Anda di halaman 1dari 2

HARGA SATUAN JUMLAH

NO URAIAN PEKERJAAN VOLUME SAT


( Rp ) ( Rp )

- Beton K-175 0.35 m³ 900,000 315,000


- Pembesian 42.24 kg 22,500 950,400
- Bekisting 0.69 m³ 95,000 65,550
7 Pek Kolom Sopi Sopi (30/30)
- Beton K-225 1.98 m³ 1,150,000 2,277,000
- Pembesian 73.37 kg 22,500 1,650,825
- Bekisting 26.46 m³ 95,000 2,513,700
8 Pek Balok B4 dan Sopi Sopi (15/20)
- Beton K-175 1.58 m³ 900,000 1,422,000
- Pembesian 244.92 kg 22,500 5,510,700
- Bekisting 28.93 m³ 95,000 2,748,350
9 Pek Plat Beton Topi Topi (10/60)
- Beton K-225 1.21 m³ 1,150,000 1,391,500
- Pembesian 200.13 kg 22,500 4,502,925
- Bekisting 14.14 m³ 95,000 1,343,300
C.2 PEKERJAAN ATAP
Rangka Atap
1 L 40.40.4 366.65 kg 22,500 8,249,625
2 2 X L 50,50,5 946.30 kg 22,500 21,291,750
3 Kuda-kuda 2x C 100.50.20.2,3 32.50 kg 22,500 731,250
4 Gording C 125.50.20.2,3 902.00 kg 22,500 20,295,000
5 L 50,50,5 dudukan gording 49.80 kg 22,500 1,120,500
6 Trekstang Ø12 49.65 kg 22,500 1,117,125
7 Ikatan angin Ø16 166.60 kg 22,500 3,748,500
8 Pelat sambung T 10mm 377.10 kg 22,500 8,484,750
9 Angkur Ø16 x 300 mm 64.00 bh 65,000 4,160,000
10 Baut M12 x 30 mm 608.00 bh 15,000 9,120,000
11 Cat Sincromat Rangka Baja 150.00 m² 42,500 6,375,000
Penutup
1 Atap Spandek t = 0.35 mm 256.23 m² 125,000 32,028,750
2 Pasang Alumunium Foil, Glaswool, Roofmesh 160.00 m² 85,000 13,600,000
3 Listplank GRC 76.60 m¹ 65,000 4,979,000
4 Plashing/ban bahan atap (plester, aci, waterproofing) 6.00 m¹ 165,000 990,000
Sub Total C 160,982,500
D PEKERJAAN PLAFOND
1 Plafond Gipsum 9 mm + Rangka Hollow 4/4 ; t = 0.35 20.00 m² 145,000 2,900,000
2 Plafond Calsiboard 4,5 mm + Rangka 76.00 m² 165,000 12,540,000
3 Lis Gipsum 5 cm 52.00 m¹ 37,500 1,950,000
Sub Total D 17,390,000
E PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 226.39 m² 135,000 30,562,650
2 Plester + Acian 452.78 m³ 83,500 37,807,130
3 Pasangan Rolaag Bata 19.80 m¹ 145,000 2,871,000
4 Pekerjaan Rabat Beton t = 5 cm keliling bang lbr = 100 cm 2.60 m³ 2,750,000 7,150,000
HARGA SATUAN JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
( Rp ) ( Rp )

5 Pekerjaan Meja Beton Wastafel t = 8 cm 0.12 m³ 2,750,000 330,000


6 Pasangan Keramik Lantai 40/40 Polished (Unica white essenza) 21.40 m² 375,000 8,025,000
7 Pasangan Keramik Lantai 30/30 unPolished (rabat) 55.60 m² 210,000 11,676,000
8 Pasangan Keramik Lantai 20/20 unPolished (KM) 3.04 m² 195,000 592,800
9 Pasangan Plint Keramik Lantai 40/10 polished 21.20 m¹ 47,500 1,007,000
10 Acian Lantai 168.70 m² 37,500 6,326,250
11 Pengecatan Lantai (Cat minyak) 168.70 m² 45,000 7,591,500
Sub Total E 113,939,330

GRAND TOTAL 292,311,830

Jakarta, 20 Oktober 2020