68 100.00 0.22 - - - 2.68 100.00 0.22
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 0.33 100.00 0.03 - - - 0.33 100.00 0.03
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 675.41 100.00 0.76 - - - 675.41 100.00 0.76
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 46.95 100.00 0.05 - - - 46.95 100.00 0.05
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 36.72 100.00 0.41 - - - 36.72 100.00 0.41
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 7.34 100.00 0.08 - - - 7.34 100.00 0.08
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 4,201.42 100.00 8.93 - - - 4,201.42 100.00 8.93
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - 2,730.48 100.00 5.80 2,730.48 100.00 5.80
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 319.95 100.00 0.68 - - - 319.95 100.00 0.68
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - 1,871.71 100.00 3.98 1,871.71 100.00 3.98
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 95.98 100.00 0.20 - - - 95.98 100.00 0.20
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - 4.37 100.00 0.01 4.37 100.00 0.01
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - 30.72 100.00 0.07 30.72 100.00 0.07
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - 32.40 100.00 0.07 32.40 100.00 0.07
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - 190.84 100.00 0.41 190.84 100.00 0.41
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - 2.10 100.00 0.00 2.10 100.00 0.00
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - 173.95 100.00 0.37 173.95 100.00 0.37
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - 175.80 100.00 0.37 175.80 100.00 0.37
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - 72.91 100.00 0.15 72.91 100.00 0.15
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - 217.04 100.00 0.46 217.04 100.00 0.46
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - 12.56 100.00 0.03 12.56 100.00 0.03
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - 96.00 100.00 0.11 96.00 100.00 0.11
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - 288.00 100.00 0.17 288.00 100.00 0.17
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - 112.00 100.00 0.05 112.00 100.00 0.05
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - 141.86 100.00 0.13 141.86 100.00 0.13
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - 99.11 100.00 0.09 99.11 100.00 0.09
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - 44.16 100.00 0.09 44.16 100.00 0.09
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 11.36 12.36 23.72
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 24.79 12.36 37.15

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : IX (SEMBILAN)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 22 Agust. - 28 Agust. 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 14.25
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 10.55
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 24.79

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 27.52 100.00 0.06 - - - 27.52 100.00 0.06
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 3.01 100.00 0.03 - - - 3.01 100.00 0.03
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 12.04 100.00 0.29 - - - 12.04 100.00 0.29
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 34.40 100.00 1.47 - - - 34.40 100.00 1.47
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 48.99 100.00 0.13 - - - 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 9.94 100.00 0.03 - - - 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 3.02 100.00 0.03 - - - 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 0.86 100.00 0.01 - - - 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 1.51 100.00 0.06 - - - 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 0.43 100.00 0.02 - - - 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 10.80 100.00 0.87 - - - 10.80 100.00 0.87
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 3.00 100.00 0.24 - - - 3.00 100.00 0.24
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 7.76 100.00 0.62 - - - 7.76 100.00 0.62
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 4.38 100.00 0.35 - - - 4.38 100.00 0.35
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 6.46 100.00 0.52 - - - 6.46 100.00 0.52
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 1,542.13 100.00 1.74 - - - 1,542.13 100.00 1.74
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 457.32 100.00 0.52 - - - 457.32 100.00 0.52
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 973.73 100.00 1.10 - - - 973.73 100.00 1.10
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 594.77 100.00 0.67 - - - 594.77 100.00 0.67
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 439.86 100.00 0.50 - - - 439.86 100.00 0.50
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 39.60 100.00 0.19 - - - 39.60 100.00 0.19
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 12.00 100.00 0.06 - - - 12.00 100.00 0.06
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 77.60 100.00 0.39 - - - 77.60 100.00 0.39
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 58.46 100.00 0.30 - - - 58.46 100.00 0.30
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 61.45 100.00 0.31 - - - 61.45 100.00 0.31
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 15.12 100.00 0.01 - - - 15.12 100.00 0.01
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 4.32 100.00 0.00 - - - 4.32 100.00 0.00
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 100.72 100.00 0.69 - - - 100.72 100.00 0.69
SUB JUMLAH II 393,195,123.97 15.83 11.20 - 11.20
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - 2.68 100.00 0.22 2.68 100.00 0.22
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - 0.33 100.00 0.03 0.33 100.00 0.03
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 675.41 100.00 0.76 - - - 675.41 100.00 0.76
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 46.95 100.00 0.05 - - - 46.95 100.00 0.05
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - 36.72 100.00 0.41 36.72 100.00 0.41
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - 7.34 100.00 0.08 7.34 100.00 0.08
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - 4,201.42 100.00 8.93 4,201.42 100.00 8.93
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - 319.95 100.00 0.68 319.95 100.00 0.68
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - 95.98 100.00 0.20 95.98 100.00 0.20
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 0.81 10.55 11.36
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 14.25 10.55 24.79

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : VIII (DELAPAN)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 15 Agust. - 21 Agust. 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 12.75
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 1.50
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 14.25

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 27.52 100.00 0.06 - - - 27.52 100.00 0.06
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 3.01 100.00 0.03 - - - 3.01 100.00 0.03
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 12.04 100.00 0.29 - - - 12.04 100.00 0.29
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 34.40 100.00 1.47 - - - 34.40 100.00 1.47
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 48.99 100.00 0.13 - - - 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 9.94 100.00 0.03 - - - 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 3.02 100.00 0.03 - - - 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 0.86 100.00 0.01 - - - 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 1.51 100.00 0.06 - - - 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 0.43 100.00 0.02 - - - 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 10.80 100.00 0.87 - - - 10.80 100.00 0.87
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 3.00 100.00 0.24 - - - 3.00 100.00 0.24
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 7.76 100.00 0.62 - - - 7.76 100.00 0.62
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 4.38 100.00 0.35 - - - 4.38 100.00 0.35
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 6.46 100.00 0.52 - - - 6.46 100.00 0.52
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 1,542.13 100.00 1.74 - - - 1,542.13 100.00 1.74
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 457.32 100.00 0.52 - - - 457.32 100.00 0.52
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 973.73 100.00 1.10 - - - 973.73 100.00 1.10
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 594.77 100.00 0.67 - - - 594.77 100.00 0.67
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 439.86 100.00 0.50 - - - 439.86 100.00 0.50
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 39.60 100.00 0.19 - - - 39.60 100.00 0.19
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 12.00 100.00 0.06 - - - 12.00 100.00 0.06
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 77.60 100.00 0.39 - - - 77.60 100.00 0.39
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 58.46 100.00 0.30 - - - 58.46 100.00 0.30
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 61.45 100.00 0.31 - - - 61.45 100.00 0.31
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 15.12 100.00 0.01 - - - 15.12 100.00 0.01
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 4.32 100.00 0.00 - - - 4.32 100.00 0.00
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - 100.72 100.00 0.69 100.72 100.00 0.69
SUB JUMLAH II 393,195,123.97 15.83 10.52 0.69 11.20
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - 675.41 100.00 0.76 675.41 100.00 0.76
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - 46.95 100.00 0.05 46.95 100.00 0.05
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - 0.81 0.81
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 12.75 1.50 14.25

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : VII (TUJUH)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 08 Agust. - 14 Agust. 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 10.25
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 2.50
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 12.75

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 27.52 100.00 0.06 - - - 27.52 100.00 0.06
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 3.01 100.00 0.03 - - - 3.01 100.00 0.03
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 12.04 100.00 0.29 - - - 12.04 100.00 0.29
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 34.40 100.00 1.47 - - - 34.40 100.00 1.47
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 48.99 100.00 0.13 - - - 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 9.94 100.00 0.03 - - - 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 3.02 100.00 0.03 - - - 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 0.86 100.00 0.01 - - - 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 1.51 100.00 0.06 - - - 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 0.43 100.00 0.02 - - - 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 10.80 100.00 0.87 - - - 10.80 100.00 0.87
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 3.00 100.00 0.24 - - - 3.00 100.00 0.24
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 - - - 7.76 100.00 0.62 7.76 100.00 0.62
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 - - - 4.38 100.00 0.35 4.38 100.00 0.35
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 - - - 6.46 100.00 0.52 6.46 100.00 0.52
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 1,542.13 100.00 1.74 - - - 1,542.13 100.00 1.74
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 457.32 100.00 0.52 - - - 457.32 100.00 0.52
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 973.73 100.00 1.10 - - - 973.73 100.00 1.10
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 594.77 100.00 0.67 - - - 594.77 100.00 0.67
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 439.86 100.00 0.50 - - - 439.86 100.00 0.50
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 39.60 100.00 0.19 - - - 39.60 100.00 0.19
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 12.00 100.00 0.06 - - - 12.00 100.00 0.06
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 - - - 77.60 100.00 0.39 77.60 100.00 0.39
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 - - - 58.46 100.00 0.30 58.46 100.00 0.30
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 - - - 61.45 100.00 0.31 61.45 100.00 0.31
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 15.12 100.00 0.01 - - - 15.12 100.00 0.01
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 4.32 100.00 0.00 - - - 4.32 100.00 0.00
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - - - - - - -
SUB JUMLAH II 393,195,123.97 15.83 8.02 2.50 10.52
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - - - - - - -
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - - - - - - -
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - - -
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 10.25 2.50 12.75

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : VI (ENAM)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 01 Agust. - 07 Agust. 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 6.14
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 4.11
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 10.25

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 - - - 27.52 100.00 0.06 27.52 100.00 0.06
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 - - - 3.01 100.00 0.03 3.01 100.00 0.03
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 - - - 12.04 100.00 0.29 12.04 100.00 0.29
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 - - - 34.40 100.00 1.47 34.40 100.00 1.47
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 48.99 100.00 0.13 - - - 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 9.94 100.00 0.03 - - - 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 3.02 100.00 0.03 - - - 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 0.86 100.00 0.01 - - - 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 1.51 100.00 0.06 - - - 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 0.43 100.00 0.02 - - - 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 10.80 100.00 0.87 - - - 10.80 100.00 0.87
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 3.00 100.00 0.24 - - - 3.00 100.00 0.24
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 - - - - - - - - -
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 - - - - - - - - -
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 - - - - - - - - -
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 1,542.13 100.00 1.74 - - - 1,542.13 100.00 1.74
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 457.32 100.00 0.52 - - - 457.32 100.00 0.52
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 - - - 973.73 100.00 1.10 973.73 100.00 1.10
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 - - - 594.77 100.00 0.67 594.77 100.00 0.67
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 - - - 439.86 100.00 0.50 439.86 100.00 0.50
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 39.60 100.00 0.19 - - - 39.60 100.00 0.19
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 12.00 100.00 0.06 - - - 12.00 100.00 0.06
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 - - - - - - - - -
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 - - - - - - - - -
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 - - - - - - - - -
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 15.12 100.00 0.01 - - - 15.12 100.00 0.01
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 4.32 100.00 0.00 - - - 4.32 100.00 0.00
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - - - - - - -
SUB JUMLAH II 393,195,123.97 15.83 3.91 4.11 8.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - - - - - - -
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - - - - - - -
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - - -
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 6.14 4.11 10.25

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : V (LIMA)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 25 Juli - 31 Juli 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 2.51
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 3.63
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 6.14

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 - - - - - - - - -
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 - - - - - - - - -
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 - - - - - - - - -
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 - - - - - - - - -
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 48.99 100.00 0.13 - - - 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 9.94 100.00 0.03 - - - 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 3.02 100.00 0.03 - - - 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 0.86 100.00 0.01 - - - 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 1.51 100.00 0.06 - - - 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 0.43 100.00 0.02 - - - 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 - - - 10.80 100.00 0.87 10.80 100.00 0.87
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 - - - 3.00 100.00 0.24 3.00 100.00 0.24
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 - - - - - - - - -
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 - - - - - - - - -
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 - - - - - - - - -
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 - - - 1,542.13 100.00 1.74 1,542.13 100.00 1.74
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 - - - 457.32 100.00 0.52 457.32 100.00 0.52
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 - - - - - - - - -
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 - - - - - - - - -
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 - - - - - - - - -
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 - - - 39.60 100.00 0.19 39.60 100.00 0.19
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 - - - 12.00 100.00 0.06 12.00 100.00 0.06
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 - - - - - - - - -
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 - - - - - - - - -
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 - - - - - - - - -
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 - - - 15.12 100.00 0.01 15.12 100.00 0.01
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 - - - 4.32 100.00 0.00 4.32 100.00 0.00
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - - - - - - -
SUB JUMLAH II 393,195,123.97 15.83 0.28 3.63 3.91
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - - - - - - -
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - - - - - - -
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - - -
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 2.51 3.63 6.14

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : IV (EMPAT)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 18 Juli - 24 Juli 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : 2.23
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 0.28
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 2.51

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 101.00 100.00 0.26 - - - 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 1.00 100.00 0.01 - - - 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 16.00 100.00 1.19 - - - 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 1.00 100.00 0.77 - - - 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 2.23 - 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 - - - - - - - - -
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 - - - - - - - - -
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 - - - - - - - - -
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 - - - - - - - - -
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 - - - 48.99 100.00 0.13 48.99 100.00 0.13
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 - - - 9.94 100.00 0.03 9.94 100.00 0.03
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 - - - 3.02 100.00 0.03 3.02 100.00 0.03
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 - - - 0.86 100.00 0.01 0.86 100.00 0.01
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 - - - 1.51 100.00 0.06 1.51 100.00 0.06
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 - - - 0.43 100.00 0.02 0.43 100.00 0.02
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 - - - - - - - - -
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 - - - - - - - - -
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 - - - - - - - - -
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 - - - - - - - - -
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 - - - - - - - - -
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 - - - - - - - - -
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 - - - - - - - - -
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 - - - - - - - - -
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 - - - - - - - - -
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 - - - - - - - - -
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 - - - - - - - - -
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 - - - - - - - - -
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 - - - - - - - - -
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - - - - - - -
SUB JUMLAH II 393,195,123.97 15.83 - 0.28 0.28
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - - - - - - -
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - - - - - - -
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - - -
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 2.23 0.28 2.51

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : III (TIGA)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 11 Juli - 17 Juli 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : -
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : 2.23
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : 2.23

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 - - - 101.00 100.00 0.26 101.00 100.00 0.26
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 - - - 1.00 100.00 0.01 1.00 100.00 0.01
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 - - - 16.00 100.00 1.19 16.00 100.00 1.19
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 - - - 1.00 100.00 0.77 1.00 100.00 0.77
SUB JUMLAH I 55,459,131.08 2.23 - 2.23 2.23
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 - - - - - - - - -
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 - - - - - - - - -
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 - - - - - - - - -
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 - - - - - - - - -
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 - - - - - - - - -
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 - - - - - - - - -
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 - - - - - - - - -
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 - - - - - - - - -
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 - - - - - - - - -
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 - - - - - - - - -
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 - - - - - - - - -
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 - - - - - - - - -
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 - - - - - - - - -
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 - - - - - - - - -
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 - - - - - - - - -
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 - - - - - - - - -
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 - - - - - - - - -
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 - - - - - - - - -
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 - - - - - - - - -
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - - - - - - -
SUB JUMLAH II 393,195,123.97 15.83 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - - - - - - -
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - - - - - - -
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - - -
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 - 2.23 2.23

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : II (DUA)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 04 Juli - 10 Juli 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : -
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : -
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : -

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 - - - - - - - - -
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 - - - - - - - - -
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 - - - - - - - - -
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 - - - - - - - - -
SUB JUMLAH I 55,459,131.08 2.23 - - -
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 - - - - - - - - -
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 - - - - - - - - -
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 - - - - - - - - -
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 - - - - - - - - -
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 - - - - - - - - -
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 - - - - - - - - -
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 - - - - - - - - -
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 - - - - - - - - -
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 - - - - - - - - -
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 - - - - - - - - -
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 - - - - - - - - -
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 - - - - - - - - -
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 - - - - - - - - -
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 - - - - - - - - -
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 - - - - - - - - -
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 - - - - - - - - -
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 - - - - - - - - -
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 - - - - - - - - -
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 - - - - - - - - -
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - - - - - - -
SUB JUMLAH II 393,195,123.97 15.83 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - - - - - - -
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - - - - - - -
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - - -
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 - - -

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PERDAGANGAN KONTRAKTOR PELAKSANA : CV. MATAHARI MINGGU KE : I (SATU)
PEKERJAAN : PEMBANGUNAN PASAR RAKYAT BENDE NOMOR KONTRAK : 01/KONTRAK/TP-APBN/DPP/VII/2022 TANGGAL LAPORAN : 01 Juli - 03 Juli 2021
LOKASI : KEL. BENDE KEC. MOTUI KAB. KONAWE UTARA NILAI KONTRAK : Rp. 2.757.693.000,00 BOBOT S/D MINGGU LALU : -
TAHUN ANGGARAN : 2022 TANGGAL KONTRAK : 01 Juli 2022 BOBOT MINGGU INI : -
SUMBER DANA : TP-APBN KONSULTAN PENGAWAS : CV. GEOMETRI ENG. CONSULTAN BOBOT S/D MINGGU INI : -

KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
I PEKERJAAN PENDAHULUAN
1.Pengukuran dan pemasangan bowplank m1 101.00 62,905.64 6,353,469.64 0.26 - - - - - - - - -
2.Pemasangan papan nama proyek ls 1.00 223,000.00 223,000.00 0.01 - - - - - - - - -
3.Pembuatan direksi keet / kantor sementara m2 16.00 1,852,041.34 29,632,661.44 1.19 - - - - - - - - -
4.Kesehatan dan Keselamatan Kerja Ls 1.00 19,250,000.00 19,250,000.00 0.77 - - - - - - - - -
SUB JUMLAH I 55,459,131.08 2.23 - - -
II PEKERJAAN TANAH DAN STRUKTUR BAWAH
II.1 PONDASI
A. Pekerjaan Pondasi Keliling Bangunan
1. Pekerjaan galian tanah pondasi m3 27.52 50,960.00 1,402,419.20 0.06 - - - - - - - - -
2. Pekerjaan urugan pasir bawah pondasi m3 3.01 269,500.00 811,195.00 0.03 - - - - - - - - -
3. Pekerjaan pasangan pondasi batu kosong m3 12.04 590,866.50 7,114,032.66 0.29 - - - - - - - - -
4. pekerjaan pasangan pondasi m3 34.40 1,058,743.00 36,420,759.20 1.47 - - - - - - - - -
B. Pekerjaan Pondasi Rolag Pada Meja Los
1. Pondasi rollag bata m2 78.40 136,800.00 10,725,120.00 0.43 - - - - - - - - -
los
II.2 STRUKTUR BAWAH
A. Pekerjaan galian tanah
manual
1. Pile Cap 1 (pondasi 1) m3 48.99 66,894.80 3,277,176.25 0.13 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 9.94 66,894.80 664,934.31 0.03 - - - - - - - - -
3. Rollag Meja Hamparan A m3 7.56 50,960.00 385,257.60 0.02 - - - - - - - - -
4. Rollag Meja Hamparan B m3 5.94 50,960.00 302,702.40 0.01 - - - - - - - - -
5. Rollag Los A m3 6.10 50,960.00 310,856.00 0.01 - - - - - - - - -
6. Rollag Los B m3 1.78 50,960.00 90,708.80 0.00 - - - - - - - - -
B. Urugan Pasir
1. Pile Cap 1 (pondasi 1) m3 3.02 269,500.00 813,890.00 0.03 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 0.86 269,500.00 231,770.00 0.01 - - - - - - - - -
3. pasir urug bawah rabat m3 49.32 269,500.00 13,291,740.00 0.54 - - - - - - - - -
4. Pasir urug bawah los m3 30.62 269,500.00 8,252,090.00 0.33 - - - - - - - - -
C. Lantai kerja (beton B-0)
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 1.51 1,034,659.50 1,562,335.85 0.06 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 0.43 1,034,659.50 444,903.59 0.02 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
D. Beton K-300 :
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 10.80 1,998,073.00 21,579,188.40 0.87 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 3.00 1,998,073.00 5,994,219.00 0.24 - - - - - - - - -
b. Sloof
1. Sloof 1 m3 7.76 1,998,073.00 15,505,046.48 0.62 - - - - - - - - -
2. Sloof 2 m3 4.38 1,998,073.00 8,751,559.74 0.35 - - - - - - - - -
3. Sloof 3 m3 6.46 1,998,073.00 12,907,551.58 0.52 - - - - - - - - -
E. Beton K-200 :
1. Lantai parit keliling m3 2.06 1,783,796.00 3,674,619.76 0.15 - - - - - - - - -
2. tutup parit keliling m3 2.58 1,783,796.00 4,602,193.68 0.19 - - - - - - - - -
3. Rabat beton untuk lantai m3 38.82 1,783,796.00 69,246,960.72 2.79 - - - - - - - - -
4. ramp m3 0.17 1,783,796.00 303,245.32 0.01 - - - - - - - - -
F. Pembesian
a. Pile Cap
1. Pile Cap 1 (pondasi 1) kg 1,542.13 28,011.58 43,197,497.87 1.74 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) kg 457.32 28,011.58 12,810,255.77 0.52 - - - - - - - - -
b. Sloof
1. Sloof 1 kg 973.73 28,011.58 27,275,715.79 1.10 - - - - - - - - -
2. Sloof 2 kg 594.77 28,011.58 16,660,447.44 0.67 - - - - - - - - -
3. Sloof 3 kg 439.86 28,011.58 12,321,173.58 0.50 - - - - - - - - -
c. Parit
1. Tutup parit kg 132.01 28,011.58 3,697,808.68 0.15 - - - - - - - - -
G. Bekesting Halus
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m2 39.60 118,131.16 4,677,993.94 0.19 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m2 12.00 118,131.16 1,417,573.92 0.06 - - - - - - - - -
b. Sloof
1. Sloof 1 m2 77.60 126,347.48 9,804,564.45 0.39 - - - - - - - - -
2. Sloof 2 m2 58.46 126,347.48 7,386,273.68 0.30 - - - - - - - - -
3. Sloof 3 m2 61.45 126,347.48 7,764,052.65 0.31 - - - - - - - - -
H. Tanah Urug
a. Pile Cap
1. Pile Cap 1 (pondasi 1) m3 15.12 24,421.60 369,254.59 0.01 - - - - - - - - -
2. Pile Cap 2 (pondasi 2) m3 4.32 24,421.60 105,501.31 0.00 - - - - - - - - -
b. peninggian elevasi
1. Tanah urug bawah lantai m3 100.72 169,187.20 17,040,534.78 0.69 - - - - - - - - -
SUB JUMLAH II 393,195,123.97 15.83 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III PEKERJAAN STRUKTUR TENGAH
III.1 PEKERJAAN STRUKTUR BETON
A PEKERJAAN BETON
a. kolom
1. Tipe kolom (K1) m3 2.68 1,998,073.00 5,354,835.64 0.22 - - - - - - - - -
2. Tipe kolom (K2) m3 0.33 1,954,708.00 645,053.64 0.03 - - - - - - - - -
3. Tipe kolom (KP) m3 2.27 1,954,708.00 4,437,187.16 0.18 - - - - - - - - -
b. Ring balok
1. Ring Balk 2 m3 1.52 1,783,796.00 2,711,369.92 0.11 - - - - - - - - -
2. Balok Letiu m3 0.36 1,783,796.00 642,166.56 0.03 - - - - - - - - -
c. Plat beton
1. Dak beton main gate depan m3 0.40 1,783,796.00 713,518.40 0.03 - - - - - - - - -
d. Plat beton meja los
1. Los Model A m3 0.91 1,783,796.00 1,623,254.36 0.07 - - - - - - - - -
2. Los Model B m3 0.68 1,783,796.00 1,212,981.28 0.05 - - - - - - - - -
e. kolom beton meja los
1. Los m3 1.08 1,783,796.00 1,926,499.68 0.08 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m3 0.69 1,783,796.00 1,230,819.24 0.05 - - - - - - - - -
2. dinding beton septicktank m3 2.41 1,783,796.00 4,298,948.36 0.17 - - - - - - - - -
B PEKERJAAN PEMBESIAN
a. Kolom Struktur
1. Tipe kolom (K1) kg 675.41 28,011.58 18,919,301.25 0.76 - - - - - - - - -
2. Tipe kolom (K2) kg 46.95 28,011.58 1,315,143.68 0.05 - - - - - - - - -
3. Tipe kolom (KP) kg 397.47 28,011.58 11,133,762.70 0.45 - - - - - - - - -
b. ring balok
1. Ring Balk 2 kg 122.92 28,011.58 3,443,183.41 0.14 - - - - - - - - -
2. Balok Letiu kg 144.81 28,011.58 4,056,356.90 0.16 - - - - - - - - -
c. plat beton
1. Dak beton main gate depan kg 12.28 28,011.58 343,982.20 0.01 - - - - - - - - -
d. Plat meja beton los
1. Los Model A kg 35.37 28,011.58 990,769.58 0.04 - - - - - - - - -
2. Los Model B kg 26.52 28,011.58 742,867.10 0.03 - - - - - - - - -
e. kolom beton meja los
1. Los kg 458.38 28,011.58 12,839,948.04 0.52 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap kg 21.21 28,011.58 594,125.61 0.02 - - - - - - - - -
2. dinding beton septicktank kg 58.02 28,011.58 1,625,231.87 0.07 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
C PEKERJAAN BEKISTING
a. Kolom Struktur
1. Tipe kolom (K1) m2 36.72 278,683.13 10,233,244.53 0.41 - - - - - - - - -
2. Tipe kolom (K2) m2 7.34 278,683.13 2,045,534.17 0.08 - - - - - - - - -
3. Tipe kolom (KP) m2 50.70 278,683.13 14,129,234.69 0.57 - - - - - - - - -
b. Ring Balk
1. Ring Balk 2 m2 10.26 286,481.93 2,939,304.60 0.12 - - - - - - - - -
2. Balok Letiu m2 12.24 286,481.93 3,506,538.82 0.14 - - - - - - - - -
c. Plat Beton
1. Dak beton main gate depan m2 4.00 355,698.90 1,422,795.60 0.06 - - - - - - - - -
d. Plat meja beton los
1. Los Model A m2 12.00 355,698.90 4,268,386.80 0.17 - - - - - - - - -
2. Los Model B m2 9.00 355,698.90 3,201,290.10 0.13 - - - - - - - - -
e. kolom beton meja los
1. Los m2 13.65 278,683.13 3,804,024.72 0.15 - - - - - - - - -
f. bak kontrol dan bak penampungan
1. dinding beton grease trap m2 5.64 278,683.13 1,571,772.85 0.06 - - - - - - - - -
2. dinding beton septicktank m2 22.95 278,683.13 6,395,777.83 0.26 - - - - - - - - -
III.2 PEKERJAAN STRUKTUR BAJA KONVENSIONAL
a. Struktur utama
1. Kolom Struktur K1 kg 4,201.42 52,782.80 221,762,711.58 8.93 - - - - - - - - -
2. Kuda kuda baja kg 2,730.48 52,782.80 144,122,379.74 5.80 - - - - - - - - -
3. konsol teritisan kg 319.95 52,782.80 16,887,856.86 0.68 - - - - - - - - -
4. ring balok 3 kg 1,871.71 52,782.80 98,794,094.59 3.98 - - - - - - - - -
5. gording kanal C kg 2,056.60 52,782.80 108,553,106.48 4.37 - - - - - - - - -
b. asesoris Struktur pendukung
1. Rip 1 (plat buhul) kg 95.98 52,782.80 5,066,093.14 0.20 - - - - - - - - -
2. Rip 2 (plat buhul) kg 4.37 52,782.80 230,660.84 0.01 - - - - - - - - -
3. Rip 3 (plat buhul) kg 30.72 52,782.80 1,621,487.62 0.07 - - - - - - - - -
4. Rip 4 (plat buhul) kg 32.40 52,782.80 1,710,162.72 0.07 - - - - - - - - -
5. Rip 5 (plat buhul) kg 190.84 52,782.80 10,073,069.55 0.41 - - - - - - - - -
6. Rip 6 (plat buhul) kg 2.10 52,782.80 110,843.88 0.00 - - - - - - - - -
7. Rip 7 (plat buhul) kg 173.95 52,782.80 9,181,568.06 0.37 - - - - - - - - -
8. Endplate 1 kg 175.80 52,782.80 9,279,216.24 0.37 - - - - - - - - -
9. Endplate 2 kg 72.91 52,782.80 3,848,393.95 0.15 - - - - - - - - -
10. Endplate 3 kg 217.04 52,782.80 11,455,978.91 0.46 - - - - - - - - -
11. Endplate 4 kg 12.56 52,782.80 662,951.97 0.03 - - - - - - - - -
12. Angkur baut bh 96.00 27,500.00 2,640,000.00 0.11 - - - - - - - - -
13. Baut 19 bh 288.00 15,000.00 4,320,000.00 0.17 - - - - - - - - -
14. Baut 16 bh 112.00 10,000.00 1,120,000.00 0.05 - - - - - - - - -
15. Trackstank kg 141.86 22,900.00 3,248,594.00 0.13 - - - - - - - - -
16. Kait angin kg 99.11 22,900.00 2,269,619.00 0.09 - - - - - - - - -
17. Dudukan Gording kg 44.16 52,782.80 2,330,888.45 0.09 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
III.3 PEKERJAAN STRUKTUR BAJA RINGAN
1. kuda-kuda 1 m2 37.60 345,881.20 13,005,133.12 0.52 - - - - - - - - -
SUB JUMLAH III 806,614,022.02 32.47 - - -
IV PEKERJAAN ATAP, TALANG DAN LISTPLANK
a. Penutup atap
1. Atap utama m2 418.38 333,151.00 139,383,715.38 5.61 - - - - - - - - -
2. Atap sky light m2 95.12 447,811.00 42,595,782.32 1.71 - - - - - - - - -
3. Atap main gate m2 36.48 333,151.00 12,153,348.48 0.49 - - - - - - - - -
b. Bubungan
1. Nok atap main gate m1 4.40 269,451.00 1,185,584.40 0.05 - - - - - - - - -
2. Bubungan rabat m3 0.75 1,034,659.50 775,994.63 0.03 - - - - - - - - -
c. Talang
1. Rangka talang atap utama kg 897.65 23,600.00 21,184,540.00 0.85 - - - - - - - - -
2. Plat talang atap utama m2 40.00 466,600.00 18,664,000.00 0.75 - - - - - - - - -
3. Roof drain unit 6.00 306,400.00 1,838,400.00 0.07 - - - - - - - - -
d. Listplank
1. Listplank atap teritisan GRC lebar 20cm m1 96.00 124,558.00 11,957,568.00 0.48 - - - - - - - - -
2. Listplank teritisan GRC lebar 15cm m1 96.00 116,718.00 11,204,928.00 0.45 - - - - - - - - -
3. Listplank atap main gate GRC lebar 20cm m1 9.60 124,558.00 1,195,756.80 0.05 - - - - - - - - -
4. Listplank main gate GRC lebar 15cm m1 9.60 116,718.00 1,120,492.80 0.05 - - - - - - - - -
SUB JUMLAH IV 263,260,110.81 10.60 - - -
V PEKERJAAN DINDING
Pekerjaan dinding bata
1. Dinding bata bangunan utama m2 360.25 175,542.50 63,239,185.63 2.55 - - - - - - - - -
2. Dinding bata meja los m2 96.77 175,542.50 16,987,247.73 0.68 - - - - - - - - -
3. Dinding bata parit m2 75.20 175,542.50 13,200,796.00 0.53 - - - - - - - - -
4. Dinding bata tangga dan balkon m2 3.76 175,542.50 660,039.80 0.03 - - - - - - - - -
5. Dinding bata trasram m2 38.70 175,542.50 6,793,494.75 0.27 - - - - - - - - -
6. Dinding roster m2 38.40 1,064,730.80 40,885,662.72 1.65 - - - - - - - - -
SUB JUMLAH V 141,766,426.62 5.71 - - -
VI PEKERJAAN PELAPIS DINDING
a. Plaster aci
1. Dinding bata bangunan utama m2 720.50 62,979.70 45,376,873.85 1.83 - - - - - - - - -
2. dinding bata parit m2 150.40 68,589.22 10,315,818.69 0.42 - - - - - - - - -
3. kolom teras termasuk skoneng m2 14.16 62,979.70 891,792.55 0.04 - - - - - - - - -
b. Pekerjaan keramik dinding
1. Keramik dinding toilet m2 52.08 194,466.30 10,127,804.90 0.41 - - - - - - - - -
2. Keramik dinding meja los m2 123.40 194,466.30 23,997,141.42 0.97 - - - - - - - - -
SUB JUMLAH VI 90,709,431.41 3.65 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
VII PEKERJAAN PELAPIS LANTAI
a. Keramik
1. Keramik selasar pasar m2 193.65 214,960.55 41,627,110.51 1.68 - - - - - - - - -
2. Keramik los termasuk meja Hamparan m2 149.13 214,960.55 32,057,066.82 1.29 - - - - - - - - -
3. Keramik selasar depan m2 42.21 214,960.55 9,073,484.82 0.37 - - - - - - - - -
4. keramik ruang pengelola m2 8.12 214,960.55 1,745,479.67 0.07 - - - - - - - - -
5. keramik ruang keamanan m2 4.56 214,960.55 980,220.11 0.04 - - - - - - - - -
6. keramik ruang kesehatan m2 5.28 214,960.55 1,134,991.70 0.05 - - - - - - - - -
7. keramik toilet m2 16.25 214,960.55 3,493,108.94 0.14 - - - - - - - - -
8. keramik ruang tera m2 2.31 214,960.55 496,558.87 0.02 - - - - - - - - -
9. keramik kios m2 62.28 214,960.55 13,387,743.05 0.54 - - - - - - - - -
b. tali air
1. Pembuatan tali air selasar samping dan belakang m2 104.30 24,412.72 2,546,246.70 0.10 - - - - - - - - -
SUB JUMLAH VII 106,542,011.18 4.29 - - -
VIII PEKERJAAN PENGECATAN
a. Pengecatan area luar
1. Pengecatan dinding bangunan utama m2 177.07 31,396.75 5,559,422.52 0.22 - - - - - - - - -
2. Pengecatan kolom selasar m2 14.64 31,396.75 459,648.42 0.02 - - - - - - - - -
3. Pengecatan listplank atap teritisan GRC lebar 20cm m2 31.50 31,396.75 988,997.63 0.04 - - - - - - - - -
4. Pengecatan listplank atap main gate GRC lebar 20cm m2 5.04 31,396.75 158,239.62 0.01 - - - - - - - - -
5. Pengecatan dinding roster m2 38.40 31,396.75 1,205,635.20 0.05 - - - - - - - - -
b. Pengecatan area dalam
1. Pengecatan dinding bagian dalam pasar m2 300.81 28,848.75 8,677,992.49 0.35 - - - - - - - - -
2. Pengecatan dinding bagian dalam kios m2 239.80 28,848.75 6,917,930.25 0.28 - - - - - - - - -
3. Pengecatan dinding bagian dalam ruang Pengelola m2 28.09 28,848.75 810,361.39 0.03 - - - - - - - - -
4. Pengecatan dinding bagian dalam ruang Pos Jaga m2 22.15 28,848.75 638,999.81 0.03 - - - - - - - - -
5. Pengecatan dinding bagian dalam ruang Kesehatan m2 23.26 28,848.75 671,021.93 0.03 - - - - - - - - -
6. Pengecatan dinding bagian dalam ruang mushola m2 34.24 28,848.75 987,781.20 0.04 - - - - - - - - -
7. Pengecatan dinding bagian dalam ruang toilet m2 34.20 28,848.75 986,627.25 0.04 - - - - - - - - -
8. Pengecatan dinding bagian dalam ruang tera ulang m2 17.65 28,848.75 509,180.44 0.02 - - - - - - - - -
c. Pengecatan Plafond
1. Pengecatan Plafond Kios m2 75.53 28,848.75 2,178,946.09 0.09 - - - - - - - - -
2. Pengecatan Plafond Ruang Pengelola m2 8.12 28,848.75 234,251.85 0.01 - - - - - - - - -
3. Pengecatan Plafond ruang Pos Jaga m2 4.56 28,848.75 131,550.30 0.01 - - - - - - - - -
4. Pengecatan Plafond ruang Kesehatan m2 5.27 28,848.75 152,032.91 0.01 - - - - - - - - -
5. Pengecatan Plafond ruang toilet m2 16.25 28,848.75 468,792.19 0.02 - - - - - - - - -
6. Pengecatan Plafond ruang toilet m2 69.42 28,848.75 2,002,680.23 0.08 - - - - - - - - -
c. Pengecatan bidang besi
1. pengecatan teralis besi pengaman pipa air hujan m2 10.80 43,913.80 474,269.04 0.02 - - - - - - - - -
2. pengecatan besi grill los m2 4.00 43,913.80 175,655.20 0.01 - - - - - - - - -
3. pengecatan besi siku support kabel tray unit 21.00 43,913.80 922,189.80 0.04 - - - - - - - - -
4. pengecatan besi beton longdrat support kabel tray unit 16.00 43,913.80 702,620.80 0.03 - - - - - - - - -
SUB JUMLAH VIII 36,014,826.54 1.45 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
IX PEKERJAAN KUSEN
1. Rolling door kios Lebar 3 m m2 42.14 2,556,697.50 107,739,232.65 4.34 - - - - - - - - -
2. Rolling door kios Lebar 2 m m2 12.47 2,556,697.50 31,882,017.83 1.28 - - - - - - - - -
3. Pintu jendela 1 (PJ1)
- Kusen aluminium natural 3" m2 5.68 885,405.50 5,029,103.24 0.20 - - - - - - - - -
- Kaca bening 5mm m2 3.08 214,889.50 661,859.66 0.03 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
4. pintu jendela 2 (PJ2)
- Kusen aluminium natural 3" m2 3.76 885,405.50 3,329,124.68 0.13 - - - - - - - - -
- Kaca bening 5mm m2 1.54 214,889.50 330,929.83 0.01 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.68 3,165,522.50 5,318,077.80 0.21 - - - - - - - - -
5. Pintu 1 (P1)
- Kusen aluminium natural 3" m2 2.26 885,405.50 2,001,016.43 0.08 - - - - - - - - -
- Kaca bening 5mm m2 0.24 214,889.50 51,573.48 0.00 - - - - - - - - -
- Daun pintu aluminium kaca aluminium m2 1.74 3,165,522.50 5,508,009.15 0.22 - - - - - - - - -
Pintu toilet (PT1)
- Kusen aluminium natural 3" m2 15.38 885,405.50 13,617,536.59 0.55 - - - - - - - - -
- Daun pintu almunium sudah termasuk grill m2 11.76 2,310,000.00 27,165,600.00 1.09 - - - - - - - - -
SUB JUMLAH IX 207,952,159.14 8.37 - - -
X PEKERJAAN KUNCI, ENGSEL DAN ASESORIS KUSEN
a. Pintu jendela 1 (PJ1)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
merk solid
2. engsel kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
b. pintu jendela 2 (PJ2)
1. kunci slot tanam unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. merk
engselsolid
kupuatau unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
solid closer
4. door atau setara unit 1.00 2,397,129.00 2,397,129.00 0.10 - - - - - - - - -
c. Pintu 1 (P1)
1. kunci slot tanam merk solid atau setara unit 1.00 207,025.00 207,025.00 0.01 - - - - - - - - -
2. engsel kupu unit 3.00 99,886.50 299,659.50 0.01 - - - - - - - - -
3. handle pintu merk solid atau setara unit 1.00 210,445.00 210,445.00 0.01 - - - - - - - - -
d. Pintu toilet (PT1)
1. kunci slot tanam unit 5.00 207,025.00 1,035,125.00 0.04 - - - - - - - - -
merk solid
2. engsel kupuatau unit 15.00 99,886.50 1,498,297.50 0.06 - - - - - - - - -
3. handle pintu merk unit 5.00 210,445.00 1,052,225.00 0.04 - - - - - - - - -
solid atau setara SUB JUMLAH X 10,531,294.00 0.42 - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XI PEKERJAAN PLAFOND DAN LANGT-LANGIT
1. plafon selasar depan m2 69.42 198,822.40 13,802,251.01 0.56 - - - - - - - - -
2. plafon ruang pengelola m2 8.12 198,822.40 1,614,437.89 0.06 - - - - - - - - -
3. plafon ruang Pos Jaga m2 4.56 198,822.40 906,630.14 0.04 - - - - - - - - -
4. plafon ruang Kesehatan m2 5.27 198,822.40 1,047,794.05 0.04 - - - - - - - - -
5. plafon ruang Tera m2 2.50 198,822.40 497,056.00 0.02 - - - - - - - - -
6. plafon kios m2 62.28 198,822.40 12,382,659.07 0.50 - - - - - - - - -
7. plafon toilet m2 16.25 198,822.40 3,230,864.00 0.13 - - - - - - - - -
SUB JUMLAH XI 33,481,692.16 1.35 - - -
XII PEKERJAAN LAIN-LAIN
1. Plat nama pasar (signage) tampak depan cm2 600.00 15,000.00 9,000,000.00 0.36 - - - - - - - - -
2. logo pasar signage Bh 3.00 635,000.00 1,905,000.00 0.08 - - - - - - - - -
3. teralis pengaman pipa air hujan kg 66.40 27,000.00 1,792,800.00 0.07 - - - - - - - - -
4. support gantung untuk pipa air hujan kg 11.17 27,000.00 301,590.00 0.01 - - - - - - - - -
5. pipa display los m1 37.00 174,650.00 6,462,050.00 0.26 - - - - - - - - -
6.. Pembuatan dan pengadaan box filter grease trap unit 2.00 1,539,000.00 3,078,000.00 0.12 - - - - - - - - -
SUB JUMLAH XII 22,539,440.00 0.91 - - -
XIII PEKERJAAN MEKANIKAL ELEKTRIKAL
XIII.1 PEKERJAAN PANEL DISTRIBUSI
A PEKERJAAN PANEL
a. Pekerjaan Main Panel Distribusi (MDP)
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 60x80
set cm) 1.00 5,704,580.00 5,704,580.00 0.23 - - - - - - - - -
2. Change Over Switch (COS) 160 A, 3 Phasa unit 1.00 4,392,500.00 4,392,500.00 0.18 - - - - - - - - -
3. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
4. MCCB 80A ,10KA, 3 phasa unit 1.00 855,600.00 855,600.00 0.03 - - - - - - - - -
5. MCCB 40A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
6.. MCCB 25A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
7. MCCB 16A , 3 phasa unit 1.00 615,600.00 615,600.00 0.02 - - - - - - - - -
8. MCB 10A, 6kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
b Pekerjaan Main Panel Distribusi (SDP1) untuk kios
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 60A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 1.00 160,600.00 160,600.00 0.01 - - - - - - - - -
4. MCB 10A, 10kA, 1 phasa unit 4.00 180,600.00 722,400.00 0.03 - - - - - - - - -
c. Pekerjaan Main Panel Distribusi (SDP2) untuk los
1. Box Panel plat 1,5mm fin. Cat warna abu-abu kulit jeruk (uk. 40x60
set cm) 1.00 3,954,580.00 3,954,580.00 0.16 - - - - - - - - -
2. MCCB 80A ,10KA, 3 phasa unit 1.00 820,600.00 820,600.00 0.03 - - - - - - - - -
3. MCB 10A, 5kA, 1 phasa unit 10.00 160,600.00 1,606,000.00 0.06 - - - - - - - - -
4. MCB 2A, 10kA, 1 phasa (posisi di meja los) unit 70.00 160,600.00 11,242,000.00 0.45 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
B PEKERJAAN KABEL TROVOOR + ARDE & KABEL TRAY
a. Pekerjaan Kabel Trovoor
1. Pekerjaan Kabel Tovoor NYY 4 x 50 mm2 m1 15.00 523,000.00 7,845,000.00 0.32 - - - - - - - - -
2. Pekerjaan Kabel Tovoor NYY 4 x 25 mm2 m1 4.50 283,000.00 1,273,500.00 0.05 - - - - - - - - -
b. Pekerjaan Kabel Tray
1. Pekerjaan pengadaan + pasang Kabel Tray m1 99.90 456,400.00 45,594,360.00 1.84 - - - - - - - - -
2. Pekerjaan pengadaan pipa galvanis sambungan dari kabel traym1
ke instalasi 3.40
Los 165,200.00 561,680.00 0.02 - - - - - - - - -
c. Pekerjaan Grounding
1. Pekerjaan Grounding , nilai maksimal = 1 ohm ls 1.00 4,350,000.00 4,350,000.00 0.18 - - - - - - - - -
XIII.2 PEKERJAAN INSTALASI
a. Instalasi penarikan kabel lampu dan stop kontak
1. Pengadaan + penarikan instalasi penerangan Down Light, TL, titik 36.00 225,895.00 8,132,220.00 0.33 - - - - - - - - -
2. Pengadaan + penarikan instalasi stop kontak normal (1 gang) titik 86.00 233,695.00 20,097,770.00 0.81 - - - - - - - - -
3. Pengadaan + penarikan instalasi saklar titik 24.00 233,695.00 5,608,680.00 0.23 - - - - - - - - -
b. Pekerjaan Armature
1. Pengadaan + pasang armature lampu downlight & titik 30.00 237,980.00 7,139,400.00 0.29 - - - - - - - - -
2. Pengadaan + Pasang Armature lampu TL 1 titik 36.00 392,980.00 14,147,280.00 0.57 - - - - - - - - -
3. Pengadaan + Pasang Armature lampu emergency TL 2 titik 8.00 629,300.00 5,034,400.00 0.20 - - - - - - - - -
4. Pengadaan + Pasang stop kontak 1 gang titik 86.00 62,980.00 5,416,280.00 0.22 - - - - - - - - -
5. Pengadaan + Pasang saklar tunggal titik 24.00 42,980.00 1,031,520.00 0.04 - - - - - - - - -
XIII.4 PEKERJAAN TATA UDARA 0
1. Pengadaan dan pemasangan ventilator 60 CM = 24’’/100 x 86 xset
86 10.00 2,150,000.00 21,500,000.00 0.87 - - - - - - - - -
2. Pengadaan dan pemasangan exhaust fan 10" unit 2.00 805,000.00 1,610,000.00 0.06 - - - - - - - - -
SUB JUMLAH XIII 187,849,530.00 7.56 - - -
XIV PEKERJAAN PLUMBING
a. Pekerjaan plumbing air bersih
1. Pengadaan + pemasangan Tandon Air Unit 1.00 16,500,000.00 16,500,000.00 0.66 - - - - - - - - -
2. Pengadaan + pemasangan pipa air bersih supplay dari pompa m1ke pipa vertikal
12.00turun ke los
144,956.70 1,739,480.40 0.07 - - - - - - - - -
3. Pengadaan + pemasangan pipa air bersih supplay dari pipa 1" m1
horisontal ke
36.00
kran los 97,328.70 3,503,833.20 0.14 - - - - - - - - -
4. Pengadaan + pemasangan kran dinding 1/2" unit 14.00 57,388.73 803,442.22 0.03 - - - - - - - - -
5. Pengadaan + pemasangan washtafel set 3.00 915,098.52 2,745,295.56 0.11 - - - - - - - - -
6.. Pengadaan + pemasangan urinoir set 3.00 1,995,466.00 5,986,398.00 0.24 - - - - - - - - -
7. Pengadaan + pemasangan stop kran galvanis 1" pada pipa turunsetmenuju los2.00 332,800.00 665,600.00 0.03 - - - - - - - - -
8. Pengadaan + pemasangan stop kran PVC 1" posisi pada pompa setin dan out 2.00 38,500.00 77,000.00 0.00 - - - - - - - - -
9. Pengadaan + pemasangan stop kran PVC 1" posisi pada pipa suplay
set vertikal18.00
pada los 38,500.00 693,000.00 0.03 - - - - - - - - -
10. Pengadaan dan pemasangan wastafel Portable unit 4.00 6,600,000.00 26,400,000.00 1.06 - - - - - - - - -
b. Pekerjaan plumbing air kotor
1. Pengadaan + pemasangan pipa air kotor dari parit los ke grease
m1trap 24.00 142,232.20 3,413,572.80 0.14 - - - - - - - - -
2. Pengadaan + pemasangan pipa air kotor dari grease trap ke IPAL
m1 gedung12.00 199,703.42 2,396,441.04 0.10 - - - - - - - - -
3. Pengadaan + pemasangan pipa air kotor toilet dan wudhu ke parit
m1 30.50 65,679.60 2,003,227.80 0.08 - - - - - - - - -
4. Pengadaan + pemasangan floor drain set 5.00 165,473.00 827,365.00 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
c. Pekerjaan plumbing air kotoran
1. Pengadaan + pemasangan pipa air kotoran dari closet ke septictank
m1 16.00 199,703.42 3,195,254.72 0.13 - - - - - - - - -
2. Pengadaan + pemasangan pipa udara pada septictank m1 2.20 65,679.60 144,495.12 0.01 - - - - - - - - -
3. Pengadaan + pemasangan pipa peresapan pada septictank m1 4.00 142,232.30 568,929.20 0.02 - - - - - - - - -
4. Pengadaan + pemasangan closet jongkok unit 5.00 827,120.00 4,135,600.00 0.17 - - - - - - - - -
d. Pekerjaan plumbing air hujan
1. Pengadaan + pemasangan pipa air hujan m1 34.50 199,703.42 6,889,767.99 0.28 - - - - - - - - -
2. bak kontrol parit 40x40 unit 4.00 770,586.25 3,082,345.00 0.12 - - - - - - - - -
SUB JUMLAH XIV 85,771,048.05 3.45 - - -
XV PEKERJAAN SISTEM PEMADAM KEBAKARAN
1. Pengadaan dan pemasangan fire extinguisher unit 6.00 1,925,000.00 11,550,000.00 0.46 - - - - - - - - -
SUB JUMLAH XV 11,550,000.00 0.46 - - -
XVI PEKERJAAN BAK SAMPAH
XVI.1 PEKERJAAN TANAH DAN PERSIAPAN
A PEKERJAAN PERSIAPAN
1. pengukuran dan Pemasangan Bowplank m2 17.00 62,905.64 1,069,395.88 0.04 - - - - - - - - -
B PEKERJAAN TANAH
1. galian tanah m3 7.04 50,960.00 358,758.40 0.01 - - - - - - - - -
2. urugan tanah kembali m3 1.76 24,421.60 42,982.02 0.00 - - - - - - - - -
3. pasir urug bawah rabat dan pondasi m3 3.00 269,500.00 808,500.00 0.03 - - - - - - - - -
XVI.2 PEKERJAAN STRUKTUR
A PEKERJAAN BETON
a. struktur bawah
1. Pasangan Pondasi Batu Kosong m3 3.08 590,866.50 1,819,868.82 0.07 - - - - - - - - -
2. Pasangan Pondasi Batu Gunung m3 5.28 1,058,743.00 5,590,163.04 0.23 - - - - - - - - -
3. Sloof m3 0.51 1,954,708.00 996,901.08 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m3 0.26 1,954,708.00 508,224.08 0.02 - - - - - - - - -
2. ring balok m3 0.43 1,954,708.00 840,524.44 0.03 - - - - - - - - -
3. Rabat beton untuk lantai m3 1.50 1,783,796.00 2,675,694.00 0.11 - - - - - - - - -
B PEMBESIAN
a. struktur bawah
1. Sloof kg 111.04 28,011.58 3,110,405.84 0.13 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom kg 49.87 28,011.58 1,396,937.49 0.06 - - - - - - - - -
2. ring balok kg 73.70 28,011.58 2,064,453.45 0.08 - - - - - - - - -
C BEKISTING
a. struktur bawah
1. Sloof m2 7.92 118,131.16 935,598.79 0.04 - - - - - - - - -
b. struktur tengah dan atas
1. Kolom m2 3.95 118,131.16 466,618.08 0.02 - - - - - - - - -
2. ring balok total m2 6.60 118,131.16 779,665.66 0.03 - - - - - - - - -
KONTRAK PROGRES MINGGU LALU PROGRES MINGGU INI PROGRES S/D MINGGU INI
SAT. VOL. HARGA SATUAN JUMLAH HARGA BOBOT
No URAIAN PEKERJAAN TERTIMB. PROGRES TERTIMB. PROGRES TERTIMB. PROGRES
VOLUME VOLUME VOLUME
(RP) (RP) % % % % % % %
XVI.3 PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
a. pasangan dinding bata
1. pasangan dinding 1/2 bata m2 29.82 175,542.50 5,234,677.35 0.21 - - - - - - - - -
2. plaster dan aci dinding m2 28.46 62,979.70 1,792,402.26 0.07 - - - - - - - - -
b. Pekerjaan finishing dinding
1. Pengecatan dinding m2 21.66 31,396.75 680,053.61 0.03 - - - - - - - - -
SUB JUMLAH XVI 31,171,824.28 1.25 - - -
JUMLAH TOTAL 2,484,408,071.26 100.00 - - -

Wanggudu, 03 Juli 2022


Di Setujui Oleh : Di Periksa Oleh : Di Buat Oleh :
Pejabat Pembuat Komitmen (PPK) Konsultan Pengawas Konsultan Pengawas
Dinas Perdagangan dan Perindustrian ` CV. Geometri Engineering Consultant CV. Geometri Engineering Consultant
Kab. Konawe Utara

JUMADIN. M, S.Sos LA ODE MUNAJAB, ST ASWONO, ST


Nip. 19670721 199203 1 010 Direktur Inspector