TERBILANG : EMPAT RATUS SEMBILAN PULUH SEMBILAN JUTA ENAM RATUS TUJUH PULUH TUJUH RIBU RUPIAH
HARGA
KODE SATUA HARGA SATUAN JUMLAH HARGA
INDEK URAIAN BAHAN UPAH
ANALISA N ( Rp ) ( Rp )
( Rp ) ( Rp )
A. PEKERJAAN PERSIAPAN
A. 6.6.4 1 M' MENGUKUR DAN MEMASANG BOUWPLANK
0.0120 m3 kayu meranti, balok @ 2,200,000.00 26,400.00
0.0200 kg Paku Biasa 2' - 5' @ 16,000.00 320.00
0.0070 m3 kayu papan 3/20 @ 2,100,000.00 14,700.00
0.1000 oh tukang kayu @ 70,000.00 7,000.00
0.1000 oh pekerja @ 55,000.00 5,500.00
0.0100 oh kepala tukang @ 75,000.00 750.00
0.0050 oh mandor @ 75,000.00 375.00
JUMLAH 41,420.00 13,625.00 55,045.00
A. 6.6.6 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT - ALAT
1.7000 btg Dolken kayu dia 8-10/4 m' @ 11,200.00 19,040.00
0.2100 kg Kayu @ 2,100,000.00 441,000.00
0.3000 kg Paku biasa 2'-5' @ 16,000.00 4,800.00
10.5000 kg Semen portland @ 1,300.00 13,650.00
0.0300 m3 Pasir Beton @ 250,000.00 7,500.00
0.0500 m3 Koral beton @ 263,000.00 13,150.00
1.5000 Lbr Seng gelombang @ 40,900.00 61,350.00
2.0000 oh Tukang kayu @ 70,000.00 140,000.00
1.0000 oh Pekerja @ 55,000.00 55,000.00
0.2000 oh Kepala tukang @ 75,000.00 15,000.00
0.0500 oh Mandor @ 75,000.00 3,750.00
JUMLAH 560,490.00 213,750.00 774,240.00
B. PEKERJAAN TANAH
B. 6.6.1 1 M3 GALIAN TANAH BIASA SEDALAM 1 M'
0.4000 oh pekerja @ 55,000.00 22,000.00
- oh tukang gali @ 70,000.00 -
- oh kepala tukang @ 75,000.00 -
0.0400 oh mandor @ 75,000.00 3,000.00
JUMLAH 25,000.00 25,000.00
B. 6.6.7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 M
0.0010 Ltr Roundup @ 65,000.00 65.00
0.0500 oh pekerja @ 55,000.00 2,750.00
- oh tukang gali @ 70,000.00 -
- oh kepala tukang @ 75,000.00 -
0.0050 oh mandor @ 75,000.00 375.00
JUMLAH 3,190.00 3,190.00
B. 6.6.9 1 M3 URUGAN KEMBALI
0.1920 oh pekerja @ 55,000.00 10,560.00
- oh tukang gali @ 70,000.00 -
- oh kepala tukang @ 75,000.00 -
0.0190 oh mandor @ 75,000.00 1,425.00
JUMLAH 11,985.00 11,985.00
B. 6.6.11 1 M3 URUGAN TANAH
1.2000 M3 Tanah urug @ 51,900.00 62,280.00
0.2500 oh pekerja @ 55,000.00 13,750.00
0.0250 oh mandor @ 75,000.00 1,875.00
1.0000 oh Ls biaya pemadatan @ 25,500.00 25,500.00
JUMLAH 62,280.00 41,125.00 103,405.00
B. 6.6.11.a 1 M3 URUGAN PASIR
1.2000 M3 Pasir pasang putih (Sepaku) @ 225,000.00 270,000.00
0.3000 oh pekerja @ 55,000.00 16,500.00
0.0100 oh mandor @ 75,000.00 750.00
1.0000 oh Ls biaya pemadatan @ 25,500.00 25,500.00
JUMLAH 270,000.00 42,750.00 312,750.00
HARGA
KODE SATUA HARGA SATUAN JUMLAH HARGA
INDEK URAIAN BAHAN UPAH
ANALISA N ( Rp ) ( Rp )
( Rp ) ( Rp )
C. PEKERJAAN PONDASI
C.6.6.5 1 M3 PASANG PONDASI BATU KALI / GUNUNG / BELAH 1 Pc ; 4 Ps
1.1000 m3 batu belah 15/20 cm @ 225,000.00 247,500.00
163.0000 kg semen porland @ 1,300.00 211,900.00
0.5200 m3 Pasir Pasang sungai ex. Kandilo @ 280,000.00 145,600.00
9 1.5000 oh pekerja @ 55,000.00 82,500.00
3.6 0.6000 oh tukang batu @ 70,000.00 42,000.00
0.36 0.0600 oh kepala tukang @ 75,000.00 4,500.00
0.45 0.0750 oh mandor @ 75,000.00 5,625.00
JUMLAH 605,000.00 134,625.00 739,625.00
C. 6.6.14 1 M3 PASANGAN BATU KOSONG (AANSTAMPING)
1.2000 m3 batu gunung @ 225,000.00 270,000.00
0.3000 m3 pasir urug @ 225,000.00 67,500.00
0.7800 oh pekerja @ 55,000.00 42,900.00
0.3900 oh tukang batu @ 70,000.00 27,300.00
0.0390 oh kepala tukang @ 75,000.00 2,925.00
0.0390 oh mandor @ 75,000.00 2,925.00
JUMLAH 337,500.00 76,050.00 413,550.00
D. PEKERJAAN DINDING
D.6.6.2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc ; 2 Ps
120.0000 bh bata merah @ 800.00 96,000.00
43.5000 kg semen portland @ 1,300.00 56,550.00
0.0800 m3 pasir pasang @ 280,000.00 22,400.00
0.6500 oh pekerja @ 55,000.00 35,750.00
0.2000 oh tukang batu @ 70,000.00 14,000.00
0.0200 oh kepala tukang @ 75,000.00 1,500.00
0.0300 oh mandor @ 75,000.00 2,250.00
JUMLAH 174,950.00 53,500.00 228,450.00
D. 6.6.9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 2 ps
60.0000 bh bata merah 8 x 8 x 15 cm @ 800.00 48,000.00
18.9500 kg semen porland @ 1,300.00 24,635.00
0.0380 m3 pasir pasang @ 280,000.00 10,640.00
0.3200 oh pekerja @ 55,000.00 17,600.00
0.1000 oh tukang batu @ 70,000.00 7,000.00
0.0100 oh kepala tukang @ 75,000.00 750.00
0.0150 oh mandor @ 75,000.00 1,125.00
JUMLAH 83,275.00 26,475.00 109,750.00
D. 6.6.11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps
60.0000 bh bata merah 8 x 8 x 15 cm @ 800.00 48,000.00
11.5000 kg semen porland @ 1,300.00 14,950.00
0.0430 m3 pasir pasang @ 280,000.00 12,040.00
0.3200 oh pekerja @ 55,000.00 17,600.00
0.1000 oh tukang batu @ 70,000.00 7,000.00
0.0100 oh kepala tukang @ 75,000.00 750.00
0.0150 oh mandor @ 75,000.00 1,125.00
JUMLAH 74,990.00 26,475.00 101,465.00
E. 6.6.2 1 M2 PLESTERAN 1 pc ; 2 ps, TEBAL 15 MM
8.5200 kg semen portland @ 1,300.00 11,076.00
0.0170 m3 pasir pasang @ 280,000.00 4,760.00
0.2000 oh pekerja @ 55,000.00 11,000.00
0.1500 oh tukang batu @ 70,000.00 10,500.00
0.0150 oh kepala tukang @ 75,000.00 1,125.00
0.0100 oh mandor @ 75,000.00 750.00
JUMLAH 15,836.00 23,375.00 39,211.00
HARGA
KODE SATUA HARGA SATUAN JUMLAH HARGA
INDEK URAIAN BAHAN UPAH
ANALISA N ( Rp ) ( Rp )
( Rp ) ( Rp )
I. PEKERJAAN PLAFOND
I. 6.6.19 1M' PLAFOND KAYU PROFIL
1.1000 m' List kayu profil Meranti @ 10,300.00 11,330.00
0.0100 Kg paku biasa @ 16,000.00 160.00
0.0500 oh pekerja @ 55,000.00 2,750.00
0.0500 oh tukang kayu @ 70,000.00 3,500.00
0.0050 oh kepala tukang @ 75,000.00 375.00
0.0030 oh mandor @ 75,000.00 225.00
JUMLAH 11,490.00 6,850.00 18,340.00
I. 6.6.20 1M2 PLAFOND ASBES ( 1,00 X 1,00 ) M, TEBAL 3,2MM RANGKA MERANTI
0.0120 m3 kayu meranti @ 2,200,000.00 26,400.00
0.0600 Kg paku biasa @ 16,000.00 960.00
1.1000 lbr asbes 1,00 x 1,00 m @ 18,000.00 19,800.00
0.1800 oh pekerja @ 55,000.00 9,900.00
0.3200 oh tukang kayu @ 70,000.00 22,400.00
0.0320 oh kepala tukang @ 75,000.00 2,400.00
0.0090 oh mandor @ 75,000.00 675.00
JUMLAH 47,160.00 35,375.00 82,535.00
J. PEKERJAAN SANITAIR
J. 6.6.2 MEMASANG 1 BH CLOSED JONGKOK KERAMIK
1.0000 bh closed jongkok keramik @ 135,000.00 135,000.00
6.0000 kg semen portland @ 1,300.00 7,800.00
0.0100 m3 pasir pasang @ 280,000.00 2,800.00
0.5000 oh pekerja @ 55,000.00 27,500.00
0.5000 oh tukang batu @ 70,000.00 35,000.00
0.1600 oh mandor @ 75,000.00 12,000.00
JUMLAH 145,600.00 74,500.00 220,100.00
J. 6.6.25 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1/2 "
1.2000 m' Pipa PVC @ 5,050.00 6,060.00
35.0000 % Perlengkapan @ 1,767.50 1,767.50
0.0360 oh pekerja @ 55,000.00 1,980.00
0.0600 oh Tukang Batu @ 70,000.00 4,200.00
0.0060 oh kepala tukang @ 75,000.00 450.00
0.0018 oh mandor @ 75,000.00 135.00
JUMLAH 7,827.50 6,765.00 14,592.50
J. 6.6.26 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4"
1.2000 m' Pipa PVC @ 5,250.00 6,300.00
35.0000 % Perlengkapan @ 1,837.50 1,837.50
0.0360 oh pekerja @ 55,000.00 1,980.00
0.0600 oh Tukang Batu @ 70,000.00 4,200.00
0.0060 oh kepala tukang @ 75,000.00 450.00
0.0018 oh mandor @ 75,000.00 135.00
JUMLAH 8,137.50 6,765.00 14,902.50
J. 6.6.31 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3"
1.2000 m' Pipa PVC @ 67,000.00 80,400.00
35.0000 % Perlengkapan @ 23,450.00 23,450.00
0.0810 oh pekerja @ 55,000.00 4,455.00
0.1350 oh Tukang Batu @ 70,000.00 9,450.00
0.0135 oh kepala tukang @ 75,000.00 1,012.50
0.0041 oh mandor @ 75,000.00 307.50
JUMLAH 103,850.00 15,225.00 119,075.00
HARGA
KODE
SAT HARGA SATUAN ( Rp JUMLAH
ANALIS INDEK URAIAN BAHAN UPAH
UAN ) HARGA ( Rp )
A
( Rp ) ( Rp )
1 2 3 4 = 6+5 5 6 7
1 2 3 4 = 6+5 5 6 7
1 2 3 4 = 6+5 5 6 7
1 2 3 4 = 6+5 5 6 7
1 2 3 4 = 6+5 5 6 7
219 Pintu Panel kayu Bangkirai Uk. Besar L 80 cm Bh 544,500.00 - 544,500.00 ###
220 Pintu Panel kayu Bangkirai Uk. Kecil L 70 cm Bh 484,000.00 - 484,000.00 ###
221 Pintu Panel kayu Ulin Ukuran Besar L 80 cm Bh 513,700.00 - 513,700.00 ###
222 Pintu Panel kayu Ulin Ukuran Kecil L 70 cm Bh 484,000.00 - 484,000.00 ###
223 Pintu Panel Lapis Formika (Fabrikasi) Bh 363,000.00 - 363,000.00 ###
224 Pintu PVC KM/WC Bh 750,000.00 - 750,000.00
225 Pintu Skat Bh 385,000.00 - 385,000.00 ###
226 Pipa Galvanis AW Dia 1 " M' 52,100.00 - 52,100.00 ###
227 Pipa Galvanis AW Dia 2 " M' 103,100.00 - 103,100.00 ###
228 Pipa Galvanis AW Dia 3 " M' 182,150.00 - 182,150.00 ###
229 Pipa Galvanis AW Dia 4 " M' 259,300.00 - 259,300.00 ###
230 Pintu / Ventilasi Jeruji Besi M2 400,000.00 - 400,000.00
231 Pipa Listrik PVC 1/2" Btg 20,000.00 - 20,000.00
232 Pipa PVC AW Dia 1 " Btg 24,100.00 - 24,100.00 ###
233 Pipa PVC AW Dia 1/2 " Btg 20,200.00 - 20,200.00 ###
234 Pipa PVC AW Dia 2 " Btg 48,900.00 - 48,900.00 ###
235 Pipa PVC AW Dia 3" M' 67,000.00 - 67,000.00
236 Pipa PVC AW Dia 3/4 " Btg 21,000.00 - 21,000.00 ###
237 Pipa PVC AW Dia 4 " M' 151,000.00 - 151,000.00 ###
238 Pipa stainless steel 2 " M' 37,400.00 - 37,400.00 ###
239 Pipa stainless steel 3 " M' 67,000.00 - 67,000.00 ###
240 Pitting Bh 6,450.00 - 6,450.00 ###
241 Plamir Kg 18,500.00 - 18,500.00 ###
242 Plitur Kg 42,500.00 - 42,500.00 ###
243 Plint / list lantai keramik Bh 3,100.00 - 3,100.00 ###
244 Plint marmer 10 x 40 cm Bh 21,800.00 - 21,800.00 ###
245 Calsieboard Lbr 63,000.00 63,000.00
245 Plywood 3 mm Lbr 44,600.00 - 44,600.00 ###
246 Plywood 4 mm Lbr 56,500.00 - 56,500.00 ###
247 Plywood 6 mm Lbr 79,000.00 - 79,000.00 ###
248 Plywood 9 mm Lbr 124,583.33 - 124,583.33 ###
249 Plywood 12 mm Lbr 220,000.00 - 220,000.00 ###
250 Plywood 18 mm Lbr 231,000.00 - 231,000.00 ###
251 Porselen 20 x 20 cm Bh 52,000.00 - 52,000.00 ###
252 Polycarbonat M2 825,000.00 - 825,000.00 ###
253 Rangka Plafond besi hollow M2 102,080.00 - 102,080.00 ###
254 Rangka Atap Baja Ringan + Reng M2 220,000.00 - 220,000.00
255 Rol Cat Tembok Bh 16,500.00 - 16,500.00 ###
256 Railling Tangga Besi Hollow M' 475,000.00 - 475,000.00
257 Rolling door Standart 1 Unit - - -
258 Roster beton 20 x 20 cm Bh 33,000.00 - 33,000.00 ###
259 Roster beton 20 x 30 cm Bh 46,000.00 - 46,000.00 ###
260 Roster kayu bangkirai 20 x 20 cm Bh 36,000.00 - 36,000.00 ###
261 Rumput Hias M2 27,500.00 - 27,500.00 ###
262 Saklar Ganda Bh 19,000.00 - 19,000.00 ###
263 Saklar Tunggal Bh 15,000.00 - 15,000.00 ###
264 Sealent Kg 35,000.00 - 35,000.00
265 Seal Tape Bh 4,000.00 - 4,000.00
266 Sekering Kas 3 Group + Instalasi Unit 146,800.00 - 146,800.00 ###
267 Semen Abu - Abu / PC ( 50 kg/Zak ) Kg 1,300.00 - 1,300.00 ###
268 Semen Warna Kg 10,000.00 - 10,000.00 ###
269 Semen putih Kg 2,000.00 - 2,000.00 ###
270 Seng gelombang Besar / kecil Lbr 40,900.00 - 40,900.00 ###
271 Seng Plat BJLS 30 M' 6,853.85 - 6,853.85 ###
272 Seng Plat BJLS 28 Lbr 53,600.00 - 53,600.00
273 Seng Plat Lbr 53,600.00 - 53,600.00 ###
274 Septictank ( 3 x 1,5 )+Resapan (1,5 x 1,5 ) Unit 695,000.00 - 695,000.00 ###
275 Septictank Kayu Unit 1,815,000.00 - 1,815,000.00 ###
276 Sirlak Kg 29,700.00 - 29,700.00 ###
HARGA DASAR BIAYA HARGA DASAR
NO URAIAN SAT KETERANGAN
TANPA PAJAK ANGKUT SATUAN
1 2 3 4 = 6+5 5 6 7