NO ITEM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH KETERANGAN

I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 lsn 5,000,000.00 5,000,000.00
2 Pembersihan lahan kerja 288.00 m2 19,200.00 5,529,600.00
3 Pek. Bouwplank 168.00 m2 92,000.00 15,456,000.00
SUB JUMLAH I 25,985,600.00
II PEKERJAAN TANAH DAN GALIAN
1 Galian tanah pondasi Footplat (600x600x250) 6.14 m3 94,100.00 578,150.40
2 Urugan tanah kembali 4.92 m3 31,300.00 153,845.76
3 Buang tanah 1.23 m3 41,200.00 50,626.56
4 Pek. Galian tanah saluran lebar 50cm, T=25 cm 8.05 m3 94,100.00 757,505.00
SUB JUMLAH II 1,540,127.72
III PEKERJAAN PONDASI DAN BETON
1 Pek. Pengecoran Pondasi Foot Plat K-225 2.16 m3 1,140,200.00 2,462,832.00
Pek. Pembesian Pondasi Foot Plat (Besi Ø-12mm) 306.81 kg 17,800.00 5,461,215.44
Pek. Bekisting Pondasi Foot Plat 14.40 m2 193,100.00 2,780,640.00

2 Pek. Pengecoran Kolom K-225 1.44 m3 1,140,200.00 1,641,888.00


Pek. Pembesian Kolom (Besi Ø-12mm & Besi Ø-8mm) 269.88 kg 17,800.00 4,803,846.91
Pek. Bekisting Kolom 28.80 m2 375,400.00 10,811,520.00

3 Pek. Pengecoran Sloof K-225 6.78 m3 1,140,200.00 7,730,556.00


Pek. Pembesian Sloof (Besi Ø-12mm & Besi Ø-8mm) 1,230.55 kg 17,800.00 21,903,856.36
Pek. Bekisting Sloof (150x200) 113.00 m2 342,000.00 38,646,000.00

SUB JUMLAH III 96,242,354.71


IV PEKERJAAN KONSTRUKSI KAYU
1 Kolom tiang t= 4.4 m (Balok Kayu 10/10 x 400 cm) 1.23 m3 5,967,900.00 7,352,452.80
2 Kolom tiang t= 2.9 m (Balok Kayu 10/10 x 400 cm) 2.24 m3 5,967,900.00 13,368,096.00
3 Gelagar (Balok Kayu 10/10 x 400cm) 3.32 m3 5,967,900.00 19,813,428.00
SUB JUMLAH IV 40,533,976.80
V PEKERJAAN DINDING DAN LANTAI
1 Pek. Lantai (kayu merah) kaso uk.4/6 9.06 m3 5,967,900.00 54,083,496.96
2 Pek. Dinding kaso 4/6 4.02 m3 5,967,900.00 24,012,442.44
SUB JUMLAH V 78,095,939.40
VI PEKERJAAN SALURAN
1 Pek. Pas. Batu Kali 3.22 m3 1,011,200.00 3,256,064.00
2 Saluran Beton Tumbuk (1Pc ; 3Ps ; 5 Kr) l= 50cm x t= 5cm 1.61 m3 177,400.00 285,614.00
SUB JUMLAH VI 3,541,678.00
VII PEKERJAAN LISTRIK
1 Pek. Pemasangan Daya 1300 kwh 1.00 lot 2,600,000.00 2,600,000.00
2 Pas. Titik lampu 17.00 ttk 157,400.00 2,675,800.00
3 Pas. Stop kontak 4.00 ttk 30,000.00 120,000.00
4 Pas. Saklar ganda 4.00 bh 36,200.00 144,800.00
5 Pas. Lampu TL 8.00 bh 77,200.00 617,600.00
6 Pas. Panel MCB 1.00 bh 202,500.00 202,500.00
SUB JUMLAH VII 6,360,700.00
VIII PEKERJAAN ATAP
1 Pek.Kuda-kuda (Kaso 4/6) 3.21 m2 5,967,900.00 19,152,662.11
2 Pek. Atap Asbes (2.4mx1.05m)x4mm 115.00 m2 78,100.00 8,981,500.00
3 Pek. Nok Asbes 14.00 m' 309,400.00 4,331,600.00
4 Pekerjaan Listplank Papan 20x2mm 19.20 m' 98,000.00 1,881,600.00
SUB JUMLAH VIII 32,465,762.11
IX PEKERJAAN PAGAR WIREMESH + RANGKA SIKU
1 Wiremesh M6-150 + Rangka Siku 40x40x4x6m 252.00 m2 74,991.95 18,897,971.40
2 DynaBolt M8 128.00 pcs 17,000.00 2,176,000.00
SUB JUMLAH VIII 21,073,971.40

JUMLAH TOTAL 305,840,110.14