AITEM RAB VOLUME PERENCANAAN AITEM RAB VOLUME PERUBAHAN/ REALISASI DI LAPANGAN
Harga Harga
VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA
No Uraian Satuan Satuan (Rp) No Uraian Satuan Satuan (Rp)
1 Unit 2 Unit (Rp.) 1 Unit 2 Unit (Rp.)
A PEKERJAAN TAMBAHAN
1 Mobilisasi Alat Ls 1.00 101,250,000.00 101,250,000.00
2 Pematangan Khusus Lokasi (1) M³ 88.8 70,348.33 6,246,931.70
I PEKERJAAN PERSIAPAN I PEKERJAAN PERSIAPAN
2 Pembersian Awal M² 72.00 144.00 94,000.00 13,536,000.00 2 Pembersian Awal M² 72.00 144.00 94,000.00 13,536,000.00
3 Pemasangan Bowplank M 22.00 44.00 154,790.00 6,810,760.00 3 Pemasangan Bowplank M 22.00 44.00 154,790.00 6,810,760.00
4 Foto Dokumentasi + Laporan Ls 1.00 2.00 7,000,000.00 14,000,000.00 4 Foto Dokumentasi + Laporan Ls 1.00 2.00 7,000,000.00 14,000,000.00
5 Papan Nama Proyek Ls 1.00 2.00 1,500,000.00 3,000,000.00 5 Papan Nama Proyek Ls 1.00 2.00 1,500,000.00 3,000,000.00
II PEKERJAAN TANAH DAN PONDASI - - II PEKERJAAN TANAH DAN PONDASI - -
1 Galian Tanah M³ 12.30 24.59 94,000.00 2,311,610.40 1 Galian Tanah M³ 12.30 24.59 94,000.00 2,311,610.40
2 Pasangan Pondasi Batu gunung M³ 7.48 14.96 7,183,886.36 107,470,940.00 2 Pasangan Pondasi Batu gunung M³ 7.48 14.96 7,183,886.36 107,470,940.00
3 Pasangan Batu Kosong M³ 1.92 3.85 3,428,850.00 13,201,072.50 3 Pasangan Batu Kosong M³ 1.92 3.85 3,428,850.00 13,201,072.50
4 Urugan Pasir Bawah Pondasi M³ 1.85 3.70 1,623,500.00 6,014,742.80 4 Urugan Pasir Bawah Pondasi M³ 1.85 3.70 1,623,500.00 6,014,742.80
5 Urugan Pasir Bawah Lantai M³ 1.18 2.35 1,623,500.00 3,822,628.16 5 Urugan Pasir Bawah Lantai M³ 1.18 2.35 1,623,500.00 3,822,628.16
6 Urugan Tanah Kembali M³ 4.62 9.24 45,050.00 416,262.00 6 Urugan Tanah Kembali M³ 4.62 9.24 45,050.00 416,262.00
7 Urugan Tanah Dan Pemadatan M³ 4.71 9.42 1,227,500.00 11,560,889.60 7 Urugan Tanah Dan Pemadatan M³ 4.71 9.42 1,227,500.00 11,560,889.60
III PEKERJAAN KAYU - - III PEKERJAAN KAYU - -
1 Kolom Kayu besi 10/10 M³ 0.30 0.60 12,082,400.00 7,249,440.00 1 Kolom Kayu besi 10/10 M³ 0.30 0.60 12,082,400.00 7,249,440.00
2 Pekerjaan Ring Balok Kayu Besi 10/ M³ 0.22 0.44 12,082,400.00 5,316,256.00 2 Pekerjaan Ring Balok Kayu Besi 10/1 M³ 0.22 0.44 12,082,400.00 5,316,256.00
3 Kuda-kuda kayu besi 5/10 M³ 0.69 1.38 12,082,400.00 16,673,712.00 3 Kuda-kuda kayu besi 5/10 M³ 0.69 1.38 12,082,400.00 16,673,712.00
4 Pekerjaan Gording kayu besi 5/10 M³ 0.88 1.76 12,082,400.00 21,265,024.00 4 Pekerjaan Gording kayu besi 5/10 M³ 0.88 1.76 12,082,400.00 21,265,024.00
5 Pekerjaan kusen kayu besi 5/10 M³ 0.15 0.30 14,705,000.00 4,411,500.00 5 Pekerjaan kusen kayu besi 5/10 M³ 0.15 0.30 14,705,000.00 4,411,500.00
6 Pekerjaan daun jendela kaca M² 1.00 2.00 1,203,500.00 2,407,000.00 6 Pekerjaan daun jendela kaca M² 1.00 2.00 1,203,500.00 2,407,000.00
7 Pekerjaan Daun pintu M² 1.42 2.83 1,210,000.00 3,428,898.00 7 Pekerjaan Daun pintu M² 1.42 2.83 1,210,000.00 3,428,898.00
IV PEKERJAAN PASANGAN DINDING DAN LANTAI - - IV PEKERJAAN PASANGAN DINDING DAN LANTAI - -
1 Pas. Batu Tela Dinding 1 pc : 4 ps M³ 5.83 11.66 2,413,127.27 28,137,064.00 1 Pas. Batu Tela Dinding 1 pc : 4 ps M³ 5.83 11.66 2,413,127.27 28,137,064.00
2 Plesteran Dinding,t.15 mm M² 77.90 155.80 247,018.18 38,485,432.73 2 Plesteran Dinding,t.15 mm M² 77.90 155.80 247,018.18 38,485,432.73
3 Pek. Acian Dinding M² 77.90 155.80 130,590.91 20,346,063.64 3 Pek. Acian Dinding M² 77.90 155.80 130,590.91 20,346,063.64
4 Pek Lantai Beton Tumbuk M³ 1.82 3.65 379,431.82 1,383,195.93 4 Pek Lantai Beton Tumbuk M³ 1.82 3.65 379,431.82 1,383,195.93
5 Pek Pasangan Tegel 30/30 M² 11.52 23.04 558,509.09 12,868,049.45 5 Pek Pasangan Tegel 30/30 M² 11.52 23.04 558,509.09 12,868,049.45
6 Pek Pasangan Tegel 10/10 M² 1.38 2.76 558,509.09 1,541,485.09 6 Pek Pasangan Tegel 10/10 M² 1.38 2.76 558,509.09 1,541,485.09
V PEKERJAAN ATAP DAN PLAFON - - V PEKERJAAN ATAP DAN PLAFON - -
1 Atap Seng Gelombang M² 25.77 51.55 99,400.00 5,123,950.72 1 Atap Seng Gelombang M² 25.77 51.55 99,400.00 5,123,950.72
2 Rangka Plafon + tripleks 3mm M² 13.89 27.77 894,085.00 24,830,707.44 2 Rangka Plafon + tripleks 3mm M² 13.89 27.77 894,085.00 24,830,707.44
3 Pemasangan lisplank M 21.48 42.96 249,135.00 10,702,839.60 3 Pemasangan lisplank M 21.48 42.96 249,135.00 10,702,839.60
VI PEKERJAAN PENGGANTUNG DAN PENGUNCI - - VI PEKERJAAN PENGGANTUNG DAN PENGUNCI - -
1 Kunci Pintu Bh 3.00 6.00 456,050.00 2,736,300.00 1 Kunci Pintu Bh 3.00 6.00 456,050.00 2,736,300.00
2 Engsel Pintu 4" - Stainles Steel Bh 3.00 6.00 65,262.50 391,575.00 2 Engsel Pintu 4" - Stainles Steel Bh 3.00 6.00 65,262.50 391,575.00
3 Engsel Jendela Bh 3.00 6.00 45,175.00 271,050.00 3 Engsel Jendela Bh 3.00 6.00 45,175.00 271,050.00
4 Grendel Jendela / Ventilasi Bh 3.00 6.00 83,500.00 501,000.00 4 Grendel Jendela / Ventilasi Bh 3.00 6.00 83,500.00 501,000.00
5 Hak Angin Jendela Bh 3.00 6.00 65,262.50 391,575.00 5 Hak Angin Jendela Bh 3.00 6.00 65,262.50 391,575.00
VII PEKERJAAN PENGECATAN - - VII PEKERJAAN PENGECATAN - -
1 Cat Dinding M² 77.90 155.80 160,515.00 25,008,237.00 1 Cat Dinding M² 77.90 155.80 160,515.00 25,008,237.00
2 Cat Kayu Kusen M² 5.20 10.40 57,850.00 601,640.00 2 Cat Kayu Kusen M² 5.20 10.40 57,850.00 601,640.00
3 Cat Kayu Lisplank M² 8.59 17.18 50,815.00 873,204.96 3 Cat Kayu Lisplank M² 8.59 17.18 50,815.00 873,204.96
4 Cat Plafon M² 13.89 27.77 45,725.00 1,269,883.85 4 Cat Plafon M² 13.89 27.77 45,725.00 1,269,883.85
VIII PEKERJAAN AKHIR - - VIII PEKERJAAN AKHIR - -
1 Pembersihan Akhir Ls 1.00 2.00 5,100,000.00 10,200,000.00 1 Pembersihan Akhir Ls 1.00 2.00 5,100,000.00 10,200,000.00
Jumlah 428,559,989.86 Jumlah 536,056,921.56
PPN 11% 47,141,598.88 PPN 11% 58,966,261.37
Jumlah Total 475,701,588.74 Jumlah Total 595,023,182.93
Pembulatan Jumlah 475,000,000.00 Pembulatan Jumlah 595,000,000.00