Anda di halaman 1dari 7

RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN GEDUNG WORKSHOP - BLK KOMUNITAS


PEMBERI TUGAS : KEMENTERIAN KETENAGAKERJAAN RI
KEJURUAN : TEKHNIK INFORMATIKA
TAHUN ANGGARAN : 2022

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp. ) ( Rp. )
A PEKERJAAN PERSIAPAN
1 Papan Proyek 1 unit 500,000 500,000
2 Pek. Laporan & Dokumentasi 1 ls 2,000,000 2,000,000
Sub Total A 2,500,000
B PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Pondasi 82.8 m3 63,975 5,297,130
2 Pek. Urug Tanah Kembali 27.6 m3 45,950 1,268,220
3 Pek. Urug Tanah Peninggian Peil Lantai (t = 10 cm) 19.55 m 3
45,950 898,323
4 Pek. Pasir Urug
- Bawah Pondasi 11.83 m3 164,190 1,942,368
- Bawah Lantai 15.06 m 3
164,190 2,472,701
5 Pek. Pondasi Tapak P1 (100x100x20)
- Beton K-225 2.8 m3 1,062,000 2,973,600
- Pembesian 438.09 kg 10,800 4,731,372
- Bekisting 16.8 m2 195,000 3,276,000
6 Pek. Pondasi Batu Belah P2 19.29 m3 737,700 14,230,233
7 Pek. Sloof Beton (15/30)
- Beton K-225 3.94 m3 1,062,934 4,187,960
- Pembesian 584.85 kg 10,800 6,316,380
- Bekisting 52.58 m2 180,000 9,464,400
Sub Total B 57,058,687
C PEKERJAAN STRUKTUR
C.1 STRUKTUR BETON
1 Pek. Kolom Beton K1 (30/30)
- Beton K-225 8.21 m3 1,060,000 8,702,600
- Pembesian 1007.31 kg 10,800 10,878,948
- Bekisting 109.44 m2 100,000 10,944,000
2 Pek. Kolom Praktis KP (15/15)
- Beton K-175 0.55 m3 1,013,179 557,248
- Pembesian 105.76 kg 10,800 1,142,208
- Bekisting 14.7 m2 100,000 1,470,000
3 Pek. Balok Beton B1,B2 (20/30)
- Beton K-225 3.69 m3 106,000 391,140
- Pembesian 482.49 kg 10,400 5,017,896
- Bekisting 49.2 m2 100,000 4,920,000
4 Pek. Beton Balok Lintel BL (15/15), RB (15/15)
- Beton K-175 2.26 m3 1,013,000 2,289,380
- Pembesian 480.78 kg 10,800 5,192,424
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp. ) ( Rp. )
- Bekisting 43.82 m2 100,000 4,382,000
5 Pek. Ramp Beton T = 10 cm
- Beton K-175 0.35 m3 1,013,000 354,550
- Pembesian 42.24 kg 10,800 456,192
- Bekisting 0.69 m2 100,000 69,000
6 Pek. Kolom Sopi Sopi 30/30)
- Beton K-225 1.98 m3 1,062,000 2,102,760
- Pembesian 149.29 kg 10,800 1,612,332
- Bekisting 26.46 m2 100,000 2,646,000
7 Pek. Balok B4 Sopi Sopi (15/20)
- Beton K-175 1.32 m3 1,013,000 1,337,160
- Pembesian 197.9 kg 10,800 2,137,320
- Bekisting 17.56 m2 100,000 1,756,000
8 Pek. Plat Beton Topi Topi (10/60)
- Beton K-225 1.84 m3 1,062,000 1,954,080
- Pembesian 214.39 kg 10,800 2,315,412
- Bekisting 21.06 m2 100,000 2,106,000
C.2 PEKERJAAN ATAP
Rangka Atap
1 L 40.40.4 366.65 kg 90,000 32,998,500
2 2 X L 50,50,5 946.3 kg 18,600 17,601,180
3 Kuda Kuda 2 x C 100.50.20.2,3 32.5 kg 140,000 4,550,000
4 Gording C 125.50.20.2,3 875 kg 23,800 20,825,000
5 L 50,50,5 dudukan gording 49.8 kg 200,000 9,960,000
6 Trekstang Ø12 49.65 kg 25,000 1,241,250
7 Ikatan angin Ø16 166.6 kg 18,000 2,998,800
8 Pelat sambung T 10mm 377.1 kg 16,000 6,033,600
9 Angkur Ø16 x 300 mm 64 bh 50,000 3,200,000
10 Bout M12 x 30 mm 608 bh 429 260,832
11 Cat Sincromat Rangka baja 150 m2 6,500 975,000
Penutup
1 Atap Spandek t = 0.35 mm 223.19 m2 77,050 17,196,790
2 Pasang Alumunium Foil, Glaswool, Roofmesh 140 m2 15,750 2,205,000
3 Listplank GRC 74.6 m' 45,000 3,357,000
4 Plashing/ban banan atap (plester, aci, waterprofing) 6 m1 120,000 720,000
Sub Total C 198,857,602
D PEKERJAAN PLAFOND
1 Plafond Gipsum 9 mm + Rangka Hollow 4/4 ; t = 0.35 116.49 m2 120,000 13,978,800
2 Plafond Calsiboard 4,5 mm + Rangka 55.51 m2
120,001 6,661,256
3 Lis Gipsum 5 cm 94.85 m' 25,000 2,371,250
Sub Total D 23,011,306
E PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 275.37 m2 140,000 38,551,800
2 Plester + Acian 545.45 m3
30,000 16,363,500
3 Pasangan Rolaag Bata 19.8 m' 22,000 435,600
4 Pekerjaan Lapis cor Beton t = 5 cm bawah lantai keramik 7.53 m3 46,600 350,898
5 Pekerjaan Rabat Beton t = 5 cm keliling bang lbr = 100 cm 2.43 m3 774,000 1,880,820
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp. ) ( Rp. )
6 Pekerjaan Meja Beton Wastafel t = 8 cm 0.12 m3 774,000 92,880
7 Pasangan Keramik Lantai 40/40 Polished 136.4 m 2
92,000 12,548,800
8 Pasangan Keramik Lantai 30/30 UnPolished (rabat) 52 m 2
172,460 8,967,920
9 Pasangan Keramik Lantai 20/20 Unpolished 3.04 m2 170,535 518,426
10 Pasangan Plint Keramik Lantai 40/10 polished 97.4 m' 169,825 16,540,955
11 Pasangan Keramik Bak & Meja Wastafel 20/20 Polished 1.77 m2 57,104 101,074
12 Pasangan Keramik Dinding 30/60 Polished 5.29 m2 145,699 770,748
13 Pasangan keramik dinding 40 x40 cm Kolom Entrace 5.12 m 2
136,732 700,068
14 Pek. Logo & Tulisan 1 ls 2,000,000 2,000,000
15 Tali Air 25 m1 45,000 1,125,000
16 List Profil Dinding 27.9 m1 20,000 558,000
Sub Total E 101,506,489
F PEKERJAAN KUSEN PINTU & JENDELA
1 Kusen/Pintu type P1 1 unit 4,000,000 4,000,000
2 Kusen/Pintu type P2 4 unit 2,500,000 10,000,000
3 Kusen/Pintu type P3 (Spandrel) 1 unit 2,800,000 2,800,000
4 Kusen/Jendela type J1 1 unit 3,500,000 3,500,000
5 Kusen/Jendela type J2 9 unit 3,600,000 32,400,000
6 Kusen/Jendela type J3 1 unit 1,300,000 1,300,000
7 Kusen/Jendela type BV 4 unit 500,000 2,000,000
8 Tralis Jendela (Besi begel) 34.1 m2 -
Sub Total F 56,000,000
G PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior 272.73 m2 15,574 4,247,497
2 Pek. Pengecatan Dinding Exterior 272.73 m 2
15,574 4,247,497
3 Pek. Pengecatan Plafond 172 m2 15,574 2,678,728
4 Pek. Pengecatan Listplank 22.38 m2 15,574 348,546
Sub Total G 11,522,268
H PEKERJAAN PLUMBING & SANITAIR
1 Instalasi Pipa PVC AW 4" 16 m' 141,228 2,259,648
2 Instalasi Pipa PVC AW 2" 12 m' 57,182 686,184
3 Instalasi Pipa PVC AW 3/4" 20 m' 21,908 438,160
4 Instalasi Pipa PVC AW 1/2" 15 m' 42,885 643,275
5 Septic Tank dan Rembesan 1 unit 6,800,000 6,800,000
6 Pemasangan Closed Jongkok 1 bh 448,150 448,150
7 Pemasangan Kran Air 2 bh 26,925 53,850
8 Pemasangan Wastafel + Kran 2 bh 500,000 1,000,000
9 Pemasangan Cermin Wastafel 100x200 1 unit 655,352 655,352
Sub Total H 12,984,619
I PEKERJAAN LISTRIK
1 Penyambungan Daya Listrik 5500.00 VA 969 5,329,500
2 Perijinan Sertifikat Layak Operasi (SLO) 5500.00 VA 500 2,750,000
3 Panel Listrik (Panel terbuat dari Plat Besi dan isi 11 MCB) 1 unit 2,500,000 2,500,000
4 Pek. Instalasi Kabel Feeder NYY 4x10 mm2 2 m' 592,175 1,184,350
5 Pek. Inst Penerangan & Kabel NYM 3x2,5 mm2 + conduit 66 ttk 192,175 12,683,550
6 Pek. Instalasi Power AC 2 ttk 120,500 241,000
7 Pemasangan Lampu TKI 2x36W 16 bh 114,920 1,838,720
8 Pemasangan Lampu Baret Kotak 18/22W 7 bh 45,610 319,270
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA
( Rp. ) ( Rp. )
9 Pemasangan Lampu E27ESS 8 Watt + downlight 4'' 3 bh 31,890 95,670
10 Pemasangan Saklar Engkle 5 bh 19,000 95,000
11 Pemasangan Saklar Double 4 bh 22,000 88,000
12 Pemasangan Stop Kontak Single 9 bh 22,830 205,470
13 Pemasangan Stop Kontak Ganda 16 bh 40,370 645,920
14 Pemasangan Stop Kontak AC 2 bh 22,000 44,000
15 Pemasangan AC split wall 2 PK 2 unit 4,000,000 8,000,000
16 Grounding (max 2 Ohm) 1 lot 200,000 200,000
Sub Total I 36,220,450
J LAIN-LAIN
1 IMB 1 pkt 1,000,000 1,000,000
Sub Total J 1,000,000
TOTAL 500,661,420
JADWAL PELAKSANAAN
PEMBANGUNAN GEDUNG WORKSHOP - BLK KOMUNITAS
TEKHNIK INFORMATIKA
TAHUN ANGGARAN 2022

MINGGU KE
NO URAIAN PEKERJAAN TOTAL %
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Ket.
I START / KONTRAK/ TERMIN I
A PEKERJAAN PERSIAPAN 2,500,000 0.50 0.50
B PEKERJAAN TANAH & PONDASI 57,058,687 11.42 7.99 3.43
C PEKERJAAN STRUKTUR 198,857,602 39.80 9.95 9.9496 9.9496 9.9496
D PEKERJAAN ATAP & PLAFOND 23,011,306 4.61 0.92 0.9211 0.9211 0.9211 0.9211
E PEKERJAAN PASANGAN 101,506,489 20.32 5.08 5.0788 5.0788 5.0788
F PEKERJAAN KUSEN PINTU & JENDELA 56,000,000 11.21 2.80 2.8019 2.8019 2.8019
G PEKERJAAN PENGECATAN 11,522,268 2.31 1.15 1.153
H PEKERJAAN PLUMBING & SANITAIR 12,984,619 2.60 1.30 0.65 0.6497
I PEKERJAAN LISTRIK 36,220,450 7.25 1.81 1.8122 1.8122 1.8122
J LAIN-LAIN - - - - - 0 0 0 0 0 0 0 0 0 0 0 0 0 0
II TERMIN II
Bobot Rencana 499,661,420 100 8.5 3.4 9.9 9.9 9.9 15.0 5.1 5.1 6.0 3.7 3.7 3.7 6.2 3.6 2.5 1.8 1.8
Akumulasi Rencana 500,054,070 100 8.5 11.9 21.9 31.8 41.8 56.8 61.9 67.0 73.0 76.7 80.4 84.1 90.3 93.9 96.4 98.2 100
Bobot Realisasi 500,054,070 100 10.5 4.1 6.9 6.9 6.9 13.5 6.7 6.7 7.9 4.2 4.2 4.2 6.6 3.8 2.7 2.1 2.1
Akumulasi Realisasi 500,054,070 100 10.5 14.6 21.5 28.4 35.2 48.7 55.4 62.2 70.1 74.3 78.5 82.7 89.3 93.1 95.8 97.9 100

, 20 Juni 2022
Unit Pengelola Kegiatan
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN GEDUNG WORKSHOP - BLK KOMUNITAS


PEMBERI TUGAS : KEMENTERIAN KETENAGAKERJAAN RI
KEJURUAN : TEKHNIK INFORMATIKA
TAHUN ANGGARAN : 2022

NO ITEM PEKERJAAN TOTAL

A PEKERJAAN PERSIAPAN 2,500,000


B PEKERJAAN TANAH & PONDASI 57,058,687
C PEKERJAAN STRUKTUR 198,857,602
D PEKERJAAN ATAP & PLAFOND 23,011,306
E PEKERJAAN PASANGAN 101,506,489
F PEKERJAAN KUSEN PINTU & JENDELA 56,000,000
G PEKERJAAN PENGECATAN 11,522,268
H PEKERJAAN PLUMBING & SANITAIR 12,984,619
I PEKERJAAN LISTRIK 36,220,450
TOTAL 500,661,420
PEMBULATAN 500,000,000
TERBILANG : '' LIMA RATUS JUTA RUPIAH ''